Project Review Comments

Back to List


Project Name
Big Springs Estates Rezone (RR-5)
Description
Rezone from A-35 to RR-2.5
Location
Parcels
1300000096 1300000096
Applicant
Silver Cloud Properties, LLC
Silver Cloud Properties, LLC ( a.graber1@gmail.com )
(970) 381-4989
Silver Cloud Properties, LLC ( a.graber1@gmail.com )
(970) 381-4989
EA Number
EA22119
File Number
P256
Project Manager
Joe Letke
Status
Active
Created
8/9/2022 12:22:26 PM

View: Project Documents



Review Comments (7)

Link Agency Comment
Pikes Peak Regional Building Department
3/26/2025 8:27:08 AM
Enumerations has no comment or objection to this zone change. Enumerations will have more specific comments to the plat submittal mentioned in the letter of intent.

Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
3/26/2025 8:27:08 AM
EPC Stormwater Review
3/24/2025 3:14:15 PM
Review 1: EPC DPW Stormwater does not have comments on any of the submitted documents.

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
3/24/2025 3:14:15 PM
PCD Administrative Notice
3/17/2025 3:58:49 PM
On 03/17/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (7 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $4.83. JM 3/17/2025 3:58:49 PM
Tri-County Fire Protection District
3/14/2025 12:02:46 PM
The Tri-County Fire Department has no objections to the zoning change to an R-5. However, be advised that any building and development on an R-5 must comply with Section 6.3.3. Fire Protection and Wildfire Mitigation of the Land Development Code and will be required to have a fire protection water supply. 3/14/2025 12:02:46 PM
View EPC Environmental Services
3/12/2025 12:13:08 PM
3/12/2025 12:13:08 PM
EPC Parks Department
3/11/2025 9:09:40 AM
El Paso County Parks and Community Services. The 2022 El Paso County Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. As such, no trail easements or park land dedications are necessary. As this is a rezone application, no regional park fees will be assessed at this point in the process, however, regional park fees will be assessed during the preliminary plan stage and required at time of the recording of the forthcoming final plat. Thank you! 3/11/2025 9:09:40 AM
County Attorney - Development Review
3/10/2025 2:29:48 PM
No comments at this time. 3/10/2025 2:29:48 PM