Project Review Comments
- Project Name
- Wyoming Estates Filing No. 2
- Description
- Filing 2 - replat of 21 acre lot into additional smaller lots
- Location
- Parcels
- 4333004003 4333004003
- Applicant
-
Home Run Restorations Inc.
Shawn Shaffer ( hrrestorations@gmail.com )
(719) 649-7241 Shawn Shaffer ( hrrestorations@gmail.com )
(719) 649-7241 - EA Number
- EA21112
- File Number
- SF2322
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 3/31/2023 7:28:58 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Administrative Notice
9/10/2024 3:41:35 PM |
On 9/10/2024, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (12 addresses, the remaining properties are owned by the developer). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $8.28. PR | 9/10/2024 3:41:35 PM | |
County Attorney - Development Review
8/27/2024 2:48:05 PM |
Amendment to covenants adequately addresses conditions in the Water Supply Review. No further comments. | 8/27/2024 2:48:05 PM | |
County Attorney - Water
7/19/2024 3:05:47 PM |
I recommend the applicant seek legal counsel to assist with drafting the covenants required by the water review completed in connection with the preliminary plan, which will amend the existing covenants on the property. The amended covenants must comply with the provisions in the existing covenants that address amendments. The draft provided here also does not adequately describe the different allocations to and responsibilities of the individual lots. | 7/19/2024 3:05:47 PM | |
County Attorney - Development Review
6/27/2024 11:59:48 AM |
The recorded covenants need to be amended to 1) cover the entirety of Filings 1 and 2, if they don't already, and 2) address the requirements in the Water Review submitted with the Preliminary Plan. | 6/27/2024 11:59:48 AM | |
View |
EPC Parks Department
4/15/2024 4:41:37 PM |
The following comments are being made on behalf of El Paso County Parks. This application does not require Park Advisory Board consideration: Recommend to the Planning Commission and Board of County Commissioners that approval of the Wyoming Estates Filing No.2 Final Plat include the following condition: require fees in lieu of land dedication for regional park purposes in the amount of $2,020. | 4/15/2024 4:41:37 PM |
PCD Engineering Division
4/11/2024 10:51:25 PM |
Minor comment on the drainage report has been provided with the Preliminary Plan application (SP237). reviewed by: Daniel Torres danieltorres@elpasoco.com |
4/11/2024 10:51:25 PM | |
PCD Project Manager
4/11/2024 8:53:22 AM |
Planning Division has no further comments on the final plat. Plat will be eligible for recording upon Board of County Commissioners approval of the preliminary plan. | 4/11/2024 8:53:22 AM | |
PCD Engineering Division
3/14/2024 9:13:34 AM |
Drainage report comments are unresolved. There will be an increase in impervious coverage with this plat and drainage fees will need to be calculated for that. Please see appendix L in the ECM and calculated the drainage fees for the increase in fees for Livestock Company. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
3/14/2024 9:13:34 AM | |
View |
PCD Project Manager
3/13/2024 10:15:14 AM |
V3: Final Plat comments attached | 3/13/2024 10:15:14 AM |
PCD Project Manager
3/13/2024 10:12:57 AM |
Review 3: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - Letter of Intent (comments provided on file with SF2322) - Final Plat |
3/13/2024 10:12:57 AM | |
EPC Stormwater Review
3/11/2024 5:28:39 PM |
Review 3: Since there is not any proposed disturbance planned with SP237 or SF2322, EPC DPW Stormwater does not have comments on any of the uploaded documents. Note that prior to each home being built, a BESQCP will be required for each. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
3/11/2024 5:28:39 PM | |
View |
PCD Project Manager
12/12/2023 4:55:16 PM |
Review 2: Letter of Intent comments | 12/12/2023 4:55:16 PM |
View |
PCD Project Manager
12/12/2023 4:55:01 PM |
Review 2: Final Plat comments | 12/12/2023 4:55:01 PM |
PCD Project Manager
12/12/2023 4:57:00 PM |
Review 2: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - Letter of Intent - Final Plat |
12/12/2023 4:57:00 PM | |
EPC Stormwater Review
12/12/2023 2:31:37 PM |
Review 2: Comments provided on the drainage report from Review 1 are unresolved. Revise to address all comments provided in the previous review and submit in the next submittal. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
12/12/2023 2:31:37 PM | |
PCD Engineering Division
12/11/2023 9:20:06 AM |
Comments provided on the drainage report and the final plat from review 1 are unresolved. Revise to address all comments provided in the previous review and submit in the next submittal. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
12/11/2023 9:20:06 AM | |
View |
EPC Health Department
12/8/2023 4:42:00 PM |
12/8/2023 4:42:00 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
11/30/2023 9:41:23 AM |
CSU UDS does not have any comments MAR |
11/30/2023 9:41:23 AM | |
911 Authority - El Paso/Teller County
11/30/2023 9:03:47 AM |
Logical extension of Teleo Ct is acceptable. No action for E911 on this submittal. Thank you. Justin. |
11/30/2023 9:03:47 AM | |
Upper Black Squirrel Creek GWMD
11/8/2023 2:14:50 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. Thank you. | 11/8/2023 2:14:50 PM | |
View |
Colorado Parks and Wildlife
10/30/2023 10:00:19 AM |
10/30/2023 10:00:19 AM | |
EPC Stormwater Review
10/28/2023 12:51:19 PM |
Review 1: EPC DPW Stormwater comments have been provided with the Preliminary Plan application (SP237). Please submit the following documents for construction: - ESQCP - GEC Plan - GEC Checklist - SWMP - SWMP Checklist - PBMP Applicability Form Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
10/28/2023 12:51:19 PM | |
View |
Mountain View Electric Association, Inc.
10/26/2023 3:10:07 PM |
See attached comments | 10/26/2023 3:10:07 PM |
County Attorney - Water
10/26/2023 10:09:34 AM |
County Attorney's Office has received referrals for water reviews on both the preliminary plan and the final plat. Water supply will be reviewed in connection with the preliminary plan unless otherwise advised. | 10/26/2023 10:09:34 AM | |
County Attorney - Development Review
10/25/2023 10:28:38 PM |
No comments from County Attorney - Development Review at this time. | 10/25/2023 10:28:38 PM | |
View |
PCD Project Manager
10/25/2023 3:24:14 PM |
V1 Letter of Intent | 10/25/2023 3:24:14 PM |
View |
PCD Project Manager
10/25/2023 3:24:02 PM |
V1 Final Plat (includes Engineering comments) | 10/25/2023 3:24:02 PM |
Colorado Geological Survey
10/25/2023 2:02:20 PM |
Our previous concerns have been addressed. Therefore, CGS has no objection to approving the proposed four-lot minor subdivision (SP237 and SF2322, located at 38.8768, -104.5556). Submitted 10/25/2023 by Jonathan R. Lovekin, Senior Engineering Geologist, Colorado Geological Survey jlovekin@mines.edu |
10/25/2023 2:02:20 PM | |
PCD Engineering Division
10/25/2023 12:59:50 PM |
Review 1 comments for the following documents will be uploaded by the project manager. -Final plat Reviewed By: Lupe Packman lupepackman@elpasoco.com Daniel Torres danieltorres@elpasoco.com |
10/25/2023 12:59:50 PM | |
PCD Project Manager
10/25/2023 11:21:44 AM |
Bylaws were submitted in place of covenants. Covenants have not been submitted. | 10/25/2023 11:21:44 AM | |
PCD Project Manager
10/25/2023 3:23:33 PM |
Review 1: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - Letter of Intent - Final Plat (includes Engineering comments) Pursuant to Preliminary Plan review comments, please also update the following items: - Fire Protection Report - Electric Provider Commitment Letter - OWTS Report - Soils & Geology Report |
10/25/2023 3:23:33 PM | |
Pikes Peak Regional Building Department
10/25/2023 9:14:21 AM |
Enumerations has the following comments: 1. Enumerations has been provided with a copy of this plat for address assignment. Once addressing is returned to the applicant, it needs to be added to this plat prior to recording. 2. Enumerations will review the mylar prior to recording as per usual procedure. An Enumerations fee of $20 will be due at the time of mylar review. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
10/25/2023 9:14:21 AM | |
View |
Falcon School District 49
10/24/2023 12:25:36 PM |
Please see attached correspondence | 10/24/2023 12:25:36 PM |
View |
Falcon Fire Protection District
10/17/2023 8:30:20 AM |
10/17/2023 8:30:20 AM | |
View |
Falcon Fire Protection District
10/17/2023 8:29:45 AM |
10/17/2023 8:29:45 AM | |
View |
Colorado Division of Water Resources
10/12/2023 9:09:45 PM |
See attached letter. | 10/12/2023 9:09:45 PM |
View |
EPC Parks Department
10/9/2023 3:18:12 PM |
See Parks comments attached. | 10/9/2023 3:18:12 PM |
View |
Parks Advisory Board
10/9/2023 3:17:05 PM |
See final Parks comments attached. | 10/9/2023 3:17:05 PM |
911 Authority - El Paso/Teller County
10/9/2023 8:03:05 AM |
Logical extension of Teleo Ct is acceptable. No action for E911 on this submittal. Thank you. Justin. |
10/9/2023 8:03:05 AM | |
View |
EPC Environmental Services
10/6/2023 12:09:20 PM |
10/6/2023 12:09:20 PM | |
Colorado Department of Transportation - Pueblo Office
10/5/2023 9:51:09 AM |
CDOT has no comment | 10/5/2023 9:51:09 AM | |
RBD Floodplain
10/4/2023 4:48:43 PM |
project area not in the SFHA, no comment | 10/4/2023 4:48:43 PM |