- Project Name
- T-Mobile Stealth Tower Co-Locate
- Description
- The tower is approved through AL2116. This request is for T-Mobile to add equipment to the tower.
- Location
- Parcels
- 5136401040 5136401040
- Applicant
-
Rich Kotite
Rich Kotite ( rkotite@pbmws.com )
(641) 233-8798 Rich Kotite ( rkotite@pbmws.com )
(641) 233-8798 - File Number
- TWR257
- Project Manager
- Miranda Benson
- Status
- Closed
- Created
- 2/25/2025 3:31:20 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
3/21/2025 8:33:09 AM |
V1_ Planning review completed. No revisions or correction needed. No change to tower height (95') or footprint of lease area. No change to lighting, parking, or landscaping. Site plan packet was sent to PCD Planning Manager for stamp of approval 3/20/2025. Approval is contingent on compliance with PPRBD and Falcon FPD review comments. The applicant is to finalize co-location lease agreement prior to installation. Stamped approval will be uploaded to EDARP once received. Please include the stamped plan when uploading to PPRBD for building permit. Thank you, Miranda Benson mirandabenson2@elpasoco.com |
3/21/2025 8:33:09 AM | |
EPC Stormwater Review
3/11/2025 3:17:16 PM |
Review 1: EPC DPW Stormwater has no comments. The project will not disturb more than 1 ac of soil. Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
3/11/2025 3:17:16 PM | |
Mountain View Electric Association, Inc.
3/10/2025 1:31:31 PM |
MVEA has no objection to the tower modifications. No changes to the tower height or expansion of equipment space/compound are proposed. | 3/10/2025 1:31:31 PM | |
View |
Falcon Fire Protection District
3/10/2025 12:06:10 PM |
3/10/2025 12:06:10 PM | |
PCD Engineering Division
3/7/2025 8:57:51 AM |
There are no comments relating to drainage or transportation. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
3/7/2025 8:57:51 AM | |
Meadow Lake Airport Association
3/5/2025 1:21:32 PM |
Site appears to be outside the Meadow Lake Airport traffic pattern and height is below navigation concerns. | 3/5/2025 1:21:32 PM | |
Pikes Peak Regional Building Department
3/5/2025 10:24:53 AM |
The address for T-Mobile’s new cell site will be 14540 N Meridian Road “C”, when submitting plans for permit, please be sure to submit under the Suite/Unit C and add “C” to the plans where the address is shown. No further comments. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
3/5/2025 10:24:53 AM | |
911 Authority - El Paso/Teller County
3/4/2025 11:50:14 AM |
No action for E911 on this submittal. Thank you. Justin |
3/4/2025 11:50:14 AM |