Project Review Comments
- Project Name
- Overlook at Homestead Early Grading
- Description
- Early grading for Overlook at Homestead - Preliminary plan for 62 lots; minimum lot size 5 acres (SP238)
- Location
- Parcels
- 4100000255 4100000255 4100000256 4100000256 4122000005 4122000005
- Applicant
-
N.E.S.
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073 Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073 - EA Number
- EA2350
- File Number
- EGP241
- Project Manager
- Kylie Bagley
- Status
- Closed
- Created
- 1/11/2024 11:05:16 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
9/16/2024 5:33:41 PM |
Engineering Review Ver.4 No further engineer comments Please schedule PRECON meeting Thank you. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/16/2024 5:33:41 PM | |
EPC Stormwater Review
9/16/2024 7:03:27 AM |
Review 4: EPC DPW Stormwater comments have been resolved on the following documents: - GEC Plan EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
9/16/2024 7:03:27 AM | |
View |
PCD Engineering Division
9/5/2024 1:26:56 PM |
Drainage Report V3 | 9/5/2024 1:26:56 PM |
View |
PCD Engineering Division
9/5/2024 1:26:16 PM |
GEC_V3 | 9/5/2024 1:26:16 PM |
EPC Stormwater Review
9/5/2024 1:01:48 PM |
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents (to be uploaded by the DS Engineer): - GEC Plan EPC DPW Stormwater comments have been resolved on the following documents: - ESQCP - FAE - GEC Checklist - PBMP Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
9/5/2024 1:01:48 PM | |
PCD Engineering Division
9/5/2024 1:28:44 PM |
Engineering Review Ver.3 Please see engineering comments on the following documents. GEC Plan_V3 Address SW Comment. Please have owner signed the GEC plan FDR_V3 Please address comments. Engineer stamp/sign and owner sign FDR PCD Please program 5-day review. Thank you. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/5/2024 1:28:44 PM | |
View |
EPC Stormwater Review
5/24/2024 5:46:17 PM |
Drainage Report (uploaded for DS Engineers with their comments) | 5/24/2024 5:46:17 PM |
View |
EPC Stormwater Review
5/24/2024 5:42:02 PM |
PBMP | 5/24/2024 5:42:02 PM |
View |
EPC Stormwater Review
5/24/2024 5:37:53 PM |
GEC Checklist | 5/24/2024 5:37:53 PM |
View |
EPC Stormwater Review
5/24/2024 5:37:33 PM |
GEC Plan | 5/24/2024 5:37:33 PM |
View |
EPC Stormwater Review
5/24/2024 5:34:41 PM |
FAE | 5/24/2024 5:34:41 PM |
View |
EPC Stormwater Review
5/24/2024 5:34:27 PM |
ESQCP | 5/24/2024 5:34:27 PM |
PCD Engineering Division
5/23/2024 4:43:53 PM |
Engineering Review Ver.2 Please see engineering comments on the following documents. FDR_V2 Uploaded by SW GEC Plan_V2 Uploaded by SW Please ensure all engineering documents are stamped/dated and signed to include FAE, GEC Plan (all sheets) and Drainage Report Hao Vo Engineer II (haovo@elpasoco.com) Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
5/23/2024 4:43:53 PM | |
EPC Stormwater Review
5/24/2024 5:31:55 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - ESQCP - FAE - GEC Plan - GEC Checklist - PBMP EPC DPW Stormwater comments have been resolved on the following documents: - Drainage Report - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
5/24/2024 5:31:55 PM | |
View |
EPC Stormwater Review
2/22/2024 6:04:40 PM |
GEC Plan | 2/22/2024 6:04:40 PM |
View |
EPC Stormwater Review
2/22/2024 6:02:46 PM |
Drainage Report | 2/22/2024 6:02:46 PM |
View |
EPC Stormwater Review
2/22/2024 6:01:58 PM |
SWMP Checklist | 2/22/2024 6:01:58 PM |
View |
EPC Stormwater Review
2/22/2024 5:31:23 PM |
SWMP | 2/22/2024 5:31:23 PM |
View |
EPC Stormwater Review
2/22/2024 5:28:14 PM |
PBMP | 2/22/2024 5:28:14 PM |
View |
EPC Stormwater Review
2/22/2024 5:27:59 PM |
GEC Checklist | 2/22/2024 5:27:59 PM |
View |
EPC Stormwater Review
2/22/2024 5:27:38 PM |
FAE | 2/22/2024 5:27:38 PM |
View |
EPC Stormwater Review
2/22/2024 5:27:21 PM |
ESQCP | 2/22/2024 5:27:21 PM |
View |
PCD Engineering Division
2/22/2024 4:24:33 PM |
EGP Pre-Subdivision Site Grading Acknowledgement and Right of Access Form_V1 | 2/22/2024 4:24:33 PM |
PCD Engineering Division
2/22/2024 4:22:57 PM |
Engineering Review Ver.1 Please see engineering comments on the following documents. FDR_V1 Uploaded by SW EGP Pre-Subdivision Site Grading Acknowledgement and Right of Access Form_V1 GEC Plan PRELIM_V1 Uploaded by SW FAE_V1 Uploaded by SW Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
2/22/2024 4:22:57 PM | |
EPC Stormwater Review
2/22/2024 6:07:38 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report..........(uploaded with DSD engineering comments) - ESQCP - FAE...........................(uploaded with DSD engineering comments) - GEC Plan....................(uploaded with DSD engineering comments) - GEC Checklist - PBMP - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
2/22/2024 6:07:38 PM |