Project Review Comments
- Project Name
- Monument Glamping 1 - Special Use Modification (2024 : New submittal with Proposed Changes)
- Description
- this is a modification to modify what was originally approved on AL223 and PPR2253 to modify camp sites and provide/swap camp sites with new structures. 2024: Applicant has new consulting and a new submission of documents is anticipated.
- Location
- Parcels
- 7127001011 7127001011
- Applicant
-
Monument Ridge Ltd.
Chris Jeub ( chrisjeub@gmail.com )
(719) 660-5781 Chris Jeub ( chrisjeub@gmail.com )
(719) 660-5781 - File Number
- AL2321
- Project Manager
- Ashlyn Mathy
- Status
- Closed
- Created
- 7/27/2023 1:20:46 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
RBD Floodplain
5/8/2024 3:01:12 PM |
tent site specified for 9 and 10 no further comment | 5/8/2024 3:01:12 PM | |
PCD Project Manager
4/30/2024 8:21:05 AM |
Going to hearing June 6 and June 27th. Official US Fish and Wildlife letter is required by June 4th. -Ashlyn Mathy |
4/30/2024 8:21:05 AM | |
View |
PCD Project Manager
4/22/2024 2:58:13 PM |
clearance letter comment | 4/22/2024 2:58:13 PM |
View |
PCD Project Manager
4/22/2024 2:57:43 PM |
site plan comment | 4/22/2024 2:57:43 PM |
PCD Engineering Division
4/22/2024 1:10:34 PM |
Engineering Review Ver.5 Comments resolved on the following documents. LOI_V5 SDP_V5 with 16ft wide internal access driveway width per updated site plan. A Driveway access permit will be required for the 2nd access point. Previously 2022 issued permit was for primary access only. Applicant to submit. Road Impact fees are applicable for the newly added 4 camp sites. Thank you Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
4/22/2024 1:10:34 PM | |
View |
El Paso County Conservation Dist
4/15/2024 1:41:12 PM |
Comments attached as .PDF; apologies for the delay. | 4/15/2024 1:41:12 PM |
View |
Tri-Lakes-Monument Fire Protection District
4/11/2024 8:20:44 AM |
See attached for fire department comment | 4/11/2024 8:20:44 AM |
EPC Code Enforcement
4/2/2024 7:11:30 AM |
No comment. | 4/2/2024 7:11:30 AM | |
View |
PCD Project Manager
3/28/2024 2:53:12 PM |
site plan comments :eng and planning | 3/28/2024 2:53:12 PM |
View |
PCD Project Manager
3/28/2024 2:52:15 PM |
LOI comments : eng and planning | 3/28/2024 2:52:15 PM |
Mountain View Electric Association, Inc.
3/28/2024 1:52:43 PM |
See comment letter dated 9/18/2023. No additional comments at this time. | 3/28/2024 1:52:43 PM | |
PCD Engineering Division
3/28/2024 1:17:53 PM |
Engineering Review Ver.4 Please see engineering review comments on the following documents LOI_V4. Please address the No TIS requirements under ECM B.1.2.D with the newly added sites. Address road impact fees for added sites. Site Plan_V4 Please address required turn around points an access road width. A Driveway access permit will be required for the 2nd access point. Road Impact fees are applicable for the newly added sites. Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
3/28/2024 1:17:53 PM | |
EPC Stormwater Review
3/25/2024 2:15:09 PM |
Given the addition of more glamping sites, please address the following: - In the Letter of Intent, include 1) a discussion about drainage impacts related to the proposed development and 2) a statement about the total estimated area of disturbance to construct the sites. - In the Site Plan, add a note for the total estimated area of disturbance to construct the sites. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
3/25/2024 2:15:09 PM | |
View |
EPC Environmental Services
3/21/2024 10:01:08 AM |
3/21/2024 10:01:08 AM | |
PCD Administrative Notice
3/20/2024 11:01:57 AM |
On 3/20/2024, PCD mailed "Notice of Application" letters for the revised submittal to surrounding property owners within a manually selected range greater than 500 feet (29 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $18.56. MB | 3/20/2024 11:01:57 AM | |
View |
Tri-Lakes-Monument Fire Protection District
3/20/2024 8:14:04 AM |
The ingress/egress driveway does not have dimensions defined on the site plan map. This is a one-way in, one-way out driveway with a significant undefined slope. The 2015 IFC local amendments addresses dead-end access roads and state a 20 foot width with turnarounds at defined intervals. The fire department recommends reviewing the attached amendments and the applicant provide width definitions and turnaround alterations to the access road on the site plan. | 3/20/2024 8:14:04 AM |
RBD Floodplain
3/18/2024 10:40:42 AM |
sites 9 and 10 appear to be added into the SFHA, please specify that these sites are tent sites and not permanent structures | 3/18/2024 10:40:42 AM | |
View |
Colorado Parks and Wildlife
3/15/2024 2:14:02 PM |
3/15/2024 2:14:02 PM | |
PCD Engineering Division
11/8/2023 9:02:17 AM |
Review 3: The resubmitted site plan shows a container located on the southwest corner of the property. Approximately 5 feet of the container is inside the 20' utility and drainage easement. Please be aware structures are not allowed within utility or drainage easements without the permission of easement holders. The site plan shows the container marked as to be moved. Engineering has no other comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager. Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com |
11/8/2023 9:02:17 AM | |
PCD Project Manager
11/8/2023 8:25:26 AM |
Comments have been resolved and this will go to PC and BOCC hearing schedule. -AM |
11/8/2023 8:25:26 AM | |
EPC Code Enforcement
10/19/2023 9:09:34 AM |
The modified shipping container, in the southwest corner of the property, is still not specified on the site plan. | 10/19/2023 9:09:34 AM | |
View |
PCD Project Manager
10/13/2023 8:56:53 AM |
Site plan UNRESOLVED comments |
10/13/2023 8:56:53 AM |
View |
PCD Project Manager
10/13/2023 8:56:05 AM |
Application UNRESOLVED comments | 10/13/2023 8:56:05 AM |
View |
PCD Project Manager
10/13/2023 8:55:45 AM |
Letter of intent -many unresolved comments -this is holding up the project |
10/13/2023 8:55:45 AM |
PCD Engineering Division
10/11/2023 10:19:31 AM |
Engineering has no further comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager. Reviewed by: Carlos Hernandez & Charlene Durham P.E. charlenedurham@elpasoco.com carloshernandez@elpasoco.com |
10/11/2023 10:19:31 AM | |
View |
El Paso County Conservation Dist
9/26/2023 9:36:10 AM |
9/26/2023 9:36:10 AM | |
EPC Code Enforcement
9/26/2023 8:44:48 AM |
- Unpermitted modified shipping container located at the far southwest corner of the property is not included in the submittal and it is in violation of the required 25ft. setback. | 9/26/2023 8:44:48 AM | |
PCD Administrative Notice
9/20/2023 2:43:12 PM |
PCD mailed 15 notifications to surrounding property owners on 9/20/2023. MB | 9/20/2023 2:43:12 PM | |
View |
PCD Project Manager
9/19/2023 11:27:11 AM |
application form comment | 9/19/2023 11:27:11 AM |
View |
PCD Project Manager
9/19/2023 11:26:51 AM |
Site plan comments | 9/19/2023 11:26:51 AM |
View |
PCD Project Manager
9/19/2023 11:26:32 AM |
Letter of intent comments | 9/19/2023 11:26:32 AM |
PCD Engineering Division
9/18/2023 2:18:30 PM |
Review 1 comments will be uploaded by the project manager. Review comments on the following documents: -Letter of Intent (minor comments) - Site Plan (minor comments) Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
9/18/2023 2:18:30 PM | |
View |
Mountain View Electric Association, Inc.
9/18/2023 9:35:20 AM |
See attached comments | 9/18/2023 9:35:20 AM |
View |
EPC Environmental Services
9/14/2023 1:47:01 PM |
9/14/2023 1:47:01 PM | |
EPC Stormwater Review
9/8/2023 2:21:39 PM |
There is not any grading proposed with this submittal that is different from what was approved with PPR2253. Therefore EPC DPW Stormwater does not have any comments on this submittal. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
9/8/2023 2:21:39 PM | |
View |
Colorado Parks and Wildlife
9/1/2023 4:17:58 PM |
9/1/2023 4:17:58 PM | |
RBD Floodplain
8/30/2023 1:55:09 PM |
"Changing the term in the Special Use approval will enable us to have glamping sites that are not tents." "non tent structures" like cabins or tiny homes located in the SFHA need to be elevated to 1 foot above BFE and constructed to resist floatation and or collapse under the pressure of flood waters, or be on wheels road-ready, and be approved for highway travel . The three sites in the floodplain need to remain tent sites. |
8/30/2023 1:55:09 PM |