Project Review Comments

Back to List


Project Name
8140/8150 Cessna Drive Condo Plat
Description
Applicant would like to submit a condominium plat for the newly constructed hangars on the subject property.
Location
Parcels
4304002086 4304002086
Applicant
Ryan Schneider
Ryan Schneider ( ryschneider@gmail.com )
(719) 243-0531
Ryan Schneider ( ryschneider@gmail.com )
(719) 243-0531
File Number
SF2414
Project Manager
Joe Letke
Status
Active
Created
4/5/2024 9:33:56 AM

View: Project Documents



Review Comments (23)

Link Agency Comment
View PCD Engineering Division
11/18/2024 5:28:15 PM
Plat Drawing_V2 11/18/2024 5:28:15 PM
View PCD Engineering Division
11/18/2024 5:27:56 PM
LOI_V2 11/18/2024 5:27:56 PM
PCD Engineering Division
11/18/2024 5:29:52 PM
Engineering Review Ver.2

Engineering Comments have been provided on the following documents:

- Plat Drawing_V2 Reference Plat note concerning DMA
- LOI_V2 Minor comments

Note: The Detention Maintenance Agreement (DMA) that was completed for PPR2138 may have to be resigned as part of the plat recording. County Attorney is reviewing DMA to determine if this is required or if the DMA will convey to the LLC or HOA.

Road Impact fees paid $8541.22 paid under PPR2138
Road Impact fees apply for future to be constructed hangers.

A check of drainage basin fees for Solberg Ranch basin is being reviewed as part of the Condo plat under Appdx L, DCM Vol 1. A follow up email will be sent.

Thank you.

Edward Schoenheit, Engineer
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
11/18/2024 5:29:52 PM
EPC Stormwater Review
11/18/2024 1:53:26 PM
Review 2: All EPC DPW Stormwater comments have been addressed.

Reviewed by:
Christina Prete, P.E.
Stormwater Manager
ChristinaPrete@elpasoco.com
11/18/2024 1:53:26 PM
PCD Project Manager
11/18/2024 10:28:27 AM
Planning has comments on the following documents:

-Letter of Intent
-Plat drawings

Joe Letke
Planner
719-520-7964
11/18/2024 10:28:27 AM
Falcon Fire Protection District
11/14/2024 12:15:22 PM
No changes from Falcon Fire Protection District from my August 12, 2024, comment letter. 11/14/2024 12:15:22 PM
View EPC Health Department
9/10/2024 9:51:50 PM
9/10/2024 9:51:50 PM
USAFA Base Planner
8/19/2024 4:49:43 PM
USAFA has reviewed this application and have found that it will NOT impact USAFA's mission.

We assume that no crane or other tall construction equipment will be utilized when converting the hangars into condominiums. If that is true, USAFA will not have any comment for this project.

Thank you for the opportunity to review this project.
8/19/2024 4:49:43 PM
View PCD Project Manager
8/12/2024 3:13:17 PM
-Plat Drawing 8/12/2024 3:13:17 PM
View PCD Project Manager
8/12/2024 3:13:05 PM
-LOI 8/12/2024 3:13:05 PM
View PCD Project Manager
8/12/2024 3:12:52 PM
-Application Form 8/12/2024 3:12:52 PM
PCD Project Manager
8/12/2024 3:12:30 PM
Planning has comments on the following documents:

-Application Form
-LOI
-Plat Drawings

Joe Letke
Planner
719-520-7964
joeletke@elpasoco.com
8/12/2024 3:12:30 PM
PCD Engineering Division
8/12/2024 2:31:00 PM
Review 1 - EPC Engineering Comments have been provided on the following document:

- Plat Drawings. (To be uploaded by the project manager)

Reviewed by:
Daniel, PE
danieltorres@elpasoco.com

Hao Vo, PE
haovo@elpasoco.com
8/12/2024 2:31:00 PM
View Falcon Fire Protection District
8/12/2024 2:15:46 PM
8/12/2024 2:15:46 PM
EPC Stormwater Review
8/12/2024 1:28:56 PM
Review 1: Show existing stormwater facility and easements on the plat.

Reviewed by:
Christina Prete, P.E.
Stormwater Manager
ChristinaPrete@elpasoco.com
8/12/2024 1:28:56 PM
Upper Black Squirrel Creek GWMD
8/8/2024 4:18:20 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. 8/8/2024 4:18:20 PM
County Attorney - Development Review
8/8/2024 1:52:24 PM
No comments from County Attorney - Development Review at this time. 8/8/2024 1:52:24 PM
PCD Administrative Notice
8/5/2024 4:08:07 PM
On 8/5/2024, PCD mailed combined "Notice of Application" and "Notice of Administrative Determination" letters to surrounding property owners within a 200-foot range (33 addresses). The potential date an administrative decision can be made is 8/19/2024. Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $22.77. MB 8/5/2024 4:08:07 PM
County Attorney - Water
8/2/2024 12:02:17 PM
The County Attorney's Office can complete a Water Review and Recommendation after all documentation required by the Land Development Code Section 8.4.7. 8/2/2024 12:02:17 PM
911 Authority - El Paso/Teller County
7/31/2024 11:54:37 AM
No action for E911 on this submittal.
Thank you.
Justin
7/31/2024 11:54:37 AM
Schriever AFB
7/30/2024 12:11:37 PM
No comment. 7/30/2024 12:11:37 PM
Pikes Peak Regional Building Department
7/30/2024 10:04:40 AM
1. Why are two addresses being used for this plat. There should only be one. The unit numbering is out of order. Should start at 100 not 110.
No further comment.

Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
7/30/2024 10:04:40 AM
Colorado Springs Airport Advisory Commission
7/29/2024 11:11:05 PM
Outside of Airport Overlay. 7/29/2024 11:11:05 PM