Project Review Comments
- Project Name
- PTAA Addition No. 1 - Annexation Impact Report
- Description
- Please see the attached annexation impact report. This site will be presented to the Colorado Springs City Council on November 12, 2024. The expected BoCC presentation will be October 24, 2024.
- Location
- 5321001008 5321001009
- Parcels
- 5321001008 5321001008 5321001009 5321001009
- Applicant
-
City of Colorado Springs
Gabe Sevigny ( gabe.sevigny@coloradosprings.gov )
(719) 385-5088 Gabe Sevigny ( gabe.sevigny@coloradosprings.gov )
(719) 385-5088 - File Number
- ANX2410
- Project Manager
- Joe Letke
- Status
- Closed
- Created
- 9/16/2024 12:05:47 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
9/23/2024 9:14:10 AM |
Due to the size of the annexation, an annexation impact report will be presented before the Board of County Commissioners. Joe Letke Planner 719-520-7964 |
9/23/2024 9:14:10 AM | |
PCD Engineering Division
9/21/2024 10:35:04 PM |
Development of the proposed annexation area will result in impacts to County roadway infrastructure. The condition and adequacy of the County roads serving the annexation area will need to be addressed and improvements as appropriate to mitigate traffic impacts shall be provided. El Paso County recommends annexation of Huber Road and Tamlin Road. reviewed by: Daniel Torres danieltorres@elpasoco.com 719-520-6305 |
9/21/2024 10:35:04 PM | |
EPC Stormwater Review
9/17/2024 10:10:59 AM |
EPC SW has no comments | 9/17/2024 10:10:59 AM |