Project Review Comments
- Project Name
- 2875 E. Las Vegas St. Site Development Plan
- Description
- New warehouse/storage building to previously approved Site Development Plan PPR2333 for storage yard only. Major Site Development required for new principal structure.
- Location
- Parcels
- 6433400016 6433400016
- Applicant
-
DREXEL, BARRELL & CO.
Bison Investments ( bobby@frazeeco.com ) Bison Investments ( bobby@frazeeco.com ) - File Number
- PPR2425
- Project Manager
- Joe Letke
- Status
- Closed
- Created
- 1/10/2024 8:51:39 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
9/3/2024 11:49:19 AM |
Engineering Review Ver.4 No further engineer comments Engineer and Stormwater documents have been approved. Please schedule PRECON as applicable. Road Impact fees are applicable to be paid at time of building permit. Road Impact Class WAREHOUSE 8750sqft https://publicworks.elpasoco.com/road-impact-fees/ Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/3/2024 11:49:19 AM | |
PCD Project Manager
8/29/2024 8:11:30 AM |
Planning has no further comments. The alternative landscape plan has been forwarded to the Planning Manager to review on behalf of the PCD Director. Joe Letke Planner joeletke@elpasoco.com |
8/29/2024 8:11:30 AM | |
EPC Stormwater Review
8/28/2024 8:17:17 AM |
Review 3: EPC DPW Stormwater comments have been resolved on the following documents: - PBMP Applicability Form EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
8/28/2024 8:17:17 AM | |
PCD Engineering Division
8/27/2024 5:51:56 PM |
Engineering Review Ver.3 No further engineer comments Route for approval. Please schedule PRECON as applicable. Road Impact fees are applicable to be paid at time of building permit. Road Impact Class WAREHOUSE 8750sqft https://publicworks.elpasoco.com/road-impact-fees/ Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
8/27/2024 5:51:56 PM | |
View |
EPC Health Department
8/23/2024 5:29:28 PM |
8/23/2024 5:29:28 PM | |
PCD Engineering Division
8/19/2024 5:56:53 PM |
Engineering Review Ver.2 Please see engineering review comments on the following documents: SDP_V1 An update SDP V2 was not submitted for review. Engineer comments addressed on the following: FAE_V2 ESQCP_V2 GEC Plan_V2 PCD Please program 3-day re-review for engineering. Road Impact fees are applicable to be paid at time of building permit. Road Impact Class WAREHOUSE 8750sqft https://publicworks.elpasoco.com/road-impact-fees/ Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
8/19/2024 5:56:53 PM | |
View |
PCD Project Manager
8/19/2024 5:12:34 PM |
-LOI | 8/19/2024 5:12:34 PM |
View |
PCD Project Manager
8/19/2024 5:12:22 PM |
-Landscape Plan | 8/19/2024 5:12:22 PM |
PCD Project Manager
8/19/2024 5:11:48 PM |
Planning has comments on the following documents: -LOI -Landscape plan (Unresolved from v1) Joe Letke Planner joeletke@elpasoco.com |
8/19/2024 5:11:48 PM | |
View |
EPC Stormwater Review
8/19/2024 10:00:04 AM |
PBMP Applicability Form | 8/19/2024 10:00:04 AM |
Pikes Peak Regional Building Department
8/19/2024 8:32:26 AM |
Previous comments still apply. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
8/19/2024 8:32:26 AM | |
EPC Stormwater Review
8/19/2024 9:54:25 AM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - PBMP Applicability Form EPC DPW Stormwater comments have been resolved on the following documents: - ESQCP - FAE - GEC Plan - GEC Checklist - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
8/19/2024 9:54:25 AM | |
View |
PCD Engineering Division
7/30/2024 7:33:47 AM |
PBMP Form | 7/30/2024 7:33:47 AM |
View |
PCD Engineering Division
7/30/2024 7:30:09 AM |
SDP_V1 | 7/30/2024 7:30:09 AM |
View |
PCD Engineering Division
7/30/2024 7:23:11 AM |
ESQCP_V1 | 7/30/2024 7:23:11 AM |
View |
PCD Engineering Division
7/30/2024 7:22:54 AM |
GEC PLAN_V1 | 7/30/2024 7:22:54 AM |
View |
PCD Engineering Division
7/30/2024 7:22:32 AM |
FAE_V1 | 7/30/2024 7:22:32 AM |
View |
PCD Project Manager
7/29/2024 7:35:31 PM |
-LOI | 7/29/2024 7:35:31 PM |
View |
PCD Project Manager
7/29/2024 7:35:13 PM |
-Landscape Plan | 7/29/2024 7:35:13 PM |
View |
PCD Project Manager
7/29/2024 7:34:43 PM |
-Floor Plans | 7/29/2024 7:34:43 PM |
PCD Project Manager
7/29/2024 7:35:51 PM |
Planning has comments on the following documents: -Flood Plans -Landscape Plan -Letter of Intent Additional comments and docs will be uploaded by DPW Engineering. Joe Letke Planner joeletke@elpasoco.com |
7/29/2024 7:35:51 PM | |
PCD Engineering Division
7/30/2024 7:36:01 AM |
Engineering Review Ver.1 Please see engineering review comments on the following documents: FAE_V1 SDP_V1 ESQCP_V1 Please provide updated and corrected form. GEC Plan_V1 PBMP form to be submitted. Road Impact fees are applicable to be paid at time of building permit. Road Impact Class WAREHOUSE 8750sqft https://publicworks.elpasoco.com/road-impact-fees/ Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
7/30/2024 7:36:01 AM | |
Pikes Peak Regional Building Department
7/29/2024 11:09:23 AM |
Enumerations has the following comments: 1. Enumerations has assigned the address of 2825 E. Las Vegas St. for this new commercial building. The plan should be updated to show this address. 2. The address of 2825 E. Las Vegas St. should be used when submitting building plans for permitting. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
7/29/2024 11:09:23 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/29/2024 8:07:16 AM |
CSU UDS does not have any issues with the proposed plan MAR |
7/29/2024 8:07:16 AM | |
County Attorney - Development Review
7/28/2024 3:24:13 PM |
No comments at this time. | 7/28/2024 3:24:13 PM | |
View |
EPC Stormwater Review
7/25/2024 3:16:58 PM |
SWMP Checklist | 7/25/2024 3:16:58 PM |
View |
EPC Stormwater Review
7/25/2024 3:16:35 PM |
SWMP | 7/25/2024 3:16:35 PM |
View |
EPC Stormwater Review
7/25/2024 3:16:14 PM |
GEC Checklist | 7/25/2024 3:16:14 PM |
View |
EPC Stormwater Review
7/25/2024 3:15:41 PM |
ESQCP | 7/25/2024 3:15:41 PM |
EPC Stormwater Review
7/25/2024 3:15:58 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - ESQCP - FAE..........................(to be uploaded with Development Services comments) - GEC Plan.................(to be uploaded with Development Services comments) - GEC Checklist - SWMP - SWMP Checklist Please provide the following documents upon resubmittal (the planner will send an upload request): - PBMP Applicability Form Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
7/25/2024 3:15:58 PM | |
Colorado Springs Planning & Community Development
7/25/2024 11:43:50 AM |
Site has contiguity to the south and east. If water extensions are required/requested, annexation is required. | 7/25/2024 11:43:50 AM | |
View |
El Paso County Conservation Dist
7/23/2024 9:49:48 AM |
Please see attached .PDF for brief comments. Thanks! | 7/23/2024 9:49:48 AM |
911 Authority - El Paso/Teller County
7/16/2024 8:00:45 AM |
No action for E911 on this submittal. Thank you. Justin |