Project Review Comments
- File Number
- ASB2315
- Project Name
- Forest Lakes Filing No. 7
- Description
- 79 single-family lots; Final Plat within PUDSP-19-6
- Parcels
- 7100000443 7100000443 7100000454 7100000454
- Applicant
-
Classic Consulting Engineers & Surveyors, LLC
kyle campbell ( KCampbell@classicconsulting.net )
(719) 492-1219 kyle campbell ( KCampbell@classicconsulting.net )
(719) 492-1219 - File Number
- ASB2315
- Project Manager
- Stormwater Glenn Reese
- Status
- Active
- Created
- 10/24/2023 10:45:24 AM
View: Project Documents
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
EPC Stormwater Review
1/8/2026 4:41:13 PM |
2 |
Review 2: The applicant uploaded duplicate docs for this submittal as those that were uploaded for the last submittal. So none of my comments were addressed. Please address my previous comments on the docs listed below and then resubmit: - As-Built CDs - Pond & Road Certification letter Also, please upload Utility Acceptance Letters. Thanks. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
1/8/2026 4:41:13 PM | |
|
PCD Engineering Division
1/6/2026 9:02:27 AM |
2 |
Forest Lakes Filing No. 7 Review 2 ASB2315 There are no comments relating to drainage or transportation (found in general compliance previously by Lupe Packman). Reviewed by: Jalal Jalal Saleh, PE jalalsaleh@elpasoco.com Charlene Durham, PE charlenedurham@elpasoco.com |
1/6/2026 9:02:27 AM | |
|
EPC DPW Asset Management
12/26/2025 7:17:40 AM |
2 |
Please update the CAD so that it’s in Colorado State Plane Central zone coordinates and include horizontal control points. Reviewed by: Matt Goolsby Senior Geospatial Analyst 719.352.5937 MatthewGoolsby@elpasoco.com |
12/26/2025 7:17:40 AM | |
|
EPC DPW Asset Management
9/8/2025 9:57:41 AM |
1 |
Please update the CAD so it’s in Colorado State Plane Central zone and include horizontal control points. Reviewed by: Matt Goolsby Senior Geospatial Analyst 719.352.5937 MatthewGoolsby@elpasoco.com |
9/8/2025 9:57:41 AM | |
| View |
EPC Stormwater Review
2/21/2024 3:51:28 PM |
1 | Pond & Road Certification letter | 2/21/2024 3:51:28 PM |
| View |
EPC Stormwater Review
2/21/2024 3:51:12 PM |
1 | As-Built CDs | 2/21/2024 3:51:12 PM |
|
EPC Stormwater Review
2/21/2024 3:50:57 PM |
1 |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - As-Built CDs - Pond & Road Certification letter Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
2/21/2024 3:50:57 PM | |
|
PCD Engineering Division
2/16/2024 1:42:17 PM |
1 |
There are no comments relating to drainage or transportation. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
2/16/2024 1:42:17 PM |
EDARP