Project Review Comments

Back to List


Project Name
Owl Place Deviation for underground WQ
Description
Deviation request for underground water quality
Location
Parcels
5301001015 5301001015
Applicant
DREXEL, BARRELL & CO.
Kate Varnum ( kvarnum@drexelbarrell.com )
(719) 260-0887
Kate Varnum ( kvarnum@drexelbarrell.com )
(719) 260-0887
EA Number
EA21191
File Number
DEV223
Project Manager
Kylie Bagley
Status
Active
Created
8/4/2022 9:04:10 AM

View: Project Documents



Review Comments (9)

Link Agency Comment
View EPC Stormwater Review
4/27/2023 4:10:27 PM
Deviation Request 4/27/2023 4:10:27 PM
View EPC Stormwater Review
4/27/2023 4:09:55 PM
Conditions of Approval for UG WQ 4/27/2023 4:09:55 PM
PCD Project Manager
4/18/2023 10:13:28 AM
The planning department has no comments at this time 4/18/2023 10:13:28 AM
PCD Engineering Division
4/13/2023 4:50:37 PM
Review 2 comments on the following documents will be uploaded by the stormwater engineer:
-Deviation request

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
4/13/2023 4:50:37 PM
EPC Stormwater Review
4/27/2023 4:09:40 PM
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Conditions of Approval for UG WQ
- Deviation Request

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
4/27/2023 4:09:40 PM
PCD Project Manager
9/16/2022 1:13:24 PM
no comments from the planning department at this time 9/16/2022 1:13:24 PM
View PCD Engineering Division
9/15/2022 8:30:56 AM
Deviation request redlines 9/15/2022 8:30:56 AM
EPC Stormwater Review
9/14/2022 5:30:50 PM
Review 1: Please see PCD comments. Due to the volume or complexity of the comments provided, these comments are cursory in nature and EPC Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
GlennReese@elpasoco.com
9/14/2022 5:30:50 PM
PCD Engineering Division
9/14/2022 3:09:31 PM
Review 1 comments on the following documents will be uploaded:
-Deviation Request


reviewed by:
Daniel Torres
danieltorres@elpasoco.com
9/14/2022 3:09:31 PM