PCD Project Manager
10/5/2022 8:13:41 AM |
approved. documents have approval letter are uploaded. | 10/5/2022 8:13:41 AM |
PCD Engineering Division
9/26/2022 7:47:28 AM |
Review 1 comments on the following documents have been resolved: - Letter of Intent - Site Plan PCD Engineering has no further comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
9/26/2022 7:47:28 AM | |
Pikes Peak Regional Building Department
9/26/2022 7:14:40 AM |
Any structure being used for commercial use will require a separate address and must be converted to a commercial use structure. Please contact a staff member in Construction Plan Review with Regional Building Department for guidance on how to do so. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
9/26/2022 7:14:40 AM | |
Falcon Fire Protection District
9/23/2022 3:15:36 PM |
Falcon Fire has reviewed this application and has no objections or concerns. | 9/23/2022 3:15:36 PM | |
View |
PCD Project Manager
9/21/2022 8:41:30 AM |
See comments for site plan by engineering and planning manager. | 9/21/2022 8:41:30 AM |
View |
PCD Project Manager
9/21/2022 8:41:02 AM |
See engineering comments for Letter of Intent | 9/21/2022 8:41:02 AM |
PCD Engineering Division
9/21/2022 7:23:29 AM |
Review 1 comments will be uploaded by the project manager. Review comments on the following documents: -Letter of Intent -Site Plan There is no Driveway Access Permit on file for existing driveway. A Driveway Access Permit is required for all access points onto a county maintained road. Please apply for a driveway access permit through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online. Note: Per Resolution 19-471 the Road Impact Fee will be applicable for any new construction and/or land use approval generating new trips to a parcel. The fee will be accessed at building permit application or final land use approval, whichever is last. Please visit: https://publicworks.elpasoco.com/road-impact-fees/ for further information and to see the fee schedule. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
9/21/2022 7:23:29 AM | |
View |
El Paso County Conservation Dist
9/20/2022 11:58:28 AM |
Brief comments attached as a .pdf. | 9/20/2022 11:58:28 AM |
Upper Black Squirrel Creek GWMD
9/7/2022 2:21:24 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. | 9/7/2022 2:21:24 PM | |
View |
PCD Administrative Notice
9/6/2022 11:24:13 AM |
Sent out 7 Letters with Vicinity Maps 9/6/22 | 9/6/2022 11:24:13 AM |
Mountain View Electric Association, Inc.
9/6/2022 10:37:41 AM |
Mountain View Electric Association has no objection to the special use stables | 9/6/2022 10:37:41 AM |