Glen Aspen Dam Access Roads
Description
The City of Woodland Park City is constructing an off-line reservoir at Glen Aspen Ranch, in El Paso County. The land is owned by the Scouts of America. The City will construct primary and secondary access roads to access the reservoir.
Location
11050 Loy Creek Rd, Woodland Park
Parcels
8200000060 8200000060 8200000064 8200000064
Applicant
RESPEC - JDS-Hydro Consultants, Inc.
Kelly Bivens ( kelly.bivens@respec.com )
(719) 402-0022 x1439
Kelly Bivens ( kelly.bivens@respec.com )
(719) 402-0022 x1439
EA Number
EA258
File Number
CDR2512
Project Manager
Daniel Torres
Status
Active
Created
2/5/2025 3:11:08 PM

View: Project Documents



Review Comments (12)

Link Agency Comment
View EPC Stormwater Review
11/18/2025 5:30:19 PM
SWMP Checklist 11/18/2025 5:30:19 PM
View EPC Stormwater Review
11/18/2025 5:29:57 PM
SWMP 11/18/2025 5:29:57 PM
View EPC Stormwater Review
11/18/2025 5:29:28 PM
PCM Applicability Form 11/18/2025 5:29:28 PM
View EPC Stormwater Review
11/18/2025 5:29:05 PM
GEC Checklist 11/18/2025 5:29:05 PM
View EPC Stormwater Review
11/18/2025 5:28:48 PM
GEC Plan 11/18/2025 5:28:48 PM
View EPC Stormwater Review
11/18/2025 5:28:19 PM
FAE Comments 11/18/2025 5:28:19 PM
View EPC Stormwater Review
11/18/2025 5:28:03 PM
ESQCP Comments 11/18/2025 5:28:03 PM
View EPC Stormwater Review
11/18/2025 5:27:07 PM
Drainage Report Comments 11/18/2025 5:27:07 PM
View PCD Engineering Division
11/18/2025 4:42:54 PM
Letter of Intent comments 11/18/2025 4:42:54 PM
PCD Engineering Division
11/18/2025 4:42:30 PM
Review 1.

Engineering comments on the following documents:
- Letter of Intent
- Drainage Report ...................to be uploaded by Stormwater Engineering
- GEC Plan ..............................to be uploaded by Stormwater Engineering
- FAE .......................................to be uploaded by Stormwater Engineering

Due to the volume and nature of comments, additional comments may be expected on the next review. Project Manager, please provide a 21-day review period.

Reviewed by:
Joe Sandstrom, EI, Associate Engineer
josephsandstrom@elpasoco.com
(719) 520-6314
11/18/2025 4:42:30 PM
EPC Stormwater Review
11/18/2025 5:24:09 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- Drainage Report
- ESQCP
- FAE
- GEC Plan
- GEC Checklist
- PCM Applicability Form
- SWMP
- SWMP Checklist

Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com

Mikayla Hartford, P.E.
Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
11/18/2025 5:24:09 PM
RBD Floodplain
10/27/2025 12:37:53 PM
site not in the floodplain, no comment 10/27/2025 12:37:53 PM