Project Review Comments

Back to List


Project Name
HOPE Physical Therapy-Parking Lot
Description
Parking lot is being built next to the physical therapy center
Location
Parcels
6323402020 6323402020
Applicant
Galloway & Company, Inc.
Brynhildr Halsten ( brynhildrhalsten@gallowayus.com )
(719) 900-7220
Brynhildr Halsten ( brynhildrhalsten@gallowayus.com )
(719) 900-7220
File Number
PPR235
Project Manager
Joe Letke
Status
Active
Created
2/2/2023 1:05:00 PM

View: Project Documents



Review Comments (28)

Link Agency Comment
View PCD Engineering Division
4/22/2024 10:18:20 AM
Drainage Report Redlines 4/22/2024 10:18:20 AM
View PCD Engineering Division
4/22/2024 10:17:53 AM
Site Development Plan Comments 4/22/2024 10:17:53 AM
PCD Engineering Division
4/22/2024 10:19:24 AM
Review 3: Minor Review comments on the following documents:

- Site Development Plan
- Drainage Letter

Any questions concerning the comments, please call or email.

Planner the next submittal can have a one-week turnaround.

Reviewed by:
Charlene Durham, PE
charlenedurham@elpasoco.com
4/22/2024 10:19:24 AM
Colorado Springs Public Works
4/18/2024 6:50:48 AM
Traffic Engineering has no comments on this item.

Brian Shevock
Public Works/Traffic Engineering
Traffic Engineer
City of Colorado Springs
brian.shevock@coloradosprings.gov
(719) 385-7620
4/18/2024 6:50:48 AM
Colorado Springs Public Works
4/17/2024 6:10:02 AM
Engineering Development Review Division (EDRD) comments has been addressed, no further comments on this item.

Patrick V. Morris
Civil Engineer II
Public Works/Engineering Development Review
City of Colorado Springs
Phone: 719-385-5075
Patrick.morris@coloradosprings.gov
4/17/2024 6:10:02 AM
PCD Project Manager
4/16/2024 1:52:36 PM
There are no outstanding comments from planning.

Joe Letke
Planner II
719-520-7964
4/16/2024 1:52:36 PM
PCD Project Manager
12/26/2023 4:44:43 PM
There are no outstanding comments from planning.

Joe Letke
Planner II
719-520-7964
12/26/2023 4:44:43 PM
View PCD Engineering Division
12/26/2023 4:30:25 PM
V2 Site Development Plan Comments 12/26/2023 4:30:25 PM
View PCD Engineering Division
12/26/2023 4:29:59 PM
V2 Drainage Letter Comments 12/26/2023 4:29:59 PM
PCD Engineering Division
12/26/2023 4:29:30 PM
Review 2: Review comments on the following documents:

- Site Development Plan
- Drainage Letter

Review comments have been resolved on the following documents:
- Letter of Intent

Note:
- The Road Impact Fee will NOT be applicable to this project.
- A Financial Assurance Form will be required to be included in the next submittal due to the proposed culvert in the county right-of-way. Please see comments on the drainage letter and construction drawings.
- City of Colorado Springs drainage report and construction drawings for the inlet on the corner of the property will be uploaded to EDARP by the planner for you to reference as these documents are more recent.

A Commercial Driveway Access Permit is required prior to the start of construction. Please apply for a driveway access permit through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online.

Reviewed by:
Carlos Hernandez & Charlene Durham P.E.
charlenedurham@elpasoco.com
carloshernandez@elpasoco.com
12/26/2023 4:29:30 PM
Colorado Springs Public Works
12/21/2023 10:18:54 AM
Add the following note to the site plan:

"All curb, gutter, driveways, pedestrian ramps and sidewalk posing a safety hazard, damaged, exhibiting excessive deterioration or does not meet current City Engineering standards along Austin Bluffs Pkwy adjacent to the site will need to be removed and replaced prior to the issuance of the Certificate of Occupancy (CO). An on-site meeting can be set up with the Engineering Development Review Division (EDRD) inspector to determine what, if any improvements are required. The EDRD inspector can be reached at 719-385-5977."

Patrick V. Morris
Civil Engineer II
Public Works/Engineering Development Review
City of Colorado Springs
Phone: 719-385-5075
Patrick.morris@coloradosprings.gov
12/21/2023 10:18:54 AM
EPC Stormwater Review
12/14/2023 8:44:06 AM
Review 2: EPC DPW Stormwater comments have been resolved on the following documents:
- Drainage Letter

EPC DPW Stormwater has no further comments. Planner: no re-review necessary.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
12/14/2023 8:44:06 AM
Colorado Springs Public Works
12/12/2023 1:51:07 PM
Traffic Engineering has no comments on this item.

Zaker Alazzeh, P.E.
Traffic Engineering Manager/Deputy City Traffic Engineer
City of Colorado Springs
(719) 385-5468
Zaker.Alazzeh@coloradosprings.gov
12/12/2023 1:51:07 PM
View PCD Engineering Division
10/3/2023 4:09:32 PM
Site Development Plan Engineering Comments 10/3/2023 4:09:32 PM
View PCD Engineering Division
10/3/2023 4:09:12 PM
Drainage Letter Engineering Comments 10/3/2023 4:09:12 PM
View PCD Engineering Division
10/3/2023 4:08:46 PM
Letter of Intent Engineering Comments 10/3/2023 4:08:46 PM
View PCD Project Manager
10/3/2023 8:30:12 AM
Site Development Plan 10/3/2023 8:30:12 AM
View PCD Project Manager
10/3/2023 8:29:56 AM
Lighting Plan 10/3/2023 8:29:56 AM
View PCD Project Manager
10/3/2023 8:29:44 AM
Letter of Intent 10/3/2023 8:29:44 AM
View PCD Project Manager
10/3/2023 8:29:28 AM
Legal Description 10/3/2023 8:29:28 AM
View PCD Project Manager
10/3/2023 8:29:03 AM
Landscape Plan drawings 10/3/2023 8:29:03 AM
PCD Project Manager
10/3/2023 10:01:17 AM
Please see PCD Planning comments in green on the following documents:

-Landscape Plan drawings
-Legal Description
-Lighting Plan
-Site Development Plan


DPW Engineering will upload remaining comments including drainage report.

Joe Letke
Planner II
719-520-7964
10/3/2023 10:01:17 AM
PCD Engineering Division
10/3/2023 4:10:48 PM
Review 1: Review comments on the following documents:

- Letter of Intent
- Site Development Plan
- Drainage Letter

Note: Due to the amount and complexity of comments made additional review comments are expected in the subsequent review.

The Road Impact Fee is applicable to this project and fee will be due with final land use approval.

A Commercial Driveway Access Permit is required prior to the start of construction. Please apply for a driveway access permit through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online.

Reviewed by:
Carlos Hernandez & Charlene Durham P.E.
charlenedurham@elpasoco.com
carloshernandez@elpasoco.com
10/3/2023 4:10:48 PM
Colorado Springs Public Works
10/2/2023 2:28:00 PM
Engineering Development Review Division has the following comments:

1. Cleary show and identify the City of Colorado Springs boundary limits.
2. add the following note:
"All curb, gutter, driveways, pedestrian ramps and sidewalk posing a safety hazard, damaged, exhibiting excessive deterioration or does not meet current City Engineering standards along the City's public right-of-way (ROW) adjacent to the site will need to be removed and replaced prior to the issuance of the Certificate of Occupancy (CO). An on-site meeting can be set up with the Engineering Development Review Division (EDRD) inspector to determine what, if any improvements are required. The EDRD inspector can be reached at 719-385-5977."

Patrick V. Morris
Civil Engineer II
Public Works/Engineering Development Review
City of Colorado Springs
Phone: 719-385-5075
Patrick.morris@coloradosprings.gov
10/2/2023 2:28:00 PM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/29/2023 8:58:09 AM
The only comment that CSU has, is there is an electrical line in the R.O.W on the western edge of the property. It is recommended that locates are performed to ensure that the electrical lines are not across the property lines and under the proposed parking lot.

See attached picture for reference
9/29/2023 8:58:09 AM
Colorado Springs Public Works
9/27/2023 1:50:35 PM
Traffic Engineering has no comments on this item.

Brian Shevock
Public Works/Traffic Engineering
Traffic Engineer
City of Colorado Springs
brian.shevock@coloradosprings.gov
(719) 385-7620
9/27/2023 1:50:35 PM
EPC Stormwater Review
9/25/2023 7:12:28 AM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Letter...(to be uploaded with Development Services comments)

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
9/25/2023 7:12:28 AM
Colorado Springs Fire Department
9/18/2023 1:19:28 PM
No comment. 9/18/2023 1:19:28 PM