Project Review Comments

Back to List


Project Name
County Wetland & ROW Land Acquisition HWY 105 & LDS Church Exemption Plat Monument
Description
County acquired land for HWY 105 and for Wetland Bank for HWY 105 project. Legalizes parcels.
Location
Parcels
7113200004 7113200004 7113210036 7113210036 7113210037 7113210037
Applicant
DREXEL, BARRELL & CO.
Tim McConnell ( TMcConnell@drexelbarrell.com )
(719) 260-0887 x1219
Tim McConnell ( TMcConnell@drexelbarrell.com )
(719) 260-0887 x1219
EA Number
EA23123
File Number
EX241
Project Manager
Kari Parsons
Status
Active
Created
11/29/2023 2:54:44 PM

View: Project Documents



Review Comments (16)

Link Agency Comment
EPC Stormwater Review
6/25/2024 5:16:41 PM
EPC Stormwater has no comments on this application. A Stormwater review will be completed with the construction application for conformance with our MS4 Permit and criteria.

Reviewed by:
Christina Prete, P.E.
Stormwater Manager
ChristinaPrete@elpasoco.com
6/25/2024 5:16:41 PM
View PCD Project Manager
6/25/2024 12:50:17 PM
Exemption Plat comments 6/25/2024 12:50:17 PM
View PCD Project Manager
6/25/2024 12:49:56 PM
Letter of Intent Redlines. Please address only the exemption Criteria. We do not want to mix private land use with the justification for the exemption process through Right of way and open space acquisition. 6/25/2024 12:49:56 PM
View PCD Project Manager
6/25/2024 12:48:46 PM
The application shall be only for the exemption plat. 6/25/2024 12:48:46 PM
PCD Engineering Division
6/25/2024 12:34:24 PM
Review 1 - EPC DPW Engineer has comments in the following documents:

- Letter of Intent
- Subdivision Exemption Plat
- Application Petition Form

All documents will be uploaded by Project Manager.

Reviewed by:
Hao Vo, PE
haovo@elpasoco.com
6/25/2024 12:34:24 PM
PCD Administrative Notice
6/21/2024 3:31:10 PM
On 6/20/2024, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (83 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $53.12. MB 6/21/2024 3:31:10 PM
US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
6/18/2024 12:08:03 PM
Hello Kari Parsons,

Thank you for contacting the U.S. Fish and Wildlife Service (Service). The Service has reviewed the LDS Church exemption project and has no concerns with this project resulting in impacts to species listed as candidate, proposed, threatened, or endangered.

We appreciate your efforts to ensure the conservation of threatened and endangered species. Thank you for contacting us and please let me know if you have any further questions.

Sincerely,
Emily Berchem
6/18/2024 12:08:03 PM
Pikes Peak Regional Building Department
6/13/2024 12:25:29 PM
Enumerations has no comment.

Becky Allen
beckya@pprbd.org
719-799-2707
6/13/2024 12:25:29 PM
View Colorado Parks and Wildlife
6/12/2024 11:46:12 AM
6/12/2024 11:46:12 AM
EPC Parks Department
6/11/2024 3:14:33 PM
El Paso County Parks and Community Services. The 2022 El Paso County Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. The proposed Highway 105 Bicycle Route is located immediately adjacent and south of the project site but resides within the existing Highway 105 right-of-way as an on-street bicycle facility. As such, no parks dedications or trail easements are necessary for this application. Additionally, as this is a commercial site development application, no regional park fees will be assessed, however an update to the EPC Land Development Code over the next year and half may or may not change this fee requirement. 6/11/2024 3:14:33 PM
Mountain View Electric Association, Inc.
6/10/2024 5:03:47 PM
MVEA has no objection to the exemption plat. Please contact the office when electric service is needed for the parking facility 6/10/2024 5:03:47 PM
View EPC Environmental Services
6/7/2024 10:39:33 AM
6/7/2024 10:39:33 AM
View El Paso County Conservation Dist
6/7/2024 8:27:17 AM
Please see attached .PDF for brief comments. Thanks! 6/7/2024 8:27:17 AM
Tri-Lakes-Monument Fire Protection District
6/4/2024 7:46:42 AM
Fire District has no comment 6/4/2024 7:46:42 AM
911 Authority - El Paso/Teller County
6/4/2024 7:43:50 AM
No action for E911 on this submittal.
Thank you.
Justin
6/4/2024 7:43:50 AM
RBD Floodplain
6/3/2024 8:03:17 AM
no comment 6/3/2024 8:03:17 AM