Project Name
15080 W CHAPARRAL LOOP - VOU
Description
second dwelling to be used for family, or rented out. The new constructed house will become the primary and then the already existing house will become the second dwelling.
Location
Parcels
3132002004 3132002004
Applicant
Zach Gatti
Zach Gatti ( zagatti2@gmail.com )
(719) 238-2188
Zach Gatti ( zagatti2@gmail.com )
(719) 238-2188
EA Number
EA2332
File Number
VA233
Project Manager
Ashlyn Mathy
Status
Closed
Created
5/2/2023 10:52:43 AM

View: Project Documents



Review Comments (13)

Link Agency Comment
Mountain View Electric Association, Inc.
11/21/2023 4:01:31 PM
MVEA has no objection to the second dwelling 11/21/2023 4:01:31 PM
PCD Project Manager
10/30/2023 10:38:46 AM
comments are resolved, however one site plan with all of the information that is not a j peg would be ideal. 10/30/2023 10:38:46 AM
PCD Engineering Division
10/30/2023 8:21:29 AM
Previous review comments have been resolved. Engineering has no further comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager.

Note:
- Per El Paso County Resolution 19-471 Road Impact Fees are applicable to this project. The land use category used to assess fee is Single-Family. Road Impact fees are due at the time of land use approval or building permit approval whichever comes last per Resolution 19-471. For additional information please visit: https://publicworks.elpasoco.com/road-impact-fees/

- Driveway access permit will be required for the second driveway prior to construction and building permit approval.

Reviewed by:
Carlos Hernandez
carloshernandez@elpasoco.com

Charlene Durham P.E.
charlenedurham@elpasoco.com
10/30/2023 8:21:29 AM
View EPC Health Department
8/4/2023 3:30:29 PM
8/4/2023 3:30:29 PM
Upper Black Squirrel Creek GWMD
8/2/2023 2:52:23 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. 8/2/2023 2:52:23 PM
View PCD Project Manager
7/18/2023 8:24:43 AM
site plan drawing comments 7/18/2023 8:24:43 AM
View PCD Project Manager
7/18/2023 8:24:12 AM
letter of intent comments 7/18/2023 8:24:12 AM
PCD Engineering Division
7/17/2023 9:25:52 AM
Review 1 comments will be uploaded by the project manager. Review comments on the following documents:

- Letter of Intent
- Site Plan

There is no Driveway Access Permit on file for existing driveway or secondary driveway. A Driveway Access Permit is required for all access points onto a county or private road. Please apply for a driveway access permit through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online.

- From EA2332b the driveway access permit fee for the existing residence will be waived since the residence was built prior to 1973. The driveway access permit fee for the new residence will be approximately $204 (subject to change).

- Road Impact Fees will apply for the secondary dwelling. Fees are due at the time of building permit approval. For further fee information please visit https://publicworks.elpasoco.com/road-impact-fees/

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
7/17/2023 9:25:52 AM
View PCD Project Manager
7/14/2023 10:50:23 AM
site plan comments 7/14/2023 10:50:23 AM
View PCD Project Manager
7/14/2023 10:49:59 AM
letter of intent comments 7/14/2023 10:49:59 AM
View EPC Parks Department
7/7/2023 8:37:50 AM
See final administrative Parks comments attached. 7/7/2023 8:37:50 AM
EPC Stormwater Review
6/29/2023 2:29:28 PM
EPC Stormwater has no comments on the proposed layout. Please note, a BESQCP will need to be obtained prior to the start of construction. 6/29/2023 2:29:28 PM
View RBD Floodplain
6/27/2023 8:51:10 AM
Confirmed floodplain show is accurate and that new structure and facilities are located outside the SFHA, no further comment 6/27/2023 8:51:10 AM