- City of Fountain Project #: PP-24-003 The owner requests to replat the previous one lot into 4 lots, in order to accommodate a planned commercial retail development area with associated parking and access. The amount of land within the developable area (outside of the no-build area) has not changed, we simply are requesting to break up the developable area into 4 lots for multiple owners/buildings/tenants.
- Location
- Parcels
- 6504412018 6504412018
- Applicant
-
CIty of Fountain
Planning Supervisor Kristy Martinez ( Kristy@fountaincolorado.org )
(719) 322-2015 Planning Supervisor Kristy Martinez ( Kristy@fountaincolorado.org )
(719) 322-2015 - File Number
- OAR2418
- Project Manager
- Lacey Dean
- Status
- Closed
- Created
- 7/10/2024 8:40:19 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
7/24/2024 5:19:25 PM |
Planning staff recommends providing a buffer between the proposed use and the adjacent residential zoning district to the East Reviewed by: Lacey Dean laceydean2@elpasoco.com |
7/24/2024 5:19:25 PM | |
PCD Engineering Division
7/24/2024 3:06:58 PM |
Review #1: 1. No drainage comments. Develop flows are routed into an existing full spectrum detention pond located within City of Fountain that was sized to accommodate this developments flow per the submitted preliminary drainage report. The project is not anticipated to adversely affect unincorporated EPC properties in the immediate vicinity. 2. No transportation comments. The site is accessed via Venetucci Boulevard which is owned/maintained by City of Fountain. Per the submitted traffic memo, the proposed commercial development will generate significantly less traffic than what was originally planned for this parcel. Reviewed by: Daniel Torres, P.E. danieltorres@elpasoco.com 719-520-6305 |