Project Review Comments
- Project Name
- Flying Horse North Clubhouse
- Description
- Site Development Plan for the Flying Horse North Clubhouse
- Location
- Parcels
- 6136000006 6136000006
- Applicant
-
HR Green Inc.
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430 Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430 - File Number
- PPR259
- Project Manager
- Lacey Dean
- Status
- Active
- Created
- 2/13/2025 8:52:17 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Project Manager
3/26/2025 4:59:29 PM |
V1_Site Development Plan_comments | 3/26/2025 4:59:29 PM |
View |
PCD Project Manager
3/26/2025 4:59:15 PM |
V1_Landscape Plan drawings_comments | 3/26/2025 4:59:15 PM |
View |
PCD Project Manager
3/26/2025 4:59:01 PM |
V1_Lighting Plan_comments | 3/26/2025 4:59:01 PM |
View |
PCD Project Manager
3/26/2025 4:58:44 PM |
V1_Letter of Intent_comments | 3/26/2025 4:58:44 PM |
View |
PCD Project Manager
3/26/2025 4:58:30 PM |
V1_Application-Petition Form_comments | 3/26/2025 4:58:30 PM |
PCD Project Manager
3/26/2025 4:58:02 PM |
Review 1: EPC Planning Division has comments in green boxes on the following documents: - Application-Petition Form - Letter of Intent - Lighting Plan - Landscape Plan Drawings - Site Development Plan Reviewed by: Lacey Dean, Associate Planner laceydean2@elpasoco.com |
3/26/2025 4:58:02 PM | |
View |
PCD Engineering Division
3/26/2025 4:30:03 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents. FDR_V1 not submitted. To be reviewed with next submission. ESQCP_V1 not submitted. To be reviewed with next submission. FAE_V1 Use 2025 form not submitted. To be reviewed with next submission. GEC Plan_V1 not submitted. To be reviewed with next submission. DMA- An updated Detention Basin Agreement will be required to be submitted. To be reviewed with next submission. Access permits are required for golf cart access point and the new main entrance. Submit prior to SDP approval EPC Road Impact fees are applicable. See Comments on LOI Fees not paid for PPR2043 improvements SDP_V1 See comments LOI_V1 See comments Ensure cistern is added to the FAE Please ensure SDP is sync with the FHN Fil#3 Allen Ranch Rd design EPC Standard signature blocks are attached Thank you Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
3/26/2025 4:30:03 PM |
EPC Stormwater Review
3/24/2025 2:58:48 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s): - Site Development Plan....(to be uploaded with Development Services comments) The applicant stated in their submitted docs that all SW-related docs (including FDR) will not be submitted until the 2nd submittal. So there was nothing else for me to review now besides the SDP. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
3/24/2025 2:58:48 PM | |
View |
Mountain View Electric Association, Inc.
3/18/2025 11:30:08 AM |
See attached comments | 3/18/2025 11:30:08 AM |
Pikes Peak Regional Building Department
3/18/2025 10:43:56 AM |
1. The new clubhouse will retain the address of the existing clubhouse, 15268 Allen Ranch Rd. 2. Please notify Enumerations when the existing temp set has been removed. We will not approve plans until we are notified that the existing structure has been removed. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
3/18/2025 10:43:56 AM | |
Academy SD 20 Building Fund
3/10/2025 9:02:46 AM |
Academy District 20 is in receipt of File #PPR259 for approval of the Flying Horse North Clubhouse. The District has no comment regarding this request. If you need additional information, please contact me. Don Smith Planning Consultant |
3/10/2025 9:02:46 AM |