Project Review Comments

Back to List


Project Name
Crossroads Mixed Use Filing No. 2
Description
Two (2) commercial lots and future development tracts. Crossroads Mixed Use Filing 1 SF-21-029
Location
Parcels
5408007005 5408007005 5408007006 5408007006 5408305005 5408305005
Applicant
Kimley-Horn
Jim Houk ( jhouk@ttplan.net )
(719) 284-7830
Jim Houk ( jhouk@ttplan.net )
(719) 284-7830
EA Number
EA2055
File Number
SF2238
Project Manager
Ryan Howser
Status
Closed
Created
7/1/2022 9:21:17 AM

View: Project Documents



Review Comments (61)

Link Agency Comment
View County Attorney - Development Review
11/29/2023 12:11:14 PM
Signature to SIA attached. 11/29/2023 12:11:14 PM
PCD Engineering Division
10/11/2023 10:25:20 AM
Review comments have been resolved. The project manager will upload any approved documents.

Reviewed By:
Lupe Packman
lupepackman@elpasoco.com
10/11/2023 10:25:20 AM
View Colorado Department of Transportation - Pueblo Office
10/6/2023 12:38:04 PM
10/6/2023 12:38:04 PM
View PCD Engineering Division
9/13/2023 4:05:41 PM
GEC Plan Redlines 9/13/2023 4:05:41 PM
View PCD Engineering Division
9/13/2023 4:04:11 PM
Construction Drawings Redlines 9/13/2023 4:04:11 PM
View PCD Engineering Division
9/13/2023 4:03:41 PM
Drainage Report Redlines 9/13/2023 4:03:41 PM
PCD Engineering Division
9/13/2023 3:57:43 PM
Review 4 comments on the following documents:
-Drainage Report
-CD's
-GEC Plan

reviewed by:
Carlos Hernandez & Daniel Torres
carloshernandez@elpasoco.com & danieltorres@elpasoco.com
9/13/2023 3:57:43 PM
PCD Project Manager
8/31/2023 9:40:59 AM
Planning Division has no comments at this time. 8/31/2023 9:40:59 AM
County Attorney - Water
6/22/2023 4:27:25 PM
Because the requirements of the preliminary plan water review were not met, an amended water sufficiency finding will be provided in connection with the preliminary plan to enable this application to be reviewed administratively. 6/22/2023 4:27:25 PM
PCD Project Manager
6/21/2023 8:40:10 AM
Due to the deviation being denied, you will need to revise the FAE and GEC plan to reflect the sidewalks being added back in. Please let the PCD Project Manager know if any other documents will also need to be revised as a result of this change to the plan. 6/21/2023 8:40:10 AM
View PCD Project Manager
6/21/2023 8:03:25 AM
Deviation for sidewalk - Denied 6/21/2023 8:03:25 AM
View PCD Project Manager
6/21/2023 8:02:48 AM
Engineering comments - drainage report (includes markup summary) 6/21/2023 8:02:48 AM
View PCD Project Manager
6/21/2023 8:01:38 AM
Engineering comments - Construction drawings (includes markup summary) 6/21/2023 8:01:38 AM
PCD Project Manager
6/21/2023 8:00:14 AM
PCD Planning Division ahs no further comments at this time. 6/21/2023 8:00:14 AM
PCD Engineering Division
6/20/2023 5:04:39 PM
Review comments will be uploaded by the project manager for the following documents:

-Drainage report
-Construction drawings

Denied deviation will be uploaded by the project manager.

Reviewed By:
Lupe Packman
lupepackman@elpasoco.com
6/20/2023 5:04:39 PM
EPC Stormwater Review
6/1/2023 5:12:49 PM
Review 3: EPC DPW Stormwater comments have been resolved on the following documents:
- Drainage Report
- ESQCP
- GEC Plan

EPC DPW Stormwater has no further comments. Planner: no re-review necessary.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
6/1/2023 5:12:49 PM
View Colorado Division of Water Resources
5/16/2023 12:45:03 PM
5/16/2023 12:45:03 PM
County Attorney - Water
5/13/2023 9:10:37 PM
Please address the concerns expressed by the State Engineer's Office in its letter dated 1/24/23. This office will complete its water review upon receipt of a favorable recommendation from the SEO. 5/13/2023 9:10:37 PM
911 Authority - El Paso/Teller County
5/2/2023 7:25:49 AM
No action for E911 on this submittal.
Thank you.
Justin.
5/2/2023 7:25:49 AM
View PCD Project Manager
4/28/2023 8:33:27 AM
Final plat - Planning comments 4/28/2023 8:33:27 AM
View PCD Project Manager
4/28/2023 8:29:11 AM
Drainage report - Engineering and Stormwater comments 4/28/2023 8:29:11 AM
View PCD Project Manager
4/28/2023 8:28:44 AM
CDs - Engineering comments 4/28/2023 8:28:44 AM
PCD Project Manager
4/28/2023 7:27:03 AM
WSIS water calculations do not match the water resources report. 4/28/2023 7:27:03 AM
PCD Project Manager
4/28/2023 8:34:18 AM
Review 2: Planning Division has comments on the following documents
- Water Supply Information Summary (WSIS)
- Final plat
4/28/2023 8:34:18 AM
View EPC Stormwater Review
4/27/2023 2:11:14 PM
GEC Plan 4/27/2023 2:11:14 PM
View EPC Stormwater Review
4/27/2023 2:10:33 PM
ESQCP 4/27/2023 2:10:33 PM
PCD Engineering Division
4/27/2023 2:49:06 PM
Address review 2 comments on the following documents:
-Drainage report
-Construction drawings

Comments have been resolved for the following:
-GEC plan
-Final plat
-FAE
-CDOT permit
-TIS

Sign all engineering documents with appropriate stamps and signatures that follow DORA regulations.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
4/27/2023 2:49:06 PM
Colorado Springs Airport Advisory Commission
4/27/2023 8:40:10 AM
Colorado Springs Airport had no additional comments to provide on this item beyond those previously provided. 4/27/2023 8:40:10 AM
EPC Stormwater Review
4/27/2023 2:10:04 PM
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...(to be uploaded by PM with Development Services comments)
- ESQCP
- GEC Plan

EPC DPW Stormwater comments have been resolved on the following documents:
- FAE
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
4/27/2023 2:10:04 PM
View Colorado Department of Transportation - Pueblo Office
4/20/2023 2:40:27 PM
4/20/2023 2:40:27 PM
View PCD Engineering Division
2/9/2023 3:19:56 PM
TIS V1 Redlines 2/9/2023 3:19:56 PM
View PCD Engineering Division
2/9/2023 3:19:33 PM
Drainage Report V1 Redlines 2/9/2023 3:19:33 PM
View PCD Engineering Division
2/9/2023 2:40:51 PM
ESQCP V1 Redlines 2/9/2023 2:40:51 PM
View PCD Engineering Division
2/9/2023 2:39:09 PM
Final Plat V1 Redlines 2/9/2023 2:39:09 PM
View PCD Engineering Division
2/9/2023 2:38:39 PM
GEC Plan V1 Redlines 2/9/2023 2:38:39 PM
View PCD Engineering Division
2/9/2023 2:38:09 PM
FAE V1 Redlines 2/9/2023 2:38:09 PM
View PCD Engineering Division
2/9/2023 2:37:42 PM
CDOT Permit V1 Redlines 2/9/2023 2:37:42 PM
View PCD Engineering Division
2/9/2023 2:37:16 PM
Construction Drawings V1 Redlines 2/9/2023 2:37:16 PM
PCD Project Manager
2/8/2023 8:34:40 AM
Planning Division has comments on the final plat as well. Comments will be uploaded with Engineering review comments. 2/8/2023 8:34:40 AM
View PCD Project Manager
2/8/2023 8:34:17 AM
LOI comments 2/8/2023 8:34:17 AM
View PCD Project Manager
2/8/2023 8:33:37 AM
Water report comments 2/8/2023 8:33:37 AM
View PCD Project Manager
2/8/2023 8:33:24 AM
Wastewater report comments 2/8/2023 8:33:24 AM
View PCD Project Manager
2/8/2023 8:33:10 AM
Soils & geology report comments 2/8/2023 8:33:10 AM
View EPC Stormwater Review
2/2/2023 2:53:07 PM
SWMP Checklist 2/2/2023 2:53:07 PM
View EPC Stormwater Review
2/2/2023 2:52:46 PM
SWMP 2/2/2023 2:52:46 PM
View EPC Stormwater Review
2/2/2023 2:52:28 PM
PBMP Applicability Form 2/2/2023 2:52:28 PM
View EPC Stormwater Review
2/2/2023 2:52:14 PM
GEC Checklist 2/2/2023 2:52:14 PM
EPC Stormwater Review
2/2/2023 2:49:24 PM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...(to be uploaded by PM with PCD comments)
- ESQCP.................(to be uploaded by PM with PCD comments)
- FAE.......................(to be uploaded by PM with PCD comments)
- GEC Plan..............(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
2/2/2023 2:49:24 PM
PCD Engineering Division
2/9/2023 3:20:36 PM
Address review 1 comments on the following documents:

-Drainage report
-TIS
-FAE
-GEC plan
-Final plat
-Construction drawings
-CDOT access permit

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
2/9/2023 3:20:36 PM
View Cherokee Metro Dist
1/30/2023 2:12:59 PM
This version of the plans is rejected subject to the comments in the attached file 1/30/2023 2:12:59 PM
View Colorado Division of Water Resources
1/24/2023 3:00:36 PM
1/24/2023 3:00:36 PM
Colorado Springs Airport Advisory Commission
1/17/2023 4:15:49 PM
The following comments will be presented at the January 25, 2023 Airport Advisory Commission meeting:

Airport staff recommends no objection with the following conditions:

• Avigation Easement: Proof of Avigation Easement filing noted on plat previous submittal documentation (Recorded at Reception No. 203019547 and Reception No. 206095824); no further action is required.

• Noise: Although the proposed development will be located outside of the 65 DNL noise contour, the developer is encouraged to work with the airport for noise mitigation measures and procedures. The developer should notify tenants of potential noise impacts in their lease agreement, or wherever appropriate, to ensure all future tenants are made aware of noise impacts associated with aircraft overflight.

• FAA Form 7460-1: Based on elevation data and distance to runway, the applicant will need to file Federal Aviation Administration (FAA) Form 7460-1 “Notice of Proposed Construction or Alteration” for any new vertical development at this site, including temporary construction equipment, and provide FAA documentation to the Airport before the commencement of construction activities; FAA’s website (https://oeaaa.faa.gov/oeaaa/external/portal.jsp).
1/17/2023 4:15:49 PM
View Parks Advisory Board
1/17/2023 2:13:43 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (No PAB endorsement necessary for non-land-dedication commercial applications) 1/17/2023 2:13:43 PM
View EPC Parks Department
1/17/2023 2:12:07 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (No PAB endorsement necessary for non-land-dedication commercial applications) 1/17/2023 2:12:07 PM
County Attorney - Development Review
1/12/2023 5:25:36 PM
No proposed edits to SIA. 1/12/2023 5:25:36 PM
County Attorney - Water
1/12/2023 5:13:02 PM
County Attorney's Office will complete its water review upon receipt of a letter from the Division of Water Resources. 1/12/2023 5:13:02 PM
Pikes Peak Regional Building Department
1/12/2023 10:22:12 AM
Standard Final Plat Comments:
a. Enumerations will review the mylar prior to plat for address placement, street names, and title block.
b. A $10.00 per lot and tract platting fee will be due at the time of the review of the mylar, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. As of September 28th, 2022, an additional over the phone transaction fee of 2.95% of the total transaction will apply for any credit card payment.
c. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org (Please email the Enumerations staff that reviewed your project).
d. Mylar reviews can be reviewed via “pdf”. The mylar will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations receiving payment. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
1/12/2023 10:22:12 AM
View EPC Environmental Services
1/11/2023 2:08:37 PM
1/11/2023 2:08:37 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/6/2023 4:07:12 PM
No comments on this application.
cmasoumi@csu.org
1/6/2023 4:07:12 PM
911 Authority - El Paso/Teller County
1/5/2023 7:45:14 AM
Comments for E911 as follows:

Pacific Rail Way – Name reserved as Pacific Rail Pt. Acceptable suffixes (Grove, Heights, Point, or View).
Central Rail Pt – Available

Thank you
Justin
1/5/2023 7:45:14 AM
Mountain View Electric Association, Inc.
1/3/2023 11:50:00 AM
This is not in MVEA territory 1/3/2023 11:50:00 AM