Project Review Comments
- Project Name
- Bent Grass East - Carubia's Dental Office Building
- Description
- The proposed project will consist of +/- 6,400 square foot one-story building for a pediatric dental and orthodontics office project. The building will be situated in north-east corner of parcel. The site will contain +/- 40 parking spaces and a trash enclosure.
- Location
- Parcels
- 5301104005 5301104005
- Applicant
-
Battista Design Group
Paul Battista ( paul@battistadesign.net )
(303) 428-4895 Paul Battista ( paul@battistadesign.net )
(303) 428-4895 - EA Number
- EA2497
- File Number
- PPR256
- Project Manager
- Lacey Dean
- Status
- Active
- Created
- 8/26/2024 11:21:24 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
County Attorney - Development Review
5/6/2025 11:31:22 AM |
The recently uploaded and signed DMA does not incorporate the changes to the document that our office submitted on 4/17/25. Please accept the track changes from 4/17, sign the document, and submit a PDF version including exhibits. I will then sign the updated version. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com. |
5/6/2025 11:31:22 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/30/2025 11:27:08 AM |
Thank you for the resubmittal, all CSU comments have been addressed for PPR256. | 4/30/2025 11:27:08 AM | |
View |
County Attorney - Development Review
4/17/2025 5:40:53 PM |
See edits to attached DMA. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com |
4/17/2025 5:40:53 PM |
View |
PCD Project Manager
4/17/2025 4:44:22 PM |
V2_Traffic Impact Study_comments | 4/17/2025 4:44:22 PM |
View |
PCD Project Manager
4/17/2025 4:43:50 PM |
V2_Grading & Erosion Control Plan_comments | 4/17/2025 4:43:50 PM |
View |
PCD Project Manager
4/17/2025 4:42:52 PM |
V2_Grading & Erosion Control checklist_comments | 4/17/2025 4:42:52 PM |
View |
PCD Project Manager
4/17/2025 4:42:25 PM |
V2_Financial Assurance Forms_comments | 4/17/2025 4:42:25 PM |
View |
PCD Project Manager
4/17/2025 4:42:01 PM |
V2_drainage letter_comments | 4/17/2025 4:42:01 PM |
View |
PCD Project Manager
4/17/2025 4:41:21 PM |
V2_Detention Maintenance Agreement_comments | 4/17/2025 4:41:21 PM |
View |
PCD Project Manager
4/17/2025 4:39:54 PM |
V2_Civil CDs_comments | 4/17/2025 4:39:54 PM |
PCD Engineering Division
4/17/2025 9:54:37 AM |
DPW Engineering review 2 has comments on the following documents - Drainage Letter - Traffic Impact Study - Financial Assurance Forms - Construction Drawings Engineering comments have been addressed on the following document: - Letter of Intent Review by: Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
4/17/2025 9:54:37 AM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
4/15/2025 8:25:44 AM |
CSU has two (2) remaining comments to be addressed. Please see sheet 5 of 9 Exterior Elevations. Please have the applicant show the dimension between the window and gas meter. Appears to not met the minimum 3-foot required separation. Please have the applicant add the note shown to this sheet as well. | 4/15/2025 8:25:44 AM |
PCD Project Manager
4/14/2025 12:20:36 PM |
Review 2: EPC Planning Division comments have been resolved. Planning has no further comments. Reviewed by: Lacey Dean, Associate Planner laceydean2@elpasoco.com |
4/14/2025 12:20:36 PM | |
EPC Stormwater Review
4/15/2025 4:46:24 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following documents (to be uploaded by the PM): - CDs - Detention Maintenance Agreement - Drainage Letter - FAE - GEC Plan - GEC Checklist EPC DPW Stormwater comments have been resolved on the following document(s): - ESQCP - Landscape Plan - PBMP Applicability Form - SWMP - SWMP Checklist Reviewed by: Glenn Reese, P.E. Stormwater Engineer III 719.675.2654 GlennReese@elpasoco.com |
4/15/2025 4:46:24 PM | |
Falcon Fire Protection District
4/9/2025 7:34:46 AM |
Thank you for adding the Fire Access Plan-approved. No other comments to add to the initial comments from 02/25/2025. Curtis L. Kauffman Fire Prevention Division Lieutenant/Fire Inspector II |
4/9/2025 7:34:46 AM | |
View |
EPC Health Department
3/14/2025 2:21:11 PM |
3/14/2025 2:21:11 PM | |
View |
Mountain View Electric Association, Inc.
3/10/2025 11:07:48 AM |
See attached comments | 3/10/2025 11:07:48 AM |
Upper Black Squirrel Creek GWMD
3/4/2025 10:23:46 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. | 3/4/2025 10:23:46 PM | |
View |
PCD Project Manager
3/4/2025 6:47:09 PM |
V1_Traffic Impact Study_comments | 3/4/2025 6:47:09 PM |
View |
PCD Project Manager
3/4/2025 6:46:07 PM |
V1_Financial Assurance Forms_comments | 3/4/2025 6:46:07 PM |
View |
PCD Project Manager
3/4/2025 6:45:18 PM |
V1_Drainage Letter_comments | 3/4/2025 6:45:18 PM |
View |
PCD Project Manager
3/4/2025 6:43:59 PM |
V1_Parking plan_comments | 3/4/2025 6:43:59 PM |
View |
PCD Project Manager
3/4/2025 6:43:20 PM |
V1_Lighting Plan_comments | 3/4/2025 6:43:20 PM |
View |
PCD Project Manager
3/4/2025 6:42:25 PM |
V1_Letter of Intent_comments | 3/4/2025 6:42:25 PM |
View |
PCD Project Manager
3/4/2025 6:41:41 PM |
V1_Landscape Plan Drawings_comments | 3/4/2025 6:41:41 PM |
View |
PCD Project Manager
3/4/2025 6:40:57 PM |
V1_Site Development Plan_comments | 3/4/2025 6:40:57 PM |
PCD Project Manager
3/4/2025 6:39:33 PM |
Review 1: EPC Planning Division has comments (in green boxes) on the following documents - Site Development Plan - Landscape Plan Drawings - Letter of Intent - Parking Plan - Lighting Plan Reviewed by: Lacey Dean, Associate Planner laceydean2@elpasoco.com |
3/4/2025 6:39:33 PM | |
PCD Engineering Division
3/4/2025 1:46:31 PM |
DPW Engineering review 1 has comments on the following documents - Letter of Intent - Drainage Letter - Traffic Impact Study - Financial Assurance Forms Review by: Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
3/4/2025 1:46:31 PM | |
View |
EPC Stormwater Review
3/4/2025 11:28:55 AM |
SWMP Checklist | 3/4/2025 11:28:55 AM |
View |
EPC Stormwater Review
3/4/2025 11:28:42 AM |
SWMP | 3/4/2025 11:28:42 AM |
View |
EPC Stormwater Review
3/4/2025 11:28:27 AM |
PBMP Applicability Form | 3/4/2025 11:28:27 AM |
View |
EPC Stormwater Review
3/4/2025 11:28:10 AM |
GEC Checklist | 3/4/2025 11:28:10 AM |
View |
EPC Stormwater Review
3/4/2025 11:27:56 AM |
GEC Plan | 3/4/2025 11:27:56 AM |
View |
EPC Stormwater Review
3/4/2025 11:27:40 AM |
ESQCP | 3/4/2025 11:27:40 AM |
EPC Stormwater Review
3/4/2025 11:23:28 AM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - Drainage Letter.......(to be uploaded with Development Services comments) - ESQCP - FAE........................(to be uploaded with Development Services comments) - GEC Plan - GEC Checklist - Landscape Plan....(to be uploaded with Development Services comments) - PBMP Applicability Form - SWMP - SWMP Checklist Please provide the following document(s) upon resubmittal (the planner will need to send an upload request): - Detention Maintenance Agreement - MHFD Detention Calcs or SDI Form (actually not needed if the SFB is just for WQ treatment only, not detention. But this is currently not clear from FDR). - PBMP O&M Manual Reviewed by: Glenn Reese, P.E. Stormwater Engineer III 719.675.2654 GlennReese@elpasoco.com |
3/4/2025 11:23:28 AM | |
Falcon School District 49
3/4/2025 7:22:32 AM |
District 49 has no comment at this time. | 3/4/2025 7:22:32 AM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/28/2025 1:47:01 PM |
Good afternoon Lacey, CSU has three (3) comments to be addressed for PPR256. 1.Action Item: Gas and electric meter locations on plan view and building elevations must be shown and labeled. 2.Action Item: Add note " Gas meters must be a minimum of 3-feet from doors, operable windows, or any vents or openings in walls." 3.Action Item: Add note “CSU Field Engineer to determine final gas meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) with any questions.” Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Colorado Springs Utilities | Utilities Development Services 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
2/28/2025 1:47:01 PM |
View |
Falcon Fire Protection District
2/25/2025 1:08:48 PM |
2/25/2025 1:08:48 PM | |
Woodmen Hills Metro
2/25/2025 8:28:55 AM |
Need a water and wastewater commitment letter from Woodmen Hills Metropolitan District, water resource report and wastewater disposal report from WHMD, and a set of sites and building plans. | 2/25/2025 8:28:55 AM | |
Pikes Peak Regional Building Department
2/24/2025 9:41:10 AM |
Enumerations has the following comments: 1. It is unclear to me whether or not this is intended to be a multi-tenant building. If it is, any building plans submitted for permit must show secondary addressing which follows the RBD secondary addressing guidelines, available on our website. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
2/24/2025 9:41:10 AM | |
Bent Grass Metro
2/19/2025 11:32:11 AM |
This proposed project is located within the Bent Grass Metropolitan District boundaries. The District assesses platting and building permit fees for new development within the District Boundaries, the District also assess’ a mill levy on property within the District Boundaries. The fees for this year are as follows: Traffic Signal Fee: Commercial - $10,000/ acre Residential - $1,000/ acre Platting Fees: A. Commercial: $5500/acre B. Residential: $5500/acre Building Permit Fees: A. Commercial (Industrial/Other non-residential) $1.00/square foot B. Residential 1. Single Family: $500/unit 2. Multi Family: $350/unit |
2/19/2025 11:32:11 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/19/2025 10:45:49 AM |
TSN should be 5301104005 - 8059 MERIDIAN PARK DR - tk | 2/19/2025 10:45:49 AM | |
Colorado Department of Transportation - Pueblo Office
2/18/2025 10:55:39 AM |
We are in receipt of the above-referenced development submittal. After review of the provided documents, CDOT Staff currently has NO COMMENT pertaining to this submittal. | 2/18/2025 10:55:39 AM | |
Woodmen Road Metro
2/18/2025 10:44:09 AM |
This proposed project is located within the Woodmen Road Metropolitan District boundaries. The District assesses platting and building permit fees for new development within its Boundaries. The fees for this year are as follows: Platting Fees: Commercial: $1540/acre Residential: $385.00/lot Building Permit Fees: Commercial: Destination retail/hotel: $1.37/square foot Convenience Commercial: $5.51/Sq Ft All Other Uses: $1.10/square foot Residential: Single Family- $550/UNIT Multi Family- $385/UNIT |
2/18/2025 10:44:09 AM |