Project Review Comments

Back to List


Project Name
Crossroads Mixed Use Underground Detention CDR
Description
Construction drawing review for underground water detention
Location
Parcels
5408007005 5408007005 5408007006 5408007006
Applicant
M&S Civil Consultants, Inc.
Virgil Sanchez ( virgils@mscivil.com )
(719) 491-0818
Virgil Sanchez ( virgils@mscivil.com )
(719) 491-0818
EA Number
EA2055
File Number
CDR232
Project Manager
Ryan Howser
Status
Active
Created
12/9/2022 5:19:16 PM

View: Project Documents



Review Comments (18)

Link Agency Comment
PCD Project Manager
4/25/2023 2:42:58 PM
Planning Division has no comments at this time. 4/25/2023 2:42:58 PM
View EPC Stormwater Review
4/25/2023 11:50:01 AM
O&M Manual 4/25/2023 11:50:01 AM
View EPC Stormwater Review
4/25/2023 11:47:31 AM
GEC Plan 4/25/2023 11:47:31 AM
View EPC Stormwater Review
4/25/2023 11:46:13 AM
Drainage Letter 4/25/2023 11:46:13 AM
View EPC Stormwater Review
4/25/2023 11:42:53 AM
CDs 4/25/2023 11:42:53 AM
EPC Stormwater Review
4/25/2023 11:40:14 AM
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CDs
- Drainage Letter
- GEC Plan
- O&M Manual

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
4/25/2023 11:40:14 AM
County Attorney - Development Review
4/20/2023 3:51:20 PM
It appears that an updated Detention Maintenance Agreement is still needed to address previous comments. 4/20/2023 3:51:20 PM
PCD Engineering Division
4/19/2023 3:24:53 PM
Review 2 comments will be uploaded by the project manager. Review comments on the following documents:

- Construction Drawings
- Drainage Letter

Reviewed by:
Carlos Hernandez
Review Engineer I
carloshernandez@elpasoco.com
4/19/2023 3:24:53 PM
PCD Project Manager
2/1/2023 5:18:06 PM
No planning comments 2/1/2023 5:18:06 PM
View EPC Stormwater Review
1/31/2023 4:10:24 PM
O&M Manual 1/31/2023 4:10:24 PM
View EPC Stormwater Review
1/31/2023 4:09:30 PM
Drainage Letter 1/31/2023 4:09:30 PM
View EPC Stormwater Review
1/31/2023 4:06:28 PM
CDs 1/31/2023 4:06:28 PM
EPC Stormwater Review
1/31/2023 4:15:01 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CDs
- Drainage Letter
- O&M Manual

Note that my orange comments on the three documents listed above are in addition to Gilbert's blue comments that he previously uploaded to EDARP. But you will see his same blue comments on the three docs that I am uploading. His comments have not changed since he previously uploaded them to EDARP.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
1/31/2023 4:15:01 PM
County Attorney - Development Review
1/26/2023 1:05:50 PM
This office concurs with comment #2 from PCD Engineering dated 1/24/23 and will review the amendment once submitted. 1/26/2023 1:05:50 PM
View PCD Engineering Division
1/25/2023 7:31:51 AM
See file for Financial Assurance Estimate Redlines. 1/25/2023 7:31:51 AM
View PCD Engineering Division
1/25/2023 7:31:16 AM
See file for Drainage Letter Redlines. 1/25/2023 7:31:16 AM
View PCD Engineering Division
1/25/2023 7:30:41 AM
See file for Construction Drawing Redlines. 1/25/2023 7:30:41 AM
PCD Engineering Division
1/24/2023 4:39:45 PM
1. Review 1 comments will be uploaded by the project manager. Review comments on the following documents:
- Construction Drawings
- Drainage Letter
- Financial Assurance Estimate
NOTE: Stormwater Team are not included within these redlines but will be uploaded separately at a later date.

2. Replace the pond agreement with a draft amendment document to the recorded detention maintenance agreement that adds the following language/condition: "The district agrees to replace the underground water quality system with an approved aboveground water quality facility should it not function to the required level of performance as outlined in the attached Performance Monitoring Program, both at the owner's expense."

The intent is to leave the existing recorded pond maintenance agreement as is and record a second document as an addendum. Insert the same signature blocks from the previous agreement on the new document.

3. The stormwater engineering team is drafting the Performance Monitoring Program and will be provided to the applicant for review.


Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
1/24/2023 4:39:45 PM