Project Review Comments

Back to List


File Number
SF2517
Project Name
River Bend Residential Final Plat Filing No. 1 (Updated 2025)
Description
See previous file approvals SP187, SF1844, and SF1843.
Parcels
6514100033 6514100033 6514100034 6514100034
Applicant
Avatar Riverbend LP
Alan Toth ( atoth@avatarequities.com )
(516) 570-7575
Alan Toth ( atoth@avatarequities.com )
(516) 570-7575
EA Number
EA2513
File Number
SF2517
Project Manager
Kylie Bagley
Status
Active
Created
2/19/2025 10:08:00 AM

View: Project Documents



Review Comments (29)

Link Agency Review # Comment
View PCD Project Manager
12/5/2025 1:37:52 PM
2 SIA Redlines 12/5/2025 1:37:52 PM
View PCD Project Manager
12/5/2025 1:37:22 PM
2 O & M Redlines 12/5/2025 1:37:22 PM
View PCD Project Manager
12/5/2025 1:36:53 PM
2 Final Plat Redlines 12/5/2025 1:36:53 PM
View PCD Project Manager
12/5/2025 1:35:26 PM
2 Construction Plans 12/5/2025 1:35:26 PM
View PCD Engineering Division
12/5/2025 1:18:38 PM
2 FAE comments 12/5/2025 1:18:38 PM
View PCD Engineering Division
12/5/2025 1:17:42 PM
2 Final plat comments 12/5/2025 1:17:42 PM
View PCD Engineering Division
12/5/2025 1:17:20 PM
2 PCM Maintenance Agreement comments 12/5/2025 1:17:20 PM
View PCD Engineering Division
12/5/2025 1:16:57 PM
2 Utility Cd's comments 12/5/2025 1:16:57 PM
View PCD Engineering Division
12/5/2025 1:15:53 PM
2 Construction Drawings comments 12/5/2025 1:15:53 PM
View PCD Engineering Division
12/5/2025 1:15:11 PM
2 Final Drainage Report comments 12/5/2025 1:15:11 PM
PCD Engineering Division
12/5/2025 1:18:14 PM
2 Review 2 comments on the following documents will be uploaded:
-Final Drainage Report
-Construction Drawings
-Utility CD's

-PCM maintenance Agreement (see stormwater engineers comment)
-Final Plat (see Stormwater engineers comment)
-FAE (see stormwater engineers comment)


Please update County Engineers signature block to indicate his full name on all engineering documents: Joshua J. Palmer.

Please submit a license agreement for the street lights and private storm pipes within the ROW.


reviewed by:
Daniel Torres
danieltorres@elpasoco.com
12/5/2025 1:18:14 PM
PCD Project Manager
12/5/2025 1:36:29 PM
2 no further planning comments. Additional comments from the City of Fountain are included below:

- Construction plans
- Final Plat
- O&M Manual
- Pond Maintenance (Include Exhibits)
-SIA
12/5/2025 1:36:29 PM
View County Attorney - Development Review
12/2/2025 4:39:00 PM
2 My signature to SIA is attached.

With respect to the DMA, unless a reason is provided, I recommend that the previously approved DMA be used.

Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
12/2/2025 4:39:00 PM
EPC Stormwater Review
12/2/2025 11:42:34 AM
2 Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following documents (to be uploaded by Daniel, once he finishes his review):
- CDs
- Drainage Report
- FAE
- PCM Maintenance Agreement
- Plat

EPC DPW Stormwater comments have been resolved on the following document(s):
- ESQCP
- GEC Plan
- Letter of Intent
- PCM Applicability Form
- PCM O&M Manual
- SWMP

Please provide the following document(s) upon resubmittal (the planner will need to send an upload request):
- PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal)
Review #2 update to this request: you uploaded the Notice of Intent form itself. But what we need is just a PDF of the email chain showing that you emailed the form to the State and that they received it.

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
12/2/2025 11:42:34 AM
PCD Project Manager
6/27/2025 7:42:28 AM
1 Minor comments on letter of intent. Please update to reflect current Final Plat application, not previously approved applications. 6/27/2025 7:42:28 AM
View PCD Engineering Division
6/26/2025 4:13:11 PM
1 O&M stormwater comments 6/26/2025 4:13:11 PM
View PCD Engineering Division
6/26/2025 4:12:40 PM
1 SWMP_stormwater comments 6/26/2025 4:12:40 PM
View PCD Engineering Division
6/26/2025 4:12:08 PM
1 PCM Applicability Form_stormwater comments 6/26/2025 4:12:08 PM
View PCD Engineering Division
6/26/2025 4:11:22 PM
1 GEC Plan comments 6/26/2025 4:11:22 PM
View PCD Engineering Division
6/26/2025 4:11:01 PM
1 ESQCP stormwater comments 6/26/2025 4:11:01 PM
View PCD Engineering Division
6/26/2025 4:10:30 PM
1 Letter of Intent Comments 6/26/2025 4:10:30 PM
View PCD Engineering Division
6/26/2025 4:10:05 PM
1 TIS comments 6/26/2025 4:10:05 PM
View PCD Engineering Division
6/26/2025 4:09:46 PM
1 Utility CD's comment 6/26/2025 4:09:46 PM
View PCD Engineering Division
6/26/2025 4:09:19 PM
1 FAE comments 6/26/2025 4:09:19 PM
View PCD Engineering Division
6/26/2025 4:09:01 PM
1 Construction Drawing comments 6/26/2025 4:09:01 PM
View PCD Engineering Division
6/26/2025 4:04:08 PM
1 Final Drainage Report comments 6/26/2025 4:04:08 PM
View PCD Engineering Division
6/26/2025 4:14:28 PM
1 Review 1 comments on the following documents will be uploaded:
-Final Drainage Report
-Construction Drawings
-FAE
-Utility CD's
-TIS
-Letter of Intent

Please submit a license agreement for the street lights and private storm pipes within the ROW. See attached template.


reviewed by:
Daniel Torres
danieltorres@elpasoco.com
6/26/2025 4:14:28 PM
View County Attorney - Development Review
6/25/2025 9:50:03 AM
1 See edits to attached SIA.

The Detention Basin Maintenance Agreement was approved by the Board in connection with the previous final plat application. The Agreement needs to be separated from the resolution and staff memo and recorded as a stand-alone document along with this plat.

Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
6/25/2025 9:50:03 AM
EPC Stormwater Review
6/25/2025 3:25:32 PM
1 Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents (All docs to be uploaded by Project Manager):
- CDs
- Drainage Report
- ESQCP
- FAE
- GEC Plan
- PCM Applicability Form
- SWMP
- PCM O&M Manual
- Letter of Intent

Please provide the following document(s) upon resubmittal (the planner will need to send an upload request):
- PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal)
- PCM - MHFD Detention Calcs or SDI Form
- PCM Maintenance Agreement

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
6/25/2025 3:25:32 PM