Project Review Comments

Back to List


Project Name
7135 Templeton Gap Site Development Plan
Description
The applicant is requesting a site development plan for a landscaping business and outside storage in the RR-5 zoning district. There is an associated Variance of Use that needs to be approved prior to this application
Location
Parcels
5307000005 5307000005
Applicant
Fisk Lawnscapes
Ben Fisk ( ben@fisklawnscapes.com ) Ben Fisk ( ben@fisklawnscapes.com )
File Number
PPR2338
Project Manager
Christian Haas
Status
Closed
Created
5/9/2023 7:55:31 AM

View: Project Documents



Review Comments (31)

Link Agency Comment
PCD Project Manager
12/21/2023 4:26:46 PM
All comments have been resolved. 12/21/2023 4:26:46 PM
EPC Stormwater Review
12/14/2023 3:56:59 PM
Review 3: EPC DPW Stormwater comments have been resolved on the following documents:
- Drainage Report
- GEC Plan
- Landscape Plan
- State Non-Jurisdictional Water Impoundment Structure Application

EPC DPW Stormwater has no further comments. Planner: no re-review necessary.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
12/14/2023 3:56:59 PM
PCD Engineering Division
12/14/2023 11:17:32 AM
Previous review comments have been resolved. Any approved documents will be uploaded by the project manager.

Reviewed by:
Carlos Hernandez
carloshernandez@elpasoco.com
12/14/2023 11:17:32 AM
PCD Project Manager
11/22/2023 10:57:38 AM
All planning comments have been addressed 11/22/2023 10:57:38 AM
View PCD Project Manager
11/22/2023 10:57:25 AM
Please see Engineering and Stormwater comments on Grading and Erosion Control Plan 11/22/2023 10:57:25 AM
View PCD Project Manager
11/22/2023 10:56:45 AM
Please see comments on Drainage Report (Summary on last page) 11/22/2023 10:56:45 AM
View EPC Stormwater Review
11/21/2023 8:04:41 AM
State Non-Jurisdictional Water Impoundment Structure Application 11/21/2023 8:04:41 AM
View EPC Stormwater Review
11/21/2023 8:04:17 AM
Landscape Plan 11/21/2023 8:04:17 AM
View EPC Stormwater Review
11/21/2023 8:03:49 AM
GEC Plan 11/21/2023 8:03:49 AM
View EPC Stormwater Review
11/21/2023 8:02:42 AM
Drainage Report 11/21/2023 8:02:42 AM
PCD Engineering Division
11/21/2023 9:51:45 AM
Review 2 comments on the following documents:

- Final Drainage Report
- GEC Plan

Reviewed by:
Carlos Hernandez
carloshernandez@elpasoco.com
11/21/2023 9:51:45 AM
EPC Stormwater Review
11/21/2023 8:05:15 AM
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report
- GEC Plan
- Landscape Plan
- State Non-Jurisdictional Water Impoundment Structure Application

EPC DPW Stormwater comments have been resolved on the following documents:
- ESQCP
- FAE
- GEC Checklist
- O&M Manual
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Please sign and resubmit the following document:
- ESQCP

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
11/21/2023 8:05:15 AM
View PCD Project Manager
10/13/2023 5:08:59 PM
Both Sections 5.2.40.B.2 (Outside Storage) and Sections 6.2.2.D require screening/buffering so we cannot accept the plan as presented. Can accept alternative landscape plan that leaves out minimum ground cover standards for perimeter buffer but will need to see either opaque fencing, shrubs, sufficient trees or a combination (instead of both opaque fencing and sufficient tree/shrub buffer). Cannot use neighbors support as justification for waiving use-specific development standards 10/13/2023 5:08:59 PM
View PCD Project Manager
10/13/2023 5:01:06 PM
Please see minor comments on Site Development Plan 10/13/2023 5:01:06 PM
Falcon School District 49
10/12/2023 9:46:35 AM
District 49 does not have any comments at this time but respectfully reserves the right to comment on future submittals 10/12/2023 9:46:35 AM
PCD Project Manager
10/9/2023 3:13:46 PM
No comments at this time 10/9/2023 3:13:46 PM
View PCD Engineering Division
10/5/2023 10:07:42 AM
V1_ Landscape Plan Drawings Comments 10/5/2023 10:07:42 AM
View PCD Engineering Division
10/5/2023 10:07:17 AM
V1_ FAE Comments 10/5/2023 10:07:17 AM
View PCD Engineering Division
10/5/2023 10:00:02 AM
V1_GEC Plan Comments 10/5/2023 10:00:02 AM
View PCD Engineering Division
10/5/2023 9:59:43 AM
V1_Drainage Report Comments 10/5/2023 9:59:43 AM
PCD Engineering Division
10/5/2023 9:57:47 AM
Review 1: See comments on the following documents (Blue Text Boxes):

- Drainage Report (uploaded by engineering)
- Grading & Erosion Control Plan (uploaded by engineering)


Reviewed by:
Carlos Hernandez & Charlene Durham P.E.
charlenedurham@elpasoco.com
carloshernandez@elpasoco.com
10/5/2023 9:57:47 AM
View EPC Stormwater Review
10/4/2023 12:41:12 PM
SWMP Checklist 10/4/2023 12:41:12 PM
View EPC Stormwater Review
10/4/2023 12:40:58 PM
SWMP 10/4/2023 12:40:58 PM
View EPC Stormwater Review
10/4/2023 12:40:41 PM
PBMP Applicability Form 10/4/2023 12:40:41 PM
View EPC Stormwater Review
10/4/2023 12:40:27 PM
O&M Manual 10/4/2023 12:40:27 PM
View EPC Stormwater Review
10/4/2023 12:40:11 PM
GEC Checklist 10/4/2023 12:40:11 PM
View EPC Stormwater Review
10/4/2023 12:39:49 PM
ESQCP 10/4/2023 12:39:49 PM
Pikes Peak Regional Building Department
9/26/2023 2:26:31 PM
1. Because the use of the garage is for commercial use and not residential on a residential parcel the garage will require a separate address. Please use the address of 7155 Templeton Gap Road.
2. How tall is the block wall/fence, how tall is the split rail fence? If the trash enclosure exceeds 7’ therefore, a separate address will need to be assigned along with a separate permit.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
9/26/2023 2:26:31 PM
EPC Stormwater Review
10/4/2023 12:34:44 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...(to be uploaded with Development Services comments)
- ESQCP
- FAE.......................(to be uploaded with Development Services comments)
- GEC Plan..............(to be uploaded with Development Services comments)
- GEC Checklist
- Landscape Plan...(to be uploaded with Development Services comments)
- O&M Manual
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Please provide the following documents upon resubmittal (the planner will send an upload request):
- State Non-Jurisdictional Water Impoundment Structure Application.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
10/4/2023 12:34:44 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/21/2023 3:50:51 PM
CSU UDS Does not have any issues with the proposed project. Contact CSU Field engineering for any gas service needs 719-668-4985 9/21/2023 3:50:51 PM
Falcon Fire Protection District
9/21/2023 2:49:58 PM
This project is not inside the Falcon Fire Protection District. No comments. 9/21/2023 2:49:58 PM