Project Review Comments

Back to List


Project Name
FAWWA Water Treatment Plant Site Development Plan
Description
5,000 SF building; Utility site development plan.
Location
9275 Arroya Lane
Parcels
5227000007 5227000007
Applicant
JDS-Hydro Consultants, Inc.
Gerald Duncan ( jerry.duncan@respec.com )
(404) 793-5017
Gerald Duncan ( jerry.duncan@respec.com )
(404) 793-5017
File Number
PPR2314
Project Manager
Christian Haas
Status
Closed
Created
2/10/2023 1:42:09 PM

View: Project Documents



Review Comments (34)

Link Agency Comment
PCD Engineering Division
11/30/2023 8:03:19 AM
Engineering Review Ver.4

No further engineer comments. Documents routed for County Engineer Approval.
Road Impact fees will be applicable to the new building.
5120sqft at Institution Rate.

Thank you.

Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
11/30/2023 8:03:19 AM
EPC Stormwater Review
11/30/2023 7:22:46 AM
Review 4: EPC DPW Stormwater comments have been resolved on the following documents:
- GEC Plan
- GEC Checklist
- SWMP Checklist

EPC DPW Stormwater has no further comments. Planner: no re-review necessary.

Reviewed by:
Mikayla Hartford
Stormwater Engineer I
MikaylaHartford@elpasoco.com
11/30/2023 7:22:46 AM
PCD Project Manager
11/7/2023 8:17:03 AM
All Planning Comments have been resolved. 11/7/2023 8:17:03 AM
View EPC Stormwater Review
11/2/2023 3:31:13 PM
SWMP Checklist 11/2/2023 3:31:13 PM
View EPC Stormwater Review
11/2/2023 3:30:57 PM
GEC Plan 11/2/2023 3:30:57 PM
PCD Engineering Division
11/2/2023 3:57:40 PM
Engineering Review Ver.3

No further engineer comments.
Road Impact fees will be applicable to new building.
5120sqft at Institution Rate.

Pending Stormwater comments to be resolved for final engineer documents approval.
PCD Planner to program a 5 day re-review.
.

Thank you.

Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
11/2/2023 3:57:40 PM
EPC Stormwater Review
11/2/2023 3:24:18 PM
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- GEC Plan
- GEC Checklist (A signed and completed GEC Checklist needs to be submitted)
- SWMP Checklist (a signature is required prior to approval)

EPC DPW Stormwater comments have been resolved on the following documents:
- ESQCP
- FAE
- PBMP Applicability Form

Reviewed by:
Mikayla Hartford
Stormwater Engineer I
MikaylaHartford@elpasoco.com
11/2/2023 3:24:18 PM
View EPC Stormwater Review
10/4/2023 2:20:45 PM
LOI 10/4/2023 2:20:45 PM
View EPC Stormwater Review
10/4/2023 2:19:04 PM
SWMP Checklist 10/4/2023 2:19:04 PM
View EPC Stormwater Review
10/4/2023 2:18:46 PM
PBMP 10/4/2023 2:18:46 PM
View EPC Stormwater Review
10/4/2023 2:11:47 PM
GEc Checklist 10/4/2023 2:11:47 PM
View EPC Stormwater Review
10/4/2023 2:11:28 PM
GEC 10/4/2023 2:11:28 PM
View EPC Stormwater Review
10/4/2023 2:07:48 PM
FAE 10/4/2023 2:07:48 PM
View EPC Stormwater Review
10/4/2023 2:07:25 PM
ESQCP 10/4/2023 2:07:25 PM
View PCD Project Manager
10/4/2023 1:34:43 PM
Need application signed 10/4/2023 1:34:43 PM
View PCD Project Manager
10/4/2023 1:33:58 PM
Plumbing plan submitted instead of Lighting Plan 10/4/2023 1:33:58 PM
PCD Engineering Division
10/2/2023 2:28:35 PM
Engineering Review Ver.2

Please see comments on the following documents

LOI_V2 Please update drainage statement on LOI.
GEC_V2 Please submit complete GEC Plan. Only one page was uploaded. Other pages were missing. Ensure signatures and ENGR stamps are complete for final submital.

Comments addressed on the following documents:
SDP_V2
ESQCP_V2
FAE_V2
Road Impact fees will be applicable to new building.
5120sqft at Institution Rate.
Please program for a shortened 5 day engineer re-review period once SW comments have been addressed.

Thank you.

Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
10/2/2023 2:28:35 PM
EPC Stormwater Review
10/4/2023 1:58:55 PM
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- ESQCP
- FAE
- GEC Plan...............(uploaded with Development Services comments)
- GEC Checklist
- PBMP Applicability Form
- SWMP Checklist

EPC DPW Stormwater comments have been resolved on the following documents:
- Site Development Plan
- SWMP

Reviewed by:
Mikayla Hartford
Stormwater Engineer I
MikaylaHartford@elpasoco.com
10/4/2023 1:58:55 PM
View PCD Project Manager
4/18/2023 8:15:30 AM
Site Development Plan comments 4/18/2023 8:15:30 AM
View PCD Project Manager
4/18/2023 8:15:08 AM
Lighting Plan comments 4/18/2023 8:15:08 AM
View PCD Project Manager
4/18/2023 8:14:53 AM
Landscape Plan comments 4/18/2023 8:14:53 AM
View PCD Project Manager
4/18/2023 8:13:58 AM
Please review Planning comments on the following documents:
-Application/Petition Form
-Landscape Plans
-Lighting Plan
-Site Development Plan
4/18/2023 8:13:58 AM
View EPC Stormwater Review
4/17/2023 4:32:13 PM
PBMP 4/17/2023 4:32:13 PM
View EPC Stormwater Review
4/17/2023 4:30:40 PM
SWMP Checklist 4/17/2023 4:30:40 PM
View EPC Stormwater Review
4/17/2023 4:29:46 PM
SWMP 4/17/2023 4:29:46 PM
View EPC Stormwater Review
4/17/2023 4:28:55 PM
GEC Plan 4/17/2023 4:28:55 PM
View EPC Stormwater Review
4/17/2023 4:28:37 PM
GEC Checklist 4/17/2023 4:28:37 PM
View EPC Stormwater Review
4/17/2023 4:27:12 PM
FAE 4/17/2023 4:27:12 PM
View EPC Stormwater Review
4/17/2023 4:26:11 PM
ESQCP 4/17/2023 4:26:11 PM
View Mountain View Electric Association, Inc.
4/17/2023 11:45:37 AM
See attached comments 4/17/2023 11:45:37 AM
PCD Engineering Division
4/13/2023 5:17:23 PM
Engineer Review Ver.1

Please see engineer review comments on the following documents
Documents to be updated by PCD PM and DPW SW.

-Please provide a drainage letter to cover the East Tank Site. The prior project PPR20_017 only covered the west tank site. No drainage calcs or maps have been provided with this submittal. Additional GEC Plan comments may be necessary after review of the drainage letter and maps.
-Financial Assurance Form V1
-Grading & Erosion Control Plan V1
-Letter of Intent V1
-Erosion and Stormwater Quality Control Permit (ESQCP) V1
-Site Development Plan V1
-PBMP Applicability Form V1


Thank you
Edward Schoenheit, Engineer I
E.P.C. Dept. of Public Works
2880 International Circle
Colorado Springs, CO. 80910
Office: 719.520.6813
Cell: 719.502.9659
https://planningdevelopment.elpasoco.com/
4/13/2023 5:17:23 PM
Pikes Peak Regional Building Department
4/12/2023 2:30:38 PM
1. Existing water tank address on site is 9275 Arroya Lane, 9267 Arroya Lane was assigned to electrical to pump station. New address to the proposed Water Treatment Plant is 9255 Arroya Lane.
No further comment.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
4/12/2023 2:30:38 PM
EPC Stormwater Review
4/17/2023 4:45:25 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Site Development Plan.......................(to be uploaded with project manager comments)
- ESQCP...............(uploaded with Development Services comments)
- FAE.......................(uploaded with Development Services comments)
- GEC Plan...............(uploaded with Development Services comments)
- GEC Checklist
- SWMP
- SWMP Checklist
- PBMP Applicability Form...............(uploaded with Development Services comments)

Due to the volume or complexity of the comments provided, these comments are preliminary in nature and EPC DPW Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review.

Reviewed by:
Mikayla Hartford
Stormwater Engineer I
MikaylaHartford@elpasoco.com
4/17/2023 4:45:25 PM
Black Forest Fire Protection District
4/7/2023 3:59:52 PM
This facility shall require review(s) by the CSFD DFM per an existing MOU between BFFR and CSFD for developments and any occupancies beyond single family residence. 4/7/2023 3:59:52 PM