Project Review Comments

Back to List


Project Name
7233 Space Village - Recycling Facility
Description
Facility used for shredding of tires to be shipped out to other facilities that repurpose them into other materials.
Location
Parcels
5417001012 5417001012
Applicant
Geocycle
Samuel Moracco ( samuel.moracco@geocycle.com )
(719) 322-2464
Samuel Moracco ( samuel.moracco@geocycle.com )
(719) 322-2464
File Number
PPR2528
Project Manager
Lacey Dean
Status
Active
Created
6/23/2025 11:01:47 AM

View: Project Documents



Review Comments (30)

Link Agency Comment
View EPC Health Department
10/28/2025 5:52:24 PM
10/28/2025 5:52:24 PM
View Colorado Springs Airport Advisory Commission
10/23/2025 1:59:36 PM
This was reviewed and recommended Action and Requested items were approved by the Airport Advisory Commission on 10/22/2025.

Requested Item:
Airport staff recommends no objection with the following conditions:
• Avigation Easement: An avigation easement is requested or provide proof of previous recording (book/page or reception number). Add avigation easement note to plat.

Action Item:

• FAA Form 7460-1: Based on elevation data and distance to runway, the applicant will need to file Federal Aviation Administration (FAA) Form 7460-1 “Notice of Proposed Construction or Alteration” for any new vertical development at this site, including temporary construction equipment, and provide FAA documentation to the Airport before this item is presented to the Airport Advisory Commission; FAA’s website (https://oeaaa.faa.gov/oeaaa/external/portal.jsp).
10/23/2025 1:59:36 PM
View Colorado Department of Transportation - Pueblo Office
10/22/2025 10:17:18 AM
Please refer to the attached letter for CDOT's comments regarding this development. 10/22/2025 10:17:18 AM
View PCD Project Manager
10/21/2025 5:17:19 PM
V1_Storm Water Management Plan (SWMP)_comments 10/21/2025 5:17:19 PM
View PCD Project Manager
10/21/2025 5:16:59 PM
V1_Storm Water Management Plan (SWMP) Checklist_comments 10/21/2025 5:16:59 PM
View PCD Project Manager
10/21/2025 5:16:40 PM
V1_Site Development Plan_comments 10/21/2025 5:16:40 PM
View PCD Project Manager
10/21/2025 5:16:21 PM
V1_PCM Applicability Form_comments 10/21/2025 5:16:21 PM
View PCD Project Manager
10/21/2025 5:16:05 PM
V1_Lighting Plan_comments 10/21/2025 5:16:05 PM
View PCD Project Manager
10/21/2025 5:15:51 PM
V1_Letter of Intent_comments 10/21/2025 5:15:51 PM
View PCD Project Manager
10/21/2025 5:15:38 PM
V1_Landscape Plan drawings_comments 10/21/2025 5:15:38 PM
View PCD Project Manager
10/21/2025 5:13:35 PM
V1_Grading & Erosion Control (GEC) Plan_comments 10/21/2025 5:13:35 PM
View PCD Project Manager
10/21/2025 5:13:12 PM
V1_Grading & Erosion Control (GEC) Checklist_comments 10/21/2025 5:13:12 PM
View PCD Project Manager
10/21/2025 5:12:57 PM
V1_Floor Plans (24 x 36)_comments 10/21/2025 5:12:57 PM
View PCD Project Manager
10/21/2025 5:12:41 PM
V1_Erosion and Stormwater Quality Control Permit (ESQCP)_comments 10/21/2025 5:12:41 PM
View PCD Project Manager
10/21/2025 5:12:24 PM
V1_Elevation Plans_comments 10/21/2025 5:12:24 PM
View PCD Project Manager
10/21/2025 5:12:00 PM
V1_Drainage Report - Final_comments 10/21/2025 5:12:00 PM
View PCD Project Manager
10/21/2025 5:11:37 PM
V1_Application-Petition Form_comments 10/21/2025 5:11:37 PM
View EPC DPW Development Services - Engineering
10/21/2025 3:58:30 PM
Road Impact Fee Acknowledgement Form 10/21/2025 3:58:30 PM
View EPC DPW Development Services - Engineering
10/21/2025 3:59:11 PM
DPW Review 1. Engineering Comments have been provided on the following documents (to be uploaded by Project Manager):

- Application
- Drainage Report
- Grading & Erosion Control Plan
- Letter of Intent
- Site Development Plan

The EPC road impact fee acknowledgement form has been provided to be filled out. This will replace the general statement provided. This is a new form the county is requesting for site development plans. Please reach out to engineering staff if you have any questions regarding the form. Note Fees for Office is $3,340 per 1000sf and Industrial is $2648 per 1000 sf. Any other land uses can be found in the Road Impact Fee resolution on the county website.

Reviewed by:

Jalal Saleh, PE
jalalsaleh@elpasoco.com

Charlene Durham, PE
charlenedurham@elpasoco.com
10/21/2025 3:59:11 PM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/21/2025 9:15:21 AM
Please address the following comments for gas and electric service lines.

Action Item: Gas and electric meter locations on plan view and building elevations must be shown and labeled.
Show conceptual location of transformers for CSU Electric Field Engineering to review for clearances.

Action Item: Add note " Gas meters must be a minimum of 3-feet from doors, operable windows, or any vents or openings in walls."

Action Item: Add note “CSU Field Engineer to determine final gas/electric meter, transformer, and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions.”

Action Item: Add note “Knox padlock on gate to provide access to Colorado Springs Utility Department”

Action Item: Add note “Fencing shall not stop access to utility lines or conflict with utility equipment.”
10/21/2025 9:15:21 AM
PCD Project Manager
10/21/2025 5:02:05 PM
Review 1: EPC Planning Division has comments in green text boxes on the following documents.

- Application/Petition Form
- Letter of Intent
- Site Development Plan
- Lighting Plan
- Landscape Plan Drawings

Reviewed by:
Lacey Dean, Associate Planner
laceydean2@elpasoco.com
10/21/2025 5:02:05 PM
EPC Fire and Wildfire Program Manager
10/17/2025 9:14:33 AM
Provide the fire flow at 20psi. The fire flow shall be adequate for the hazard and determined through a nationally recognized standard. Cimmaron Hills has adopted the 2015 International Fire Code and is applicable to this application.

Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
rolandpeterson@elpasoco.com
10/17/2025 9:14:33 AM
EPC DPW Stormwater
10/21/2025 4:54:07 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- Drainage Report
- ESQCP
- GEC Checklist
- GEC Plan
- PCM Applicability Form
- SWMP
- SWMP Checklist

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com

Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
10/21/2025 4:54:07 PM
Colorado Springs Public Works
10/13/2025 11:59:24 AM
EDRD Review Comments:

1. Please limit the proposed access points along Space Village Ave to a maximum width of 36 feet.
2. Please confirm that the proposed access along Space Village Ave is aligned with the existing access at 7230 Space Village Ave.
3. If gates are proposed at any site access, they must be set back a minimum of 50 feet from the flow line and provide adequate turnaround space for U-turning vehicles.
4. Please label the proposed curb and gutter (C&G) with the type specified and ensure it complies with current City standards.
5. Please label the proposed sidewalk with the type (e.g., 5-ft detached or 6-ft attached) and ensure it meets current City standards.
6. Construction drawings for public improvements, along with financial assurance, will be required prior to construction.

Reviewed by Hao Vo, P.E.
hao.vo@coloradosprings.gov
10/13/2025 11:59:24 AM
Colorado Springs Public Works
10/13/2025 9:28:05 AM
1- Please limit the proposed access points along Space Village Ave to a maximum of 36 feet wide.
2- Please confirm that the proposed along Space Village Ave is aligned with 7230 Space Village Ave exiting access.
3- If gates are proposed at any site access, then gates will need to be spaced at a minimum of 50 feet from the flow line and provide a turnaround width for U-turn vehicles.
4- Please show and callout "on the Development Plan" the speed line of sight with the adequate sight distance length (footage) for the proposed access points along Space Village Ave
5- The developer will be responsible to extend the striping for the two-way left-turn lane (center lane) to the site eastern property line.
6- The developer will be responsible to construct an east bound right turn deceleration lane at proposed site access.
7- The details of the signing and striping of the future public roadway improvements will be addressed during the construction plans review.

Zaker Alazzeh, P.E.
Traffic Engineering Manager/Deputy City Traffic Engineer
City of Colorado Springs
(719) 385-5468
Zaker.Alazzeh@coloradosprings.gov
10/13/2025 9:28:05 AM
View EPC Environmental Services
10/10/2025 9:46:36 AM
10/10/2025 9:46:36 AM
EPC Parks Department
10/8/2025 3:30:11 PM
El Paso County Parks Department Comment:

The 2022 El Paso County Parks Master Plan does not show impacts to any COUNTY-OWNED parks, trails, or open space.

However, there is a proposed City of Colorado Springs trail known as the East Fork Sand Creek Trail which is located on the subject parcel. It is recommended that the applicant should contact Emily Duncan (Emily.Duncan@coloradosprings.gov) or Constance Schmeisser (Constance.Schmeisser@coloradosprings.gov) at City Parks for their input on this project. EPC Parks has no objections to this Site Development Plan.

Thank you!

Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
Office: 719.520.6999
10/8/2025 3:30:11 PM
Upper Black Squirrel Creek GWMD
10/8/2025 2:17:39 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. 10/8/2025 2:17:39 PM
Pikes Peak Regional Building Department
10/8/2025 10:41:32 AM
1.Office will retain the address of 7233 Space Center Ave, shop 7235, Meeting room 7237, Breakroom 7229 Space Center Ave
2. The fencing does not meet the requirement based on height to have an address assigned and separate permit issued.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
10/8/2025 10:41:32 AM
911 Authority - El Paso/Teller County
10/7/2025 10:15:47 AM
No action for E911 on this submittal.
Thank you.
Justin
10/7/2025 10:15:47 AM