Project Review Comments
- Project Name
- 11745 Owl Pl Gas Station & Convenience Store
- Description
- gas station and convenience store, major SDP
- Location
- Parcels
- 5301001015 5301001015
- Applicant
-
Galloway & Company, Inc. Colorado Springs Office
galloway-citycs@gallowayus.com ( galloway-citycs@gallowayus.com )
(719) 900-7220 galloway-citycs@gallowayus.com ( galloway-citycs@gallowayus.com )
(719) 900-7220 - EA Number
- EA2377
- File Number
- PPR244
- Project Manager
- Lacey Dean
- Status
- Active
- Created
- 8/22/2023 1:55:57 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
9/9/2024 4:11:47 PM |
Review 3: Planning has no comments. See Engineering comments. Reviewed by: Lacey Dean, Associate Planner laceydean2@elpasoco.com |
9/9/2024 4:11:47 PM | |
View |
PCD Engineering Division
9/9/2024 3:21:00 PM |
FDR_V3 | 9/9/2024 3:21:00 PM |
View |
PCD Engineering Division
9/9/2024 3:20:28 PM |
TIS_V3 | 9/9/2024 3:20:28 PM |
View |
PCD Engineering Division
9/9/2024 3:19:52 PM |
GEC_V3 | 9/9/2024 3:19:52 PM |
View |
PCD Engineering Division
9/9/2024 3:19:26 PM |
FAE_V3 | 9/9/2024 3:19:26 PM |
View |
PCD Engineering Division
9/9/2024 3:19:04 PM |
SDP V3 | 9/9/2024 3:19:04 PM |
PCD Engineering Division
9/9/2024 3:15:13 PM |
Engineering Review Ver.3 Please see engineering review comments on the following documents Road Impact Fee are applicable for Convenience Commercial Note: Additional comments may be provided once VR2321 Plat documents are finalized Site Plan may not be approved until Plat is recorded. TIS_V3. Please add engineer stamp, signature, date at the certification block Site Plan_V3. Please see comments. Entrance width to be corrected. Will address with developer for VR2321 but SDP cannot reflect a 50ft wide entrance. FAE_V3 Please have Engineer stamp/sign/date and have owner sign and date. GEC_V3 Engineer and owner to sign. All pages must be Engineer stamped FDR_V3 Please see comments Thank you Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/9/2024 3:15:13 PM | |
View |
EPC Stormwater Review
9/3/2024 12:57:56 PM |
O&M Manual | 9/3/2024 12:57:56 PM |
View |
EPC Stormwater Review
9/3/2024 12:57:43 PM |
Detention Maintenance Agreement | 9/3/2024 12:57:43 PM |
EPC Stormwater Review
9/3/2024 12:56:12 PM |
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Detention Maintenance Agreement - O&M Manual EPC DPW Stormwater comments have been resolved on the following documents: - PBMP Applicability Form SW Docs that still need to be signed include: - PBMP Applicability Form Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
9/3/2024 12:56:12 PM | |
County Attorney - 1041
8/29/2024 1:04:54 PM |
No comments at this time. Lori Seago Sr. Asst. County Attorney loriseago@elpasoco.com |
8/29/2024 1:04:54 PM | |
View |
PCD Project Manager
6/11/2024 10:50:50 AM |
V2_Site Development Plan | 6/11/2024 10:50:50 AM |
View |
PCD Project Manager
6/11/2024 10:50:32 AM |
V2_Grading and Erosion Control Plan | 6/11/2024 10:50:32 AM |
View |
PCD Project Manager
6/11/2024 10:49:59 AM |
V2_Financial Assurance Forms | 6/11/2024 10:49:59 AM |
View |
PCD Project Manager
6/11/2024 10:49:37 AM |
V2_Final Drainage Report | 6/11/2024 10:49:37 AM |
PCD Project Manager
6/11/2024 10:42:40 AM |
Review 2: EPC Planning comments have been RESOLVED on the relevant documents and Planning has no further comments. Please address comments from Stormwater and Engineering and resubmit for their review. Reviewed by: Lacey Dean, Planner I laceydean2@elpasoco.com |
6/11/2024 10:42:40 AM | |
View |
EPC Stormwater Review
5/30/2024 5:57:11 PM |
PBMP Applicability Form | 5/30/2024 5:57:11 PM |
EPC Stormwater Review
5/30/2024 5:56:50 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - PBMP Applicability Form EPC DPW Stormwater comments have been resolved on the following documents: - Drainage Report - ESQCP - GEC Plan - GEC Checklist - Landscape Plan - Letter of Intent - SWMP - SWMP Checklist Please sign, stamp, and resubmit the following documents for approval: - FDR - GEC Plan Please provide the following documents upon resubmittal, since the WQ treatment facility is actually required per ECM Appendix I.7.2: - Detention Maintenance Agreement - O&M Manual Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
5/30/2024 5:56:50 PM | |
View |
PCD Engineering Division
5/29/2024 4:14:09 PM |
TIS_V2 | 5/29/2024 4:14:09 PM |
PCD Engineering Division
5/29/2024 4:10:38 PM |
Engineering Review Ver.2 Please see engineering review comments on the following documents Road Impact Fee are applicable for Convenience Commercial Note: Additional comments may be provided once VR2321 Plat documents are finalized Site Plan may not be approved until Plat is recorded. TIS_V2. Please complete an engineer and owner certification page for the Traffic Memo being submitted. Site Plan_V2. Please see comments. Entrance width to be corrected. FAE_V2 Please have Engineer stamp/sign/date and have owner sign and date. GEC_V2 Engineer and owner to sign. All pages must be Engineer stamped FDR_V2 Please see comments Documents to be uploaded by PCD and SW Dept. Thank you Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
5/29/2024 4:10:38 PM | |
View |
El Paso County Conservation Dist
4/15/2024 1:37:41 PM |
Comments attached as .PDF; apologies for the delay. | 4/15/2024 1:37:41 PM |
Falcon School District 49
4/5/2024 8:34:38 AM |
District 49 does not have any comments at this time but respectfully reserves the right to comment on any future submittals. | 4/5/2024 8:34:38 AM | |
Upper Black Squirrel Creek GWMD
4/4/2024 4:07:37 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. | 4/4/2024 4:07:37 PM | |
View |
Falcon Fire Protection District
4/1/2024 7:18:49 AM |
4/1/2024 7:18:49 AM | |
View |
EPC Stormwater Review
3/28/2024 1:55:01 PM |
SWMP Checklist | 3/28/2024 1:55:01 PM |
View |
EPC Stormwater Review
3/28/2024 1:54:45 PM |
SWMP | 3/28/2024 1:54:45 PM |
View |
EPC Stormwater Review
3/28/2024 1:54:29 PM |
PBMP Applicability Form | 3/28/2024 1:54:29 PM |
View |
EPC Stormwater Review
3/28/2024 1:54:15 PM |
Letter of Intent | 3/28/2024 1:54:15 PM |
View |
EPC Stormwater Review
3/28/2024 1:54:01 PM |
Landscape Plan | 3/28/2024 1:54:01 PM |
View |
PCD Engineering Division
3/28/2024 1:53:50 PM |
FAE_V1 | 3/28/2024 1:53:50 PM |
View |
EPC Stormwater Review
3/28/2024 1:53:46 PM |
GEC Checklist | 3/28/2024 1:53:46 PM |
View |
EPC Stormwater Review
3/28/2024 1:53:30 PM |
GEC Plan | 3/28/2024 1:53:30 PM |
View |
EPC Stormwater Review
3/28/2024 1:53:10 PM |
ESQCP | 3/28/2024 1:53:10 PM |
View |
PCD Engineering Division
3/28/2024 1:52:54 PM |
Site Plan_V1 | 3/28/2024 1:52:54 PM |
View |
PCD Engineering Division
3/28/2024 1:51:46 PM |
LOI_V1 | 3/28/2024 1:51:46 PM |
View |
PCD Engineering Division
3/28/2024 1:50:42 PM |
TIS_V1 | 3/28/2024 1:50:42 PM |
View |
PCD Engineering Division
3/28/2024 1:50:02 PM |
FDR_V1 | 3/28/2024 1:50:02 PM |
View |
Mountain View Electric Association, Inc.
3/28/2024 1:39:05 PM |
See attached comments | 3/28/2024 1:39:05 PM |
PCD Engineering Division
3/28/2024 1:56:12 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents Road Impact Fee are applicable for Convenience Commercial Note: Additional comments may be provided once VR2321 Plat documents are finalized Site Plan may not be approved until Plat is recorded. TIS_V1 Site Plan_V1 LOI_V1 FAE_V1 GEC_V1 FDR_V1 Thank you Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
3/28/2024 1:56:12 PM | |
EPC Stormwater Review
3/28/2024 1:52:52 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded with Development Services comments) - ESQCP - GEC Plan - GEC Checklist - Landscape Plan - Letter of Intent - PBMP Applicability Form - SWMP - SWMP Checklist Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
3/28/2024 1:52:52 PM | |
View |
PCD Project Manager
3/26/2024 1:53:26 PM |
Sign Plan | 3/26/2024 1:53:26 PM |
View |
PCD Project Manager
3/26/2024 1:53:06 PM |
Lighting Plan | 3/26/2024 1:53:06 PM |
View |
PCD Project Manager
3/26/2024 1:52:04 PM |
Legal Description | 3/26/2024 1:52:04 PM |
View |
PCD Project Manager
3/26/2024 1:50:45 PM |
Application-Petition Form | 3/26/2024 1:50:45 PM |
PCD Project Manager
3/26/2024 1:49:19 PM |
Planning has made review comments on the following documents: - Application-Petition Form - Financial Assurance Forms - Landscape Plan drawings - Legal Description - Letter of Intent - Lighting Plan - Sign Plan - Site Development Plan Reviewed by: Lacey Dean laceydean2@elpasoco.com |
3/26/2024 1:49:19 PM | |
Pikes Peak Regional Building Department
3/19/2024 1:48:58 PM |
1. The trash enclosure exceeds 7’ therefore, a separate address will need to be assigned along with a separate permit. The address is 7821 Meridian Park Drive. 2. Store address is NOT 7440 Meridian Park Drive but should be 7825 Meridian Park Drive , Gas Canopy is 7829 Meridian Park Drive. No further comment. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |