- Creation of a new commercial lot from an open space tract that was not previously buildable, and did not have a water finding. ( Tract C Filing No 13 to a single Lot). Water sufficiency is required with this new plat
- Location
- Parcels
- 5225208001 5225208001
- Applicant
-
RMG-Architects
Keith Moore ( kmoore@rmg-engineers.com )
(719) 203-3321 Keith Moore ( kmoore@rmg-engineers.com )
(719) 203-3321 - File Number
- ASB2447
- Project Manager
- Stormwater Mikayla Hartford
- Status
- Active
- Created
- 12/12/2024 4:49:42 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
EPC Stormwater Review
1/21/2025 4:54:45 PM |
Review 1: EPC DPW Stormwater has the following comment: Include As-built condition stamp and engineer of record signature on each sheet. Per ECM 5.10.6 Engineering Record Drawings. Even if everything was built exactly per plan, we need an electronic PDF of the original drawings to be signed, dated, and stamped with “As-Built” on each sheet. Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
1/21/2025 4:54:45 PM | |
View |
PCD Engineering Inspections
1/21/2025 4:30:51 PM |
Road Certification Letter Comments | 1/21/2025 4:30:51 PM |
View |
PCD Engineering Inspections
1/21/2025 4:30:21 PM |
As-Built Comments | 1/21/2025 4:30:21 PM |
PCD Engineering Inspections
1/21/2025 4:20:13 PM |
See comments on both the as-built sheet and the road certification letter. | 1/21/2025 4:20:13 PM |