Project Review Comments
- Project Name
- 9440 Bur Oak Ln 20% Setback Reduction
- Description
- accessory structure located in drainage /utility easements needing admin relief.
- Location
- Parcels
- 5515403027 5515403027
- Applicant
-
Ronnie Huffman
Ronnie Huffman ( ronnie.huffman@ttp-llc.com )
(719) 391-7737 Ronnie Huffman ( ronnie.huffman@ttp-llc.com )
(719) 391-7737 - File Number
- ADR226
- Project Manager
- Justin Kilgore
- Status
- Closed
- Created
- 4/6/2022 9:54:05 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
8/22/2022 4:43:08 PM |
Planning will be able to approve this application once the utilities approve the encroachment into the easement. | 8/22/2022 4:43:08 PM | |
PCD Engineering Division
8/18/2022 5:17:12 PM |
Comments provided by E. Nijkamp, PE; Engineering Review Manager. 1. The design shall be engineered to mitigate for the swale located within the easement. A condition will be added to the site plan at the time of approval. 2. The design and construction must accommodate the drainage from the north until such time as the area to the north is developed and flow is significantly reduced from upstream. Positive flow to the west must be maintained at all times. |
8/18/2022 5:17:12 PM | |
Mountain View Electric Association, Inc.
8/16/2022 12:20:07 PM |
Mountain View Electric Association has no objection to the current plan | 8/16/2022 12:20:07 PM | |
View |
PCD Project Manager
5/25/2022 10:57:13 AM |
The letter of the intent checklist. Please make sure all items are addressed for your next submittal. | 5/25/2022 10:57:13 AM |
View |
PCD Project Manager
5/25/2022 10:55:52 AM |
Administrative relief site plan checklist - make sure all items are addressed. | 5/25/2022 10:55:52 AM |
View |
PCD Project Manager
5/25/2022 10:54:53 AM |
The letter of intent needs more detail about the request and justification. see attached. | 5/25/2022 10:54:53 AM |
View |
PCD Project Manager
5/25/2022 10:53:59 AM |
Site plan comments are attached. Please review the comments and include the data on the new drawings. The drainage area will be looked at closely. | 5/25/2022 10:53:59 AM |
Colorado Springs Public Works
5/20/2022 6:35:57 AM |
Engineering Development Review Division has no comments on this item. Patrick V. Morris Civil Engineer II Public Works/Engineering Development Review City of Colorado Springs Phone: 719-385-5075 Patrick.morris@coloradosprings.gov |
5/20/2022 6:35:57 AM | |
PCD Engineering Division
5/16/2022 1:50:19 PM |
Review 1 comments will be uploaded by the project manager. Review comments on the following documents: - Site Plan Note: There is no Driveway Access Permit on file for existing driveway. A Driveway Access Permit is required for all access points onto a county or private road. Please apply for a driveway access permit through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
5/16/2022 1:50:19 PM | |
Mountain View Electric Association, Inc.
5/12/2022 8:05:09 AM |
See note #9 on the plat - easements are 10 feet, front, side and rear. The structure needs to avoid the easement areas. | 5/12/2022 8:05:09 AM | |
Fountain
5/11/2022 1:51:31 PM |
No comments. | 5/11/2022 1:51:31 PM | |
Colorado Springs Public Works
5/10/2022 8:42:29 AM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
5/10/2022 8:42:29 AM |