Project Review Comments
- Project Name
- Solace at Cimarron Hills Site Development Plan
- Description
- Site development plan for Solace filing 2
- Location
- Parcels
- 5407205047 5407205047
- Applicant
-
Jackson Dearborn Partners
Dane Olmstead ( dolmstead@jacksondearborn.com )
(734) 216-2577 Dane Olmstead ( dolmstead@jacksondearborn.com )
(734) 216-2577 - EA Number
- EA2284
- File Number
- PPR2252
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 5/17/2022 11:41:34 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
4/26/2023 5:11:52 PM |
No additional comments. Please submit signed engineering documents with the final plat application. reviewed by: Daniel Torres danieltorres@elpasoco.com |
4/26/2023 5:11:52 PM | |
PCD Project Manager
4/26/2023 5:11:46 PM |
Planning Division has no further comments at this time. Staff will not approve this application until the final plat has been approved and recorded. | 4/26/2023 5:11:46 PM | |
View |
PCD Project Manager
3/30/2023 11:53:12 AM |
Site development plan comments | 3/30/2023 11:53:12 AM |
PCD Project Manager
3/30/2023 11:41:42 AM |
Please also include the landscape improvements in the FAE. | 3/30/2023 11:41:42 AM | |
View |
PCD Engineering Division
3/30/2023 9:53:20 AM |
Financial Assurance Estimate Form redlines | 3/30/2023 9:53:20 AM |
PCD Engineering Division
3/30/2023 9:50:39 AM |
Review 3 comments on the following documents have been uploaded: -Financial assurance estimate form No additional comments on the following documents at this time: Letter of intent Drainage report Staff reserves the right to make additional comments to the drainage report and financial assurance estimate form with the review of the Construction Documents with the final plat application. reviewed by: Daniel Torres danieltorres@elpasoco.com |
3/30/2023 9:50:39 AM | |
View |
PCD Engineering Division
1/19/2023 5:19:06 PM |
Site Development Plan Redlines | 1/19/2023 5:19:06 PM |
View |
PCD Engineering Division
1/19/2023 5:17:37 PM |
Lighting Plan Redlines | 1/19/2023 5:17:37 PM |
View |
PCD Engineering Division
1/19/2023 5:17:11 PM |
Letter of intent Redlines | 1/19/2023 5:17:11 PM |
PCD Engineering Division
1/19/2023 5:16:02 PM |
Review 2 engineering comments on the following documents have been provided on the final plat application (SF2232) associated with this project. -Letter of Intent -Drainage report -FAE Comments on the following documents have provided by the planning department: -Letter of Intent -Site Development Plan -Lighting Plan Engineering comments on the following documents have been resolved: -PBMP Applicability Form -Site development Plan reviewed by: Daniel Torres danieltorres@elpasoco.com |
1/19/2023 5:16:02 PM | |
EPC Stormwater Review
1/18/2023 1:19:26 PM |
Review 2: All Stormwater comments have been addressed. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
1/18/2023 1:19:26 PM | |
PCD Project Manager
1/17/2023 12:51:58 PM |
Planning Division has completed review. Comments will be uploaded when Engineering Division has completed their review. | 1/17/2023 12:51:58 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/5/2023 2:04:52 PM |
This project is located in the Cherokee Water District, and CSU only provides gas and electrical services in this area. To determine the final gas/electric meter, transformer, and service line locations, contact a CSU Field Engineer. If you have any questions, please call Field Engineering at 719-668-4985 (gas) or 719-668-5564 (electric). cmasoumi@csu.org |
1/5/2023 2:04:52 PM | |
View |
EPC Health Department
12/29/2022 6:46:22 PM |
12/29/2022 6:46:22 PM | |
View |
Colorado Department of Transportation - Pueblo Office
12/29/2022 9:19:49 AM |
Previous comments still apply. Please refer to letter dated December 4, 2022. | 12/29/2022 9:19:49 AM |
View |
PCD Project Manager
11/4/2022 1:39:08 PM |
SDP comments | 11/4/2022 1:39:08 PM |
View |
PCD Project Manager
11/4/2022 1:38:58 PM |
Lighting plan comments | 11/4/2022 1:38:58 PM |
View |
PCD Project Manager
11/4/2022 1:38:44 PM |
LOI comments | 11/4/2022 1:38:44 PM |
View |
PCD Project Manager
11/4/2022 1:38:33 PM |
Landscape plan comments | 11/4/2022 1:38:33 PM |
View |
PCD Project Manager
11/4/2022 1:26:05 PM |
Please see attached for the checklist for site development plan LOI. | 11/4/2022 1:26:05 PM |
PCD Project Manager
11/4/2022 1:18:44 PM |
General comment on all documents - name of project is inconsistent throughout. In some places it is referred to as Cimarron Hills Phase 2" and in other places it is referred to as "Solace Apartments." Please verify correct name and ensure it is reflected on all documents. | 11/4/2022 1:18:44 PM | |
PCD Project Manager
11/4/2022 12:41:18 PM |
Application submitted is for a final plat. Please provide a new application for a site development plan. | 11/4/2022 12:41:18 PM | |
EPC Stormwater Review
11/3/2022 10:24:33 AM |
Review 1: Please see EPC Stormwater comments on SF2232. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
11/3/2022 10:24:33 AM | |
PCD Engineering Division
11/3/2022 2:02:22 PM |
Review 1 comments on the following documents have been provided on the final plat application (SF2232) associated with this project. -Letter of Intent -Drainage report -PBMP Applicability Form -FAE Comments on the following documents will be uploaded by the project manager: -Site Development Plan reviewed by: Daniel Torres danieltorres@elpasoco.com |
11/3/2022 2:02:22 PM | |
Cherokee Metro Dist
10/31/2022 11:00:25 AM |
Cherokee has no comments on this SDP. However we have outstanding comments on the utility plans and service details which were uploaded separately. | 10/31/2022 11:00:25 AM | |
Pikes Peak Regional Building Department
10/31/2022 10:38:48 AM |
Regarding a request for approval of a development plan for Solace Apartments Filing No. 2, Enumerations has the following comments: 1. The configuration of this project has not changed since an addressing plan was established in 2021 and these addresses are still valid. These addresses should be used when submitting building plans for permitting. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
10/31/2022 10:38:48 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/31/2022 9:42:27 AM |
Ryan, I need a Preliminary Public and Facility Plan in place so that I can do my review I did not see one in any of the project folders Al | 10/31/2022 9:42:27 AM | |
View |
Colorado Springs Airport Advisory Commission
10/27/2022 7:46:00 AM |
The attached summary with comments was presented at the October 26, 2022 Airport Advisory Commission meeting with no additional comments. | 10/27/2022 7:46:00 AM |
View |
EPC Parks Department
10/19/2022 8:45:27 AM |
See final Parks comments attached. A concurrent final plat plan will be presented to the Park Advisory Board in November. | 10/19/2022 8:45:27 AM |
RBD Floodplain
10/12/2022 12:43:55 PM |
According to the site development plan for Solace Apartments Filling 2 the project is not located in the SFHA. No comment |
10/12/2022 12:43:55 PM |