Project Review Comments
- Project Name
- Lewis Palmer SD38 Trail System Site Development Plan
- Description
- Site Development Plan for trail system - all trails proposed to be located within public ROW, or on private property within designated trail / open space easements, or designated common areas. No approval of location is necessary for this project.
- Location
- Parcels
- 7111000028 7111000028 7111304014 7111304014 7111400008 7111400008 7111404032 7111404032 7111405001 7111405001 7114205030 7114205030
- Applicant
-
JR Engineering
Glenn Ellis ( gellis@jrengineering.com )
(303) 267-6241 Glenn Ellis ( gellis@jrengineering.com )
(303) 267-6241 - EA Number
- EA2148
- File Number
- PPR2240
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 7/7/2022 7:17:47 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
2/27/2024 10:06:56 AM |
Engineering has no comments. Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
2/27/2024 10:06:56 AM | |
Woodmoor Water and Sanitation District
4/5/2023 4:09:37 PM |
Woodmoor Water and Sanitation District No 1 and Lewis Palmer School District 38 are working to finalize an intergovernmental agreement. This agreement will need to be signed and recorded prior to WWSD approval of this plan set. | 4/5/2023 4:09:37 PM | |
PCD Engineering Division
4/3/2023 11:32:05 AM |
EPC Engineering has no further comments at this time. Reviewed by: Charlene Durham, P.E. charlenedurham@elpasoco.com |
4/3/2023 11:32:05 AM | |
EPC Stormwater Review
3/29/2023 11:35:07 AM |
All EPC DPW Stormwater comments have been addressed. Please sign/date/stamp and resubmit the following documents: - PBMP Applicability Form Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
3/29/2023 11:35:07 AM | |
PCD Engineering Division
3/23/2023 5:00:37 PM |
Review 3: EPC Engineering Comments have been addressed. Please provide copies of signed and sealed documents. Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
3/23/2023 5:00:37 PM | |
View |
PCD Engineering Division
1/23/2023 7:38:26 AM |
Site Development plan comments | 1/23/2023 7:38:26 AM |
View |
PCD Engineering Division
1/23/2023 7:37:57 AM |
GEC Plan comments | 1/23/2023 7:37:57 AM |
View |
PCD Engineering Division
1/23/2023 7:37:35 AM |
FAE Comments | 1/23/2023 7:37:35 AM |
View |
PCD Engineering Division
1/23/2023 7:37:16 AM |
Drainage report comments | 1/23/2023 7:37:16 AM |
View |
EPC Stormwater Review
1/18/2023 3:13:11 PM |
SWMP Checklist_v2 | 1/18/2023 3:13:11 PM |
View |
EPC Stormwater Review
1/18/2023 3:11:33 PM |
SWMP_v2 | 1/18/2023 3:11:33 PM |
View |
EPC Stormwater Review
1/18/2023 3:10:30 PM |
ESQCP_v2 | 1/18/2023 3:10:30 PM |
View |
EPC Stormwater Review
1/18/2023 3:10:13 PM |
GEC Checklist_v2 | 1/18/2023 3:10:13 PM |
EPC Stormwater Review
1/18/2023 2:44:50 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - ESQCP - SWMP - SWMP Checklist The following documents will be reviewed with the next submittal: - FAE Please sign/date/stamp and resubmit the following documents: - PBMP Applicability Form Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
1/18/2023 2:44:50 PM | |
PCD Engineering Division
1/23/2023 7:31:37 AM |
Review 2: EPC Engineering Comments have been provided on the following documents: -Site Development Plan -Drainage Report -FAE -GEC Plans Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
1/23/2023 7:31:37 AM | |
Woodmoor Water and Sanitation District
12/20/2022 1:44:16 PM |
Woodmoor Water and Sanitation District (WWSD) and Lewis Palmer School District 38 (LPSD) are working together on an Intergovernmental Agreement (IGA) for use of the Woodmoor Lake access road as a part of this trail system. Until this agreement is signed and recorded, WWSD will be unable to provide final approval on these plans, although WWSD has no comments on the plans themselves as they stand currently. | 12/20/2022 1:44:16 PM | |
View |
EPC Health Department
8/26/2022 4:53:51 PM |
8/26/2022 4:53:51 PM | |
View |
PCD Engineering Division
8/3/2022 3:25:08 PM |
Redlines Plot Plan Dwgs | 8/3/2022 3:25:08 PM |
PCD Engineering Division
8/2/2022 7:51:45 AM |
Review 1: EPC Engineering Comments have been provided on the following uploaded documents: -Plot Plan Drawings. Also, since over 1 acre of area is to be disturbed, the following documents will need to be provided on the next submittal: - ESQCP - GEC Plans - GEC Checklist - SWMP Report - SWMP Checklist - PBMP Applicability Form - Financial Assurance Estimate - Drainage Report Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com |
8/2/2022 7:51:45 AM | |
PCD Project Manager
7/29/2022 11:43:09 AM |
Planning Division has no comments - all trails are proposed to be located within public ROW, or on private property within designated trail / open space easements, or designated common areas. No approval of location is necessary for this project. | 7/29/2022 11:43:09 AM | |
Woodmoor Water and Sanitation District
7/28/2022 8:29:17 AM |
Woodmoor Water and Sanitation District No. 1 (WWSD) and Lewis Palmer School District No. 38 (LPSD) are collaborating on an Intergovernmental Agreement regarding use of a portion of WWSD property. This Agreement is currently incomplete, so WWSD is unable to give approval for the submitted plans, although we have no further comments on the plans themselves. | 7/28/2022 8:29:17 AM | |
Mountain View Electric Association, Inc.
7/19/2022 2:38:35 PM |
Mountain View Electric Association has no objection to the current plan. | 7/19/2022 2:38:35 PM | |
Tri-Lakes-Monument Fire Protection District
7/18/2022 3:19:01 PM |
Great project and it makes the pedestrians safer! JCB | 7/18/2022 3:19:01 PM | |
View |
EPC Parks Department
7/15/2022 8:25:48 AM |
See final Parks comments attached. Thanks, Greg |
7/15/2022 8:25:48 AM |
911 Authority - El Paso/Teller County
7/11/2022 10:47:09 AM |
No action for E911 on this submittal. Thank you. Justin |
7/11/2022 10:47:09 AM | |
View |
EPC Environmental Services
7/7/2022 11:45:14 AM |
7/7/2022 11:45:14 AM |