Project Review Comments

Back to List


Project Name
Eagleview MDDP/DBPS Amendment
Description
Master Development Drainage Plan / Drainage Basin Plan Study Amendment. Related to Eagleview. SP-21-006 for preliminary plan file number and SF-22-042 for final plat file
Location
Parcels
5226000001 5226000001 5226000002 5226000002
Applicant
Joe DesJardin
Joe DesJardin ( JDesJardin@proterraco.com )
(307) 899-2020
Joe DesJardin ( JDesJardin@proterraco.com )
(307) 899-2020
EA Number
EA2186
File Number
MDP232
Project Manager
Daniel Torres
Status
Closed
Created
8/16/2023 10:03:31 AM

View: Project Documents



Review Comments (13)

Link Agency Comment
PCD Engineering Division
3/25/2024 10:01:41 AM
Per coordination with the design engineer and stormwater engineer through email, remaining comments have been resolved. The MDDP will be uploaded onto EDARP once approved by the ECM administrator.


Daniel Torres
danieltorres@elpasoco.com
3/25/2024 10:01:41 AM
EPC Stormwater Review
3/8/2024 5:15:59 PM
Review 4: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document:
- MDDP....(to be uploaded by others)

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
3/8/2024 5:15:59 PM
View PCD Engineering Division
2/27/2024 5:45:38 PM
MDDP comment summary 2/27/2024 5:45:38 PM
View PCD Engineering Division
2/27/2024 5:47:39 PM
Review 3 comments on the MDDP are attached.

This MDDP/DBPS Amendment will be taken to the March 12, 2024 Drainage Board meeting.


Reviewed by:
Daniel Torres
danieltorres@elpasoco.com

Jeff Rice
jeffrice@elpasoco.com
2/27/2024 5:47:39 PM
EPC Stormwater Review
2/6/2024 4:59:03 PM
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document:
- MDDP....(to be uploaded by others)

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
2/6/2024 4:59:03 PM
View PCD Engineering Division
1/16/2024 4:35:30 PM
(MDDP comments summary) 1/16/2024 4:35:30 PM
View PCD Engineering Division
1/16/2024 4:36:22 PM
Review 2 comments on the MDDP are attached.

(If Table 4 is revised, also update the LOI accordingly.)

Please set a meeting (Teams is fine) to review the comments and concerns.


Reviewed by:
Daniel Torres
danieltorres@elpasoco.com

Jeff Rice
jeffrice@elpasoco.com
1/16/2024 4:36:22 PM
EPC Stormwater Review
1/11/2024 2:26:58 PM
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document:
- MDDP....(to be uploaded by others)

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
1/11/2024 2:26:58 PM
View PCD Engineering Division
11/27/2023 5:10:34 PM
Letter of intent redlines 11/27/2023 5:10:34 PM
View PCD Engineering Division
11/27/2023 5:09:32 PM
MDDP redlines 11/27/2023 5:09:32 PM
PCD Engineering Division
11/27/2023 5:11:46 PM
Review 1 comment on the following documents will be uploaded.
-Letter of intent
-MDDP

Initial comments have been provided. Review comments and concerns will be discussed with applicant/consultant at the upcoming meeting.

Reviewed by:
Daniel Torres
danieltorres@elpasoco.com

Jeff Rice
jeffrice@elpasoco.com
11/27/2023 5:11:46 PM
PCD Project Manager
11/21/2023 2:23:36 PM
Planning has no comments. 11/21/2023 2:23:36 PM
EPC Stormwater Review
11/21/2023 2:19:10 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- MDP....(to be uploaded by others)

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
11/21/2023 2:19:10 PM