View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Project Manager
10/10/2022 3:16:27 PM |
site plan_2 has been uploaded and approved. | 10/10/2022 3:16:27 PM |
PCD Engineering Division
10/10/2022 11:50:11 AM |
Comments have been resolved. The project manager will upload any approved documents. Reviewed By: Lupe Packman Lupepackman@elpasoco.com |
10/10/2022 11:50:11 AM | |
View |
PCD Project Manager
9/29/2022 2:54:14 PM |
see comments from engineering and planning, minor. | 9/29/2022 2:54:14 PM |
PCD Engineering Division
9/28/2022 9:38:38 AM |
Review comments are as follows: -Provide contours for site plan in areas where grading will occur. -Provide spot elevations on new parking areas. -Update site plan to show existing and proposed items to avoid confusion with what is already constructed on the site. Reviewed By: Lupe Packman lupepackman@elpasoco.com |
9/28/2022 9:38:38 AM |