Project Review Comments

Back to List


Project Name
BOCES Approval of Location
Description
Approval of location for a trade school - BOCES is a federally funded program that offers educational programs for various trades. The use includes on-site housing for the school campus. In order to develop this site, the applicant will be required to submit and receive subsequent approval of a subdivision exemption and site development plan.
Location
Parcels
4200000362 4200000362
Applicant
William Guman & Associates, Ltd.
Bill Guman ( bill@guman.net )
(719) 633-9700
Bill Guman ( bill@guman.net )
(719) 633-9700
EA Number
EA2364
File Number
U241
Project Manager
Lisa Elgin
Status
Active
Created
7/26/2023 9:58:08 AM

View: Project Documents



Review Comments (7)

Link Agency Comment
Colorado Department of Transportation - Pueblo Office
7/2/2024 3:29:22 PM
Please provide a Traffic Impact Study so that CDOT can thoroughly evaluate this development. 7/2/2024 3:29:22 PM
View Mountain View Electric Association, Inc.
7/2/2024 9:56:05 AM
See attached comments 7/2/2024 9:56:05 AM
PCD Engineering Division
7/1/2024 1:25:08 PM
Review 1 - EPC Engineering Comments have been provided on the following documents:

- Letter of Intent (to be uploaded by the project manager)
- Plot Plan Drawings (to be uploaded by the project manager)

Reviewed by:
Daniel, PE
danieltorres@elpasoco.com

Hao Vo, PE
haovo@elpasoco.com
7/1/2024 1:25:08 PM
US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
6/26/2024 2:45:09 PM
Hello Lisa Elgin,

Thank you for contacting the U.S. Fish and Wildlife Service (Service). The Service has reviewed the BOCES project and has no concerns with this project resulting in impacts to species listed as candidate, proposed, threatened, or endangered.

The location of this project falls within the block clearance zone for Colorado Springs, and as such, no listed species are expected to occur in the area.

We appreciate your efforts to ensure the conservation of threatened and endangered species. Thank you for contacting us and please let me know if you have any further questions.

Sincerely,
Emily Berchem
6/26/2024 2:45:09 PM
EPC Stormwater Review
6/26/2024 11:25:06 AM
Review 1: EPC DPW Stormwater does not have comments on any of the uploaded documents. MS4-related criteria and documents (like for an ESQCP and for stormwater quality treatment) will be reviewed at the site development plan phase. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
6/26/2024 11:25:06 AM
View EPC Environmental Services
6/24/2024 12:39:29 PM
6/24/2024 12:39:29 PM
EPC Parks Department
6/20/2024 2:09:24 PM
El Paso County Parks and Community Services. The 2022 El Paso County Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. The proposed Elbert Road and Judge Orr Road Bicycle Routes are located immediately adjacent the west and south sides of the subject property, but will be located within the individual roads' right-of ways, so no additional trail easement dedications will be necessary. As this is a commercial application, no regional park fees will be assessed at final plat unless changes to the El Paso County Land Development Code in 2024-2025 necessitate their assessment. Thank you! 6/20/2024 2:09:24 PM