Project Review Comments
- File Number
- ASB2316
- Project Name
- Widefield Park & Rec Improvements
- Parcels
- 6512300003 6512300003 6513100001 6513100001 6513100003 6513100003
- Applicant
-
Widefield School District
Project Architect Todd Kimes ( toddkimes@lkapartners.com )
(719) 473-8446 x123 Project Architect Todd Kimes ( toddkimes@lkapartners.com )
(719) 473-8446 x123 - File Number
- ASB2316
- Project Manager
- Stormwater Glenn Reese
- Status
- Active
- Created
- 10/24/2023 4:55:05 PM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
| View |
EPC Stormwater Review
9/17/2026 3:40:07 PM |
2 | Trash Screen Substitution (McNICHOLS) | 9/17/2026 3:40:07 PM |
| View |
EPC Stormwater Review
9/17/2026 3:39:46 PM |
2 | PPR2213 - FA Punchlist - 04-08-2026_KHA response | 9/17/2026 3:39:46 PM |
| View |
EPC Stormwater Review
9/17/2026 3:39:34 PM |
2 | Crossmember Replacement (Metal Option) | 9/17/2026 3:39:34 PM |
| View |
EPC Stormwater Review
9/17/2026 3:39:17 PM |
2 | PCM Certification Letter | 9/17/2026 3:39:17 PM |
| View |
EPC Stormwater Review
9/17/2026 3:39:03 PM |
2 | Engineering Record Drawings (As-Builts) | 9/17/2026 3:39:03 PM |
|
EPC Stormwater Review
9/17/2026 3:38:11 PM |
2 |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - Engineering Record Drawings (As-Builts) - PCM Certification Letter - Crossmember Replacement (Metal Option) - PPR2213 - FA Punchlist - 04-08-2026_KHA response - Trash Screen Substitution (McNICHOLS) The majority of my Review 1 comments were not resolved. Please see the attached comments for updated comments (which includes all of the unresolved Review 1 ones). Please request a meeting with me to discuss if any of my comments are unclear. Please do not resubmit anything for this ASB project until you have reviewed and addressed all of my comments and QC'd your as-built calcs compared to the as-built CDs. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
9/17/2026 3:38:11 PM | |
| View |
EPC Stormwater Review
8/5/2026 3:02:45 PM |
1 | Trash Screen Substitution (McNICHOLS) | 8/5/2026 3:02:45 PM |
| View |
EPC Stormwater Review
8/5/2026 3:02:33 PM |
1 | PPR2213 - FA Punchlist - 04-08-2026_KHA response | 8/5/2026 3:02:33 PM |
| View |
EPC Stormwater Review
8/5/2026 3:02:20 PM |
1 | Crossmember Replacement (Metal Option) | 8/5/2026 3:02:20 PM |
| View |
EPC Stormwater Review
8/5/2026 3:02:07 PM |
1 | PCM Certification Letter | 8/5/2026 3:02:07 PM |
| View |
EPC Stormwater Review
8/5/2026 3:01:55 PM |
1 | Engineering Record Drawings (As-Builts) | 8/5/2026 3:01:55 PM |
|
EPC Stormwater Review
8/5/2026 3:05:02 PM |
1 |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - Engineering Record Drawings (As-Builts) - PCM Certification Letter - Crossmember Replacement (Metal Option) - PPR2213 - FA Punchlist - 04-08-2026_KHA response - Trash Screen Substitution (McNICHOLS) This was a pretty incomplete submittal, lacking a lot of detail required for as-builts. I made mostly generic comments as so much information was missing. So I will treat the next review as a 1st review, so expect new comments with the next review. Please give me a call or set up a meeting with me if it's easier to discuss any questions/comments that way. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
8/5/2026 3:05:02 PM |
EDARP