Project Review Comments
- Project Name
- 7964 CESSNA DR Site Development Plan
- Description
- Site development plan for personal hangar in Meadow Lake Airport. PUD language states landscaping is not required
- Location
- Parcels
- 4304002091 4304002091
- Applicant
-
Bucher Design Studio
Nick Sallecchia ( nick@bucherdesign.com )
(719) 484-0480 Nick Sallecchia ( nick@bucherdesign.com )
(719) 484-0480 - File Number
- PPR2328
- Project Manager
- Christian Haas
- Status
- Closed
- Created
- 7/13/2023 3:14:45 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
EPC Health Department
10/13/2023 12:31:01 PM |
10/13/2023 12:31:01 PM | |
PCD Engineering Division
10/11/2023 10:22:10 AM |
Engineering has no further comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager. Reviewed by: Carlos Hernandez & Charlene Durham P.E. charlenedurham@elpasoco.com carloshernandez@elpasoco.com |
10/11/2023 10:22:10 AM | |
View |
PCD Engineering Division
10/5/2023 10:29:22 AM |
V2_Drainage Letter Comments | 10/5/2023 10:29:22 AM |
PCD Engineering Division
10/5/2023 10:28:58 AM |
Review 2: See comments on the following document(s): - Drainage Letter Comments have been resolved on the following document(s): - Site Development Plan - Preliminary Grading Plan Reviewed by: Carlos Hernandez & Charlene Durham P.E. charlenedurham@elpasoco.com carloshernandez@elpasoco.com |
10/5/2023 10:28:58 AM | |
PCD Project Manager
10/5/2023 10:25:46 AM |
No Planning comments. Awaiting engineer final review. | 10/5/2023 10:25:46 AM | |
EPC Stormwater Review
10/4/2023 5:21:50 PM |
Review 2: EPC DPW Stormwater comments have been resolved on the following documents: - Drainage Letter EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Please note: The proposed area of disturbance is less than 1 acre, therefore an ESQCP is not required. If the area of disturbance exceeds 1 acre at any time, all work must be stopped and an ESQCP must be obtained in order to resume construction. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
10/4/2023 5:21:50 PM | |
View |
PCD Project Manager
9/14/2023 1:45:35 PM |
Please see Engineering comments on Drainage Letter | 9/14/2023 1:45:35 PM |
View |
PCD Project Manager
9/14/2023 1:45:14 PM |
Please see Engineering comments on GradingPlan | 9/14/2023 1:45:14 PM |
View |
PCD Project Manager
9/14/2023 1:44:54 PM |
Please see Engineering comments on Site Development Plan | 9/14/2023 1:44:54 PM |
PCD Engineering Division
9/14/2023 12:28:40 PM |
Review 1 comments will be uploaded by the project manager. Review comments on the following documents: - Site Development Plan - Drainage Letter - Preliminary Grading Plan Reviewed by: Carlos Hernandez & Charlene Durham P.E. Review Engineers carloshernandez@elpasoco.com charlenedurham@elpasoco.com |
9/14/2023 12:28:40 PM | |
PCD Project Manager
9/13/2023 3:44:29 PM |
No Planning comments. | 9/13/2023 3:44:29 PM | |
EPC Stormwater Review
9/13/2023 5:13:45 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Letter...(to be uploaded with Development Services comments) Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
9/13/2023 5:13:45 PM | |
View |
Mountain View Electric Association, Inc.
9/6/2023 11:22:10 AM |
See attached comments | 9/6/2023 11:22:10 AM |
Meadow Lake Airport Association
9/5/2023 8:02:45 PM |
MLAA has no objections to the proposed project, subject to a review and Statement of No Objection from the FAA Denver ADO per Form 7460-1. The Cessna Drive gate is a separate matter. It has not worked correctly since it was destroyed by a careless driver last October. Our service technician was a member of the MLAA, who suffered a fatal accident here last month. We have engaged Taylor Fence to assume maintenance of the gate. In the meantime, we have decided to lock the gate in the open position until it is fully operational. We request that this not delay this project. (We have 75 aircraft on a waiting list for hangars) |
9/5/2023 8:02:45 PM | |
Pikes Peak Regional Building Department
8/31/2023 11:29:31 AM |
The address shown on the plan is correct based on the site plan provided, so, Enumerations has no comment or objection. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
8/31/2023 11:29:31 AM | |
View |
Falcon Fire Protection District
8/30/2023 12:08:50 PM |
8/30/2023 12:08:50 PM | |
View |
Falcon Fire Protection District
8/30/2023 12:08:11 PM |
8/30/2023 12:08:11 PM | |
Upper Black Squirrel Creek GWMD
8/23/2023 1:21:54 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. | 8/23/2023 1:21:54 PM |