Project Review Comments

Back to List


Project Name
State Highway 115 Orton Borrow Pit and Steer Batch Plant
Description
Grading and Erosion Control Plan XREF three Temp uses: temporary batch plant, construction related mining, and construction office & equipment (no more than 24 months). Includes site plan for batch plant & storage area construction offices and GEC; XREF Temp uses
Location
Parcels
7500000236 7500000236 7700000025 7700000025
Applicant
Castle Rock Construction Company
Travis Bell ( tbell@crccllc.com )
(720) 273-6227
Travis Bell ( tbell@crccllc.com )
(720) 273-6227
EA Number
EA2288
File Number
CDR2211
Project Manager
Kari Parsons
Status
Closed
Created
5/18/2022 9:08:18 AM

View: Project Documents



Review Comments (36)

Link Agency Comment
View Colorado Department of Public Health and Environment
10/28/2022 1:54:44 PM
Find our standard comments attached. 10/28/2022 1:54:44 PM
View El Paso County Conservation Dist
10/18/2022 6:25:56 PM
Brief comments attached as a .pdf. 10/18/2022 6:25:56 PM
PCD Engineering Division
10/18/2022 4:40:56 PM
PCD engineering comments have been resolved. Please submit signed engineering documents (by developer & engineer) for approval by ECM administrator.

Kari: a 7 day turnaround is sufficient for the resubmittal

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
10/18/2022 4:40:56 PM
EPC Stormwater Review
10/18/2022 11:58:57 AM
Re-Review - Batch Plant Only:

EPC Stormwater comments have been resolved on the following documents:
- Drainage Report
- ESQCP
- FAE
- GEC Plan
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

EPC Stormwater has no further comments. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
GlennReese@elpasoco.com
10/18/2022 11:58:57 AM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/13/2022 11:14:50 AM
If you are near CSU existing southern delivery water main or easement with this project, you will need to submit a plan into CSU for review. 10/13/2022 11:14:50 AM
View Colorado Division of Water Resources
10/11/2022 10:05:20 AM
Please see comments submitted on August 29, 2022 (attached). 10/11/2022 10:05:20 AM
911 Authority - El Paso/Teller County
10/7/2022 8:08:50 AM
No action for E911 on this submittal.
Thank you.
Justin
10/7/2022 8:08:50 AM
View EPC Environmental Services
10/6/2022 1:02:13 PM
10/6/2022 1:02:13 PM
Colorado Department of Transportation - Pueblo Office
9/21/2022 8:17:36 AM
The Traffic comments for the CRCC Orton Borrow Pit are modified as follows:

Section 2.14(4) of the SHAC indicates the following: A public highway reconstruction project is not required to bring legal access into full compliance with the current Code standards.

The access point will be used temporarily for a total of approximately 40 day over the life of the project ( 2 years)

A left turn acceleration lane at the access point is required per the applicant's submission; detail provided in the application. The acceleration lane can be installed using existing pavement and therefore is minimal cost to the project.

The MHT for the access point will be revised to include an advisory speed limit of 45 mph under the TRUCK ENTERING sign. A NO LEFT TURN sign is also required for the NB SH115 movement to prohibit left turn into the access from occurring.

Please let me know if you have any questions.
9/21/2022 8:17:36 AM
View Colorado Department of Transportation - Pueblo Office
9/19/2022 3:06:37 PM
9/19/2022 3:06:37 PM
PCD Engineering Division
9/13/2022 4:17:12 PM
Engineering comments on the Orton Pit portion of the development have been resolved. The documents will be uploaded by the project manger once approved by the ECM administrator.

Please address the previous comments on the batch plant portion of the development and submit for review.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
9/13/2022 4:17:12 PM
PCD Project Manager
9/13/2022 7:45:07 AM
Please show limit of disturbance lines on the site plan so that adj prop owners can be assured setbacks will be met. ; show access points to pit, and parking area of pit. Is there a loading or laydown area? or temp lighting (provide detail and locations) ?
This will also be uploaded as temp use site plan with the letter of intent.
9/13/2022 7:45:07 AM
PCD Project Manager
9/13/2022 7:35:56 AM
Once the Ortin Pit component documents have been approved, please the temporary use in EDARP which is self initiated on EDARP main page. 9/13/2022 7:35:56 AM
EPC Stormwater Review
9/8/2022 6:30:19 PM
Review 2: EPC Stormwater comments have been resolved on the following documents:
- Drainage Report
- ESQCP
- GEC Plan
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist (Orton)

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
GlennReese@elpasoco.com
9/8/2022 6:30:19 PM
View Colorado Division of Water Resources
8/29/2022 1:01:07 PM
8/29/2022 1:01:07 PM
View Colorado Department of Public Health and Environment
8/5/2022 11:59:26 AM
CDPHE Comments attached 8/5/2022 11:59:26 AM
View PCD Engineering Division
8/4/2022 4:10:14 PM
ESQCP redlines 8/4/2022 4:10:14 PM
View PCD Engineering Division
8/4/2022 4:08:37 PM
Please use the 2022 El Paso County Financial Assurance Estimate Form (FAE). An excel version has also been attached to the FAE redlines document. 8/4/2022 4:08:37 PM
View PCD Engineering Division
8/4/2022 4:02:04 PM
FAE redlines 8/4/2022 4:02:04 PM
View PCD Engineering Division
8/4/2022 4:01:41 PM
Access Permit redlines 8/4/2022 4:01:41 PM
View PCD Engineering Division
8/4/2022 4:01:15 PM
Haul Route redlines 8/4/2022 4:01:15 PM
View PCD Engineering Division
8/4/2022 4:00:44 PM
GEC Plan redlines 8/4/2022 4:00:44 PM
View PCD Engineering Division
8/4/2022 3:59:21 PM
Drainage Report redlines 8/4/2022 3:59:21 PM
View PCD Engineering Division
8/4/2022 3:58:35 PM
Traffic Impact Study Redlines 8/4/2022 3:58:35 PM
View PCD Engineering Division
8/4/2022 3:57:41 PM
Letter of Intent redlines 8/4/2022 3:57:41 PM
View EPC Stormwater Review
8/4/2022 3:01:08 PM
SWMP Checklist (Rock Creek) 8/4/2022 3:01:08 PM
View EPC Stormwater Review
8/4/2022 3:00:49 PM
SWMP Checklist (Orton) 8/4/2022 3:00:49 PM
View EPC Stormwater Review
8/4/2022 3:00:30 PM
SWMP 8/4/2022 3:00:30 PM
View EPC Stormwater Review
8/4/2022 2:59:49 PM
PBMP Applicability Form 8/4/2022 2:59:49 PM
View EPC Stormwater Review
8/4/2022 2:59:33 PM
GEC Checklist 8/4/2022 2:59:33 PM
EPC Stormwater Review
8/4/2022 2:59:12 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report....(to be uploaded by PM with PCD comments)
- ESQCP...................(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist (Orton)
- SWMP Checklist (Rock Creek)

Please provide the following documents upon resubmittal:
- FAE

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
GlennReese@elpasoco.com
8/4/2022 2:59:12 PM
PCD Project Manager
8/3/2022 12:20:09 PM
Please change title of letter intent to "Temporary Use Constructed Related Mining "
and "Temporary Use Construction Related Batch Plant"

Edit all documents to read "Temporary Use" throughout letters and full application not special use.
8/3/2022 12:20:09 PM
PCD Engineering Division
8/3/2022 4:40:37 PM
Review 1 comments on the following documents will be uploaded:
-Letter of Intent
-Traffic Impact Study: Please see comments and provide a traffic study per ECM Appendix B by a licensed civil engineer.
-Drainage report: Please also submit a drainage report for the concrete batch plant site.
-GEC Plan
-Haul Route
-Access permit
-FAE



reviewed by:
Daniel Torres
danieltorres@elpasoco.com
8/3/2022 4:40:37 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/29/2022 3:29:42 PM
I have no review comments of the above name project Al 7/29/2022 3:29:42 PM
911 Authority - El Paso/Teller County
7/14/2022 8:06:42 AM
No action for E911 on this submittal.
Thank you.
Justin
7/14/2022 8:06:42 AM
Hanover Fire Protection District
7/13/2022 1:58:03 PM
This will be in HWY 115 Fire Protection District. Please send this packet to Chief Wright Chief115vfd@gmail.com 7/13/2022 1:58:03 PM