Project Review Comments

Back to List


Project Name
LDC Church Parking Lot at HWY 105 Site Dev. Plan
Description
Parking lot on the exempted parcel; R4 allows for a parking lot.
Location
Parcels
7113200004 7113200004 7113210037 7113210037
Applicant
DREXEL, BARRELL & CO.
Tim McConnell ( TMcConnell@drexelbarrell.com )
(719) 260-0887 x1219
Tim McConnell ( TMcConnell@drexelbarrell.com )
(719) 260-0887 x1219
EA Number
EA23123
File Number
PPR2419
Project Manager
Kari Parsons
Status
Active
Created
11/29/2023 3:05:01 PM

View: Project Documents



Review Comments (9)

Link Agency Comment
Pikes Peak Regional Building Department
6/27/2024 10:50:45 AM
Electrical for the light poles is being fed from the existing church. If this changes, a separate address will need to be assigned and a permit issued for any new meter. Contact Enumerations if needed. No further comment.

Becky Allen
719-799-2707
6/27/2024 10:50:45 AM
View PCD Project Manager
6/26/2024 11:22:37 AM
Application Comments- Please adjust this so it is specific to the site development plan only. see redline 6/26/2024 11:22:37 AM
View PCD Project Manager
6/26/2024 11:20:10 AM
Landscape Plan comments- Planning Only. Engineering May upload additional comments July 2cd. 6/26/2024 11:20:10 AM
View PCD Project Manager
6/26/2024 11:19:23 AM
Site Dev Plan Comments Planning Only. Engineering and stormwater will upload their comments 6/26/2024 11:19:23 AM
View PCD Project Manager
6/26/2024 11:18:50 AM
Letter of Intent- Planning only comments. 6/26/2024 11:18:50 AM
PCD Project Manager
6/26/2024 11:18:06 AM
Engineering and Stormwater will upload the redlines for their divisions. Planning has provided planning-only comments do to an extended time out of the office. 6/26/2024 11:18:06 AM
Mountain View Electric Association, Inc.
6/24/2024 12:13:19 PM
MVEA has no objection to the parking lot on the adjoining parcel, please contact our office when ready for lighting 6/24/2024 12:13:19 PM
911 Authority - El Paso/Teller County
6/17/2024 11:27:46 AM
No action for E911 on this submittal.
Thank you.
Justin
6/17/2024 11:27:46 AM
Colorado Department of Transportation - Pueblo Office
6/17/2024 10:40:36 AM
We are in receipt of the above-referenced development submittal. After review of the provided documents, CDOT Staff currently has NO COMMENT pertaining to this submittal. 6/17/2024 10:40:36 AM