Project Review Comments
- Project Name
- Seder Subdivision - Vacate and Replat
- Description
- Replat of Lot 7 Akers Acres Subdivision No. 1
- Location
- Parcels
- 5332002015 5332002015
- Applicant
-
Baseline Engineering Corp
Steve Baggs ( steven.baggs@baselinecorp.com )
(719) 660-2378 Steve Baggs ( steven.baggs@baselinecorp.com )
(719) 660-2378 - EA Number
- EA2355
- File Number
- VR2319
- Project Manager
- Ashlyn Mathy
- Status
- Closed
- Created
- 6/2/2023 2:49:59 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
County Attorney - Water
2/9/2024 10:30:55 AM |
See attached Water Supply Review and Recommendations. Thanks! | 2/9/2024 10:30:55 AM |
PCD Engineering Division
2/6/2024 4:12:46 PM |
Comments have been resolved. The project manager will upload any approved documents. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
2/6/2024 4:12:46 PM | |
View |
PCD Project Manager
2/1/2024 2:41:17 PM |
final plat minor comment please remove replat statement, bocc statement covers everything. once this comment is revised and the water attorney comments are resolved, hearing schedule can begin. |
2/1/2024 2:41:17 PM |
View |
PCD Project Manager
1/17/2024 9:17:39 AM |
plat comments | 1/17/2024 9:17:39 AM |
PCD Engineering Division
1/17/2024 7:27:39 AM |
Resubmit the drainage report with the appropriate signatures for approval. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
1/17/2024 7:27:39 AM | |
County Attorney - Water
1/9/2024 1:31:06 PM |
The Water Supply Information Summary, Commitment Letter and Colorado Division of Water Resources letter all need to match the estimated water demand in the Water Resources Report. The Water Supply Information Summary also needs to break out the amount for commercial use and irrigation. | 1/9/2024 1:31:06 PM | |
EPC Code Enforcement
12/7/2023 12:57:00 PM |
Recommend to add condition of approval that the asphalt singles waste pile be removed within 3 months from date of closing based on recommendation from CDPHE. | 12/7/2023 12:57:00 PM | |
View |
PCD Project Manager
12/6/2023 3:46:14 PM |
final plat comments | 12/6/2023 3:46:14 PM |
View |
PCD Project Manager
12/6/2023 3:45:54 PM |
drainage report comments | 12/6/2023 3:45:54 PM |
PCD Engineering Division
12/4/2023 10:29:46 AM |
Comments have been resolved on the following documents: -Plat Comments on the following document will be uploaded by the project manager: -Drainage report Reviewed By: Lupe Packman lupepackman@elpasoco.com |
12/4/2023 10:29:46 AM | |
County Attorney - Water
12/4/2023 10:00:36 AM |
It is unclear from the documents provided whether the estimated water demand covers both proposed lots or only the new, undeveloped lot. The documents are also inconsistent regarding the uses to which the demand is attributed. Please revise the WSIS, Water Resource Report, and commitment letter as necessary to: 1. Provide the estimated demand for the subdivision as a whole, which includes both lots and all existing and anticipated uses. 2. Identify the water demand attributed to commercial use and that attributed to irrigation of landscaping. 3. If the estimated water demand, whether for the commercial uses, irrigation, or both, is less than the presumptive demand values in Section 8.4.7 (B)(7)(d) of the Land Development Code, please provide justification for the lower amount. This can include, for example, information about demands observed by Cherokee for similar uses in the area. |
12/4/2023 10:00:36 AM | |
County Attorney - Development Review
12/1/2023 4:29:10 PM |
No comments at this time. | 12/1/2023 4:29:10 PM | |
View |
EPC Parks Department
11/15/2023 1:20:40 PM |
El Paso County Parks and Community Services Final Comments - Please See Attached Documents (Administrative Comments - No PAB Endorsement Necessary for Commercial Applications) | 11/15/2023 1:20:40 PM |
County Attorney - Development Review
11/9/2023 3:14:28 PM |
No comments at this time. | 11/9/2023 3:14:28 PM | |
Falcon School District 49
11/8/2023 3:22:15 PM |
School District 49 is in receipt of File Number VR2319. At this time School District 49 has no comments. We respectfully request the opportunity to comment on future submittals. | 11/8/2023 3:22:15 PM | |
Colorado Geological Survey
11/7/2023 6:10:51 PM |
As requested by El Paso County, the Colorado Geological Survey (CGS) has reviewed the application for Seder Subdivision (county project ID VR2319, located at 38.8713, -104.6854). Referral documents include a Soils and Geology Study (Entech Engineering, 2725 Akers Drive, Job No. 231480, October 4, 2023). CGS generally agrees with Entech’s geologic interpretation, identification of hazards and constraints posed by the geology, and recommended mitigation for these conditions. This includes the need for a site-specific soil and foundation investigation for any new construction and to support any Site Development Plan for the undeveloped portion of the site. The replat (Baseline Corporation, Job No. CO-35072, August 29, 2023) references approval by the City of Colorado Springs (note 7). This should be changed to reference El Paso County. CGS has no objection to approval of the replat provided a note is added that a site-specific soil and foundation investigation is required for any new construction and that Entech’s recommendations shall be followed in developing this site. Submitted 11/7/2023 by Jonathan R. Lovekin, Senior Engineering Geologist, Colorado Geological Survey: jlovekin@mines.edu |
11/7/2023 6:10:51 PM | |
View |
PCD Project Manager
11/7/2023 3:17:26 PM |
water resources report comment | 11/7/2023 3:17:26 PM |
View |
PCD Project Manager
11/7/2023 3:16:49 PM |
wastewater disposal report comment | 11/7/2023 3:16:49 PM |
View |
PCD Project Manager
11/7/2023 3:14:17 PM |
final plat comments | 11/7/2023 3:14:17 PM |
View |
PCD Project Manager
11/7/2023 3:13:55 PM |
Drainage report comments | 11/7/2023 3:13:55 PM |
View |
PCD Project Manager
11/7/2023 3:13:32 PM |
Letter if intent comments | 11/7/2023 3:13:32 PM |
PCD Engineering Division
11/7/2023 10:59:26 AM |
Review 1 comments will be uploaded by the project manager for the following documents: -Drainage letter -Plat Reviewed by: Lupe Packman lupepackman@elpasoco.com |
11/7/2023 10:59:26 AM | |
Pikes Peak Regional Building Department
11/7/2023 9:39:48 AM |
1. The address for Lot 1 will retain the existing address of 2725 Akers Drive, Lot 2 will be 2713 Akers Drive. Please add these addresses to the final plat as close to Akers Drive as possible. 2. There is a permit for a free standing sign on the proposed lot 2, 2744 N Marksheffel Road. Will this sign remain? 3. The correct spelling is Akers Drive, no apostrophe. Please revise the final plat. 4. If/when a development plan is submitted for the new development, additional addresses may be assigned. Any commercial property which has multiple buildings will be assigned separate addresses and possibly secondary addressing based on scope. Standard Final Plat comments apply: 1. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block. 2. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. As of September 28th, 2022, an additional over the phone transaction fee of 2.95% of the total transaction will apply for any credit card payment. 3. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project BeckyA@pprbd.org 4. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
11/7/2023 9:39:48 AM | |
Colorado Springs Public Works
11/2/2023 1:42:03 PM |
Marksheffel Rd is controlled by the City of Colorado Springs and any development adjacent to City ROW is required to install Type 1 Curb, gutter and 10' sidewalk along Marksheffel Rd. Patrick V. Morris Civil Engineer II Public Works/Engineering Development Review City of Colorado Springs Phone: 719-385-5075 Patrick.morris@coloradosprings.gov |
11/2/2023 1:42:03 PM | |
EPC Stormwater Review
10/30/2023 4:45:09 PM |
Review 1: EPC DPW Stormwater does not have comments on any of the uploaded documents. No soil disturbances proposed with this VR, so no ESQCP or PBMP/PCM documents required. For the next submittal, for the PBMP Applicability Form you can upload a blank document that states "no soil disturbances proposed at this time, therefore this form is not applicable." Because we are unable to deleted submitted documents on EDARP, so you just have to override them on your end. This will help us avoid confusion related to the PBMP later. Thanks. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
10/30/2023 4:45:09 PM | |
Colorado Parks and Wildlife
10/30/2023 10:43:13 AM |
The Colorado Parks and Wildlife (CPW) is in receipt of the above referenced permit application and is familiar with the site(s). Based both on the location and type of action being proposed CPW believes impacts to the wildlife resource to be negligible. The site(s) location is not located in or on any wilderness area, wildlife preserve, or designated critical habitat. The site(s) location does not sustain any species of plant or animal life that is designated or proposed as threatened or endangered. The site(s) location is not located within a principle flyway for migratory birds. We appreciate being given the opportunity to comment. Please feel free to contact District Wildlife Manager Sarah Watson at 719.439.9636 or via email at sarah.watson@state.co.us should you have any questions or require additional information. | 10/30/2023 10:43:13 AM | |
View |
Colorado Division of Water Resources
10/30/2023 10:42:35 AM |
10/30/2023 10:42:35 AM | |
County Attorney - Water
10/27/2023 12:35:19 PM |
County Attorney’s Office will review for water sufficiency following receipt of findings from the Colorado Division of Water Resources. Thank you. | 10/27/2023 12:35:19 PM | |
View |
Falcon Fire Protection District
10/25/2023 9:49:44 AM |
10/25/2023 9:49:44 AM | |
Colorado Springs Airport Advisory Commission
10/30/2023 10:26:23 AM |
10/30/23 - The AAC had no objections to comments below. This will be presented to the Airport Advisory Commission with the below comments on 10/24/2023. Airport staff recommends no objection with the following conditions: • Avigation Easement: An avigation easement is requested or provide proof of previous recording (book/page or reception number) for development plat. • FAA Form 7460-1: If use of equipment (permanent or temporary) will exceed 190 feet above ground level in height at this site, the applicant is to file an airspace evaluation case with the Federal Aviation Administration (FAA) and provide the results to the Airport before the commencement of construction activities. FAA’s website (https://oeaaa.faa.gov/oeaaa/external/portal.jsp). |
10/30/2023 10:26:23 AM | |
Cherokee Metro Dist
10/20/2023 11:31:51 AM |
No comments | 10/20/2023 11:31:51 AM | |
911 Authority - El Paso/Teller County
10/20/2023 7:41:41 AM |
No action for E911 on this submittal. Thank you. Justin |
10/20/2023 7:41:41 AM | |
Colorado Springs Public Works
10/19/2023 1:27:03 PM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
10/19/2023 1:27:03 PM | |
View |
EPC Environmental Services
10/18/2023 12:34:30 PM |
10/18/2023 12:34:30 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/17/2023 4:19:54 PM |
Good afternoon Ashlyn, CSU has no comments on this proposed final plat. All public utility easements are correctly notated. Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Utilities Development Services | Colorado Springs Utilities 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
10/17/2023 4:19:54 PM | |
View |
EPC Code Enforcement
10/17/2023 2:53:27 PM |
10/17/2023 2:53:27 PM | |
View |
EPC Code Enforcement
10/17/2023 2:53:15 PM |
10/17/2023 2:53:15 PM | |
View |
EPC Code Enforcement
10/17/2023 2:53:02 PM |
10/17/2023 2:53:02 PM | |
EPC Code Enforcement
10/17/2023 2:52:42 PM |
I have serious concerns about moving forward with this application given the length of time the Code Enforcement case has been opened (2015). CDPHE has also been extensively involved with this property over the waste piles. The owner has had years to address the waste shingles on the property. I am requesting a plan and firm deadline for the removal of the waste shingles from the property owner/applicant and I would recommend this application not move forward until the property is in compliance. 11.3.1 (E) Relationship Between Development Application and Violation. A development application shall not be initiated or accepted for submittal by the PCD if the property subject to the application is in violation of this Code unless the purpose of the development application is to correct the violation, or unless specific authorization for submittal is granted by the PCD Director. The PCD Director may suspend any enforcement action prior to such action being heard by the BoCC while an application to correct or resolve the violation has been submitted. |
10/17/2023 2:52:42 PM | |
Colorado Department of Transportation - Pueblo Office
10/17/2023 10:11:31 AM |
CDOT has no comment | 10/17/2023 10:11:31 AM |