Project Review Comments
- Project Name
- Town of Ramah Wastewater System Site Development Plan
- Description
- Expand wastewater services to include removal of a lagoon and septic tank, and add 3 new lagoons, and a lift station 15,000gpd peak
- Location
- Parcels
- 100000088 100000088 1101107001 1101107001
- Applicant
-
Element Engineering
Nicholaus Marcotte ( nmarcotte@elementengineering.net )
(303) 378-2969 Nicholaus Marcotte ( nmarcotte@elementengineering.net )
(303) 378-2969 - File Number
- PPR2325
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 3/10/2023 2:41:29 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
7/2/2024 4:47:57 PM |
Engineering Review Ver.8 No further engineer comments Signed FDR received. Engineer & SW documents routed for approval. Thank you. Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
7/2/2024 4:47:57 PM | |
PCD Engineering Division
6/19/2024 5:24:40 PM |
Review 7: Engineering comments have been resolved on the drainage report. Please provide Town of Ramah signature on report and return for approval. Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
6/19/2024 5:24:40 PM | |
View |
PCD Engineering Division
6/12/2024 9:08:29 AM |
Drainage Report Redlines | 6/12/2024 9:08:29 AM |
PCD Engineering Division
6/12/2024 9:06:04 AM |
Review 6: See Engineering comments on the following documents - Drainage Report Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
6/12/2024 9:06:04 AM | |
EPC Stormwater Review
6/12/2024 8:27:53 AM |
Review 6: EPC DPW Stormwater comments have been resolved on the following documents: - SWMP - SWMP Checklist EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
6/12/2024 8:27:53 AM | |
View |
PCD Engineering Division
5/23/2024 2:43:34 PM |
FAE Redlines | 5/23/2024 2:43:34 PM |
View |
PCD Engineering Division
5/23/2024 2:43:15 PM |
Drainage Report Redlines | 5/23/2024 2:43:15 PM |
PCD Engineering Division
5/23/2024 2:42:39 PM |
Review 5: See Engineering comments on the following documents - Drainage Report - FAE Comments have been resolved on the Construction Drawings/GEC Plan set Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
5/23/2024 2:42:39 PM | |
View |
EPC Stormwater Review
5/21/2024 12:59:53 PM |
SWMP Checklist | 5/21/2024 12:59:53 PM |
View |
EPC Stormwater Review
5/21/2024 2:35:02 PM |
SWMP - Please note: Section VII.B Long Term Stormwater Management contains a statement that the project relies on an existing regional downgradient storwmater quality facilities for water quality treatment. This is not consistent with the Drainage Report Text. This item is outstanding and still needs to be addressed at the next submittal. | 5/21/2024 2:35:02 PM |
EPC Stormwater Review
5/21/2024 12:44:07 PM |
Review 5: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - SWMP - SWMP Checklist EPC DPW Stormwater comments have been resolved on the following documents: - CDs - FAE - PBMP Applicability Form Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
5/21/2024 12:44:07 PM | |
View |
PCD Engineering Division
4/10/2024 4:49:37 PM |
FAE Redlines | 4/10/2024 4:49:37 PM |
View |
PCD Engineering Division
4/10/2024 1:34:12 PM |
Construction Drawing Redlines | 4/10/2024 1:34:12 PM |
View |
PCD Engineering Division
4/10/2024 1:33:28 PM |
Drainage Report Redlines | 4/10/2024 1:33:28 PM |
PCD Engineering Division
4/10/2024 4:44:44 PM |
Review 4: See Engineering comments on the following documents - Construction Drawings/GEC Plan - Drainage Report Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
4/10/2024 4:44:44 PM | |
View |
EPC Stormwater Review
4/10/2024 11:37:23 AM |
PBMP | 4/10/2024 11:37:23 AM |
EPC Stormwater Review
4/10/2024 11:31:42 AM |
Review 4: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs...........(to be uploaded with Development Services comments) - FAE...........(to be uploaded with Development Services comments) - PBMP Applicability Form - SWMP (A new SWMP has not been submitted, the SWMP needs to be updated and resubmitted. See comments from submittal 1 and 2 and resubmit updated SWMP) - SWMP Checklist (See previous comments) EPC DPW Stormwater comments have been resolved on the following documents: - Drainage Report - GEC Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
4/10/2024 11:31:42 AM | |
View |
EPC Stormwater Review
2/15/2024 4:53:25 PM |
PBMP | 2/15/2024 4:53:25 PM |
View |
EPC Stormwater Review
2/15/2024 4:53:09 PM |
GEC Checklist | 2/15/2024 4:53:09 PM |
View |
EPC Stormwater Review
2/15/2024 4:52:39 PM |
FAE | 2/15/2024 4:52:39 PM |
View |
EPC Stormwater Review
2/15/2024 4:51:54 PM |
Drainage Report | 2/15/2024 4:51:54 PM |
View |
EPC Stormwater Review
2/15/2024 4:51:17 PM |
CDs | 2/15/2024 4:51:17 PM |
PCD Engineering Division
2/15/2024 12:54:00 PM |
Review 3: See comments on the following documents - Construction Drawings/GEC Plan (uploaded by the stormwater engineer) - Drainage Report (uploaded by the stormwater engineer) - Financial Assurance Estimate Form: (uploaded by the stormwater engineer) Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com Charlene Durham, PE charlenedurham@elpasoco.com |
2/15/2024 12:54:00 PM | |
EPC Stormwater Review
2/15/2024 4:46:51 PM |
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs......................(uploaded with Development Services comments) - Drainage Report...(uploaded with Development Services comments) - FAE.......................(uploaded with Development Services comments) - GEC Checklist - PBMP Applicability Form - SWMP (A new SWMP has not been submitted. See comments from submittal 1 and 2 and resubmit updated SWMP) - SWMP Checklist (See previous comments) EPC DPW Stormwater comments have been resolved on the following documents: - ESQCP Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
2/15/2024 4:46:51 PM | |
View |
EPC Stormwater Review
11/30/2023 5:10:59 PM |
SWMP Checklist | 11/30/2023 5:10:59 PM |
View |
EPC Stormwater Review
11/30/2023 5:10:36 PM |
SWMP | 11/30/2023 5:10:36 PM |
View |
EPC Stormwater Review
11/30/2023 5:10:01 PM |
PBMP | 11/30/2023 5:10:01 PM |
View |
EPC Stormwater Review
11/30/2023 5:09:44 PM |
GEC Checklist | 11/30/2023 5:09:44 PM |
View |
EPC Stormwater Review
11/30/2023 5:05:36 PM |
FAE | 11/30/2023 5:05:36 PM |
View |
EPC Stormwater Review
11/30/2023 5:04:55 PM |
ESQCP | 11/30/2023 5:04:55 PM |
View |
EPC Stormwater Review
11/30/2023 5:02:15 PM |
Drainage Report | 11/30/2023 5:02:15 PM |
View |
EPC Stormwater Review
11/30/2023 5:01:19 PM |
CDs | 11/30/2023 5:01:19 PM |
PCD Project Manager
11/30/2023 1:48:31 PM |
Planning Division has no further comments at this time. | 11/30/2023 1:48:31 PM | |
EPC Stormwater Review
11/30/2023 5:13:00 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs......................(uploaded with Development Services comments) - Drainage Report...(uploaded with Development Services comments) - ESQCP - FAE.......................(uploaded with Development Services comments) - GEC Checklist - PBMP Applicability Form - SWMP - SWMP Checklist EPC DPW Stormwater comments have been resolved on the following documents: - Site Development Plan - Geological Hazard Report Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
11/30/2023 5:13:00 PM | |
PCD Engineering Division
11/30/2023 12:49:52 PM |
Review 2 redline comments on the following documents will be uploaded by the stormwater engineer: - Construction Drawings/GEC Plan: Revise minor Comments and submit with stamps and signatures. - Drainage Report - Financial Assurance Estimate Form: Revise minor comments and submit with owner signature. Review 1 comments on the following documents have been resolved: - Letter of Intent - Geotechnical Evaluation Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com Charlene Durham, PE charlenedurham@elpasoco.com |
11/30/2023 12:49:52 PM | |
View |
Colorado Department of Public Health and Environment
11/21/2023 10:13:33 AM |
Please see auto responder from CDPHE. Please let us know if you have additional question. | 11/21/2023 10:13:33 AM |
View |
EPC Stormwater Review
8/1/2023 7:28:20 AM |
Updated GEC Checklist Form with Comments | 8/1/2023 7:28:20 AM |
View |
EPC Stormwater Review
7/31/2023 11:57:00 AM |
LOI | 7/31/2023 11:57:00 AM |
View |
EPC Stormwater Review
7/31/2023 11:56:30 AM |
Geotechnical Evaluation Report | 7/31/2023 11:56:30 AM |
View |
EPC Stormwater Review
7/31/2023 11:49:14 AM |
SWMP Checklist | 7/31/2023 11:49:14 AM |
View |
EPC Stormwater Review
7/31/2023 11:48:57 AM |
SWMP | 7/31/2023 11:48:57 AM |
View |
EPC Stormwater Review
7/31/2023 11:48:33 AM |
Site Development Plan | 7/31/2023 11:48:33 AM |
View |
EPC Stormwater Review
7/31/2023 11:45:51 AM |
PBMP | 7/31/2023 11:45:51 AM |
View |
EPC Stormwater Review
7/31/2023 11:45:33 AM |
Geological Hazard Report | 7/31/2023 11:45:33 AM |
View |
EPC Stormwater Review
7/31/2023 11:45:03 AM |
GEC Checklist | 7/31/2023 11:45:03 AM |
View |
EPC Stormwater Review
7/31/2023 11:40:57 AM |
GEC Plan | 7/31/2023 11:40:57 AM |
View |
EPC Stormwater Review
7/31/2023 11:37:12 AM |
FDR | 7/31/2023 11:37:12 AM |
View |
EPC Stormwater Review
7/31/2023 11:36:54 AM |
FAE | 7/31/2023 11:36:54 AM |
View |
EPC Stormwater Review
7/31/2023 11:34:30 AM |
ESQCP | 7/31/2023 11:34:30 AM |
View |
EPC Stormwater Review
7/31/2023 11:34:03 AM |
CDs | 7/31/2023 11:34:03 AM |
PCD Engineering Division
7/31/2023 9:14:00 AM |
Review 1 redline comments on the following documents will be uploaded by the stormwater engineer: - Construction Drawings - Drainage Report - Letter of Intent - Site Plan - Geotechnical Evaluation - Financial Assurance Estimate Form Due to the volume and complexity of comments and redlines, Staff may provide additional, more detailed comments on the next submittal. Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com Charlene Durham, PE charlenedurham@elpasoco.com |
7/31/2023 9:14:00 AM | |
PCD Project Manager
7/28/2023 10:12:08 AM |
Review #1: PCD Planning Division has comments (in green text boxes) on the following documents: - Site Development Plan Comments will be uploaded by Engineering or Stormwater. |
7/28/2023 10:12:08 AM | |
Mountain View Electric Association, Inc.
7/25/2023 1:10:45 PM |
MVEA has existing facilities near and within this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. If electric services are needed, please contact our office. | 7/25/2023 1:10:45 PM | |
EPC Stormwater Review
7/31/2023 11:31:52 AM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CDs.......................(uploaded with Development Services comments) - Drainage Report...(uploaded with Development Services comments) - ESQCP - FAE.......................(uploaded with Development Services comments) - GEC Plan...............(uploaded with Development Services comments) - GEC Checklist - Geological Hazard Report...............(uploaded with Development Services comments) - PBMP Applicability Form - Site Development...............(uploaded with Development Services comments) - SWMP - SWMP Checklist Due to the volume or complexity of the comments provided, these comments are preliminary in nature and EPC DPW Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
7/31/2023 11:31:52 AM | |
Pikes Peak Regional Building Department
7/21/2023 1:43:51 PM |
Enumerations does not address anything in the Town of Ramah. Please contact the Town of Ramah regarding an address assignment for the lift station to provide to Mountain View Electric. Becky Allen PPRBD Enumerations |
7/21/2023 1:43:51 PM | |
Colorado Department of Transportation - Pueblo Office
7/12/2023 1:18:28 PM |
Any new utilities geotechnical borings or traffic control within CDOT Right-of-Way must have a special use or utility permit. https://www.codot.gov/business/permits/utilitiesspecialuse Permit Writers Contact Gabe Martinez 5615 Wills Blvd., Suite A Pueblo, CO 81008 719-562-5519 gabrielj.martinez@state.co.us |
7/12/2023 1:18:28 PM |