Project Review Comments
- Project Name
- 6275 Lake Shore Ct RV Storage
- Description
- Location
- Parcels
- 5406204034 5406204034
- Applicant
-
Milosh LLC
Milan Jankovic ( mj@milosheng.com )
(720) 210-4213 Milan Jankovic ( mj@milosheng.com )
(720) 210-4213 - File Number
- PPR2216
- Project Manager
- Kylie Bagley
- Status
- Active
- Created
- 3/7/2022 3:33:39 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
Cimarron Hills Fire
5/25/2022 1:04:22 PM |
CHFD has reviewed this plot plan and they are approved. JT McLeod, Division Chief/Fire Inspector III. | 5/25/2022 1:04:22 PM | |
View |
PCD Project Manager
5/6/2022 1:31:12 PM |
Site Development Plan Redlines | 5/6/2022 1:31:12 PM |
View |
PCD Project Manager
5/6/2022 1:30:39 PM |
Letter of Intent Redlines | 5/6/2022 1:30:39 PM |
View |
PCD Project Manager
5/6/2022 1:29:57 PM |
Drainage Report Redlines | 5/6/2022 1:29:57 PM |
View |
PCD Project Manager
5/6/2022 1:29:25 PM |
Financial Assurance Forms Redlines | 5/6/2022 1:29:25 PM |
View |
PCD Project Manager
5/6/2022 1:28:58 PM |
Grading and Erosion Control Plan Redlines | 5/6/2022 1:28:58 PM |
View |
PCD Project Manager
5/6/2022 1:28:26 PM |
Detention Maintenance Agreement Redlines | 5/6/2022 1:28:26 PM |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/5/2022 3:39:16 PM |
Contact CSU field engineering regarding gas and electric requirements if needed. 719-668-4985. Approval can be recommended. |
5/5/2022 3:39:16 PM | |
View |
Colorado Springs Airport Advisory Commission
5/4/2022 4:59:19 PM |
The attached summary with comments will be presented at the May 25th, 2022 Airport Advisory Commission meeting. | 5/4/2022 4:59:19 PM |
View |
EPC Stormwater Review
5/3/2022 11:31:26 AM |
SWMP Checklist | 5/3/2022 11:31:26 AM |
View |
EPC Stormwater Review
5/3/2022 11:30:06 AM |
PBMP Applicability Form | 5/3/2022 11:30:06 AM |
View |
EPC Stormwater Review
5/3/2022 11:29:47 AM |
GEC Checklist | 5/3/2022 11:29:47 AM |
EPC Stormwater Review
5/3/2022 11:28:54 AM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report...(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - PBMP Applicability Form - SWMP Checklist Please provide the following documents on resubmittal (all of which are downloadable from our website linked below, besides the SWMP): - SWMP - O&M Manual - MS4 Post Construction Form - SDI Form https://publicworks.elpasoco.com/stormwater/ Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
5/3/2022 11:28:54 AM | |
Pikes Peak Regional Building Department
5/2/2022 12:58:55 PM |
1. The proposed address will be 6245 Lake Shore Court for the new commercial building. No further comments. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org W: 719-327-2953 |
5/2/2022 12:58:55 PM | |
PCD Engineering Division
5/2/2022 9:44:27 AM |
Engineer Review Ver.1 Please see comments on the following documents for correction or submission. Project Manager/Planner will upload review documents. -Letter of Intent -Detention Maintenance Agreement (needs to be completed) -Drainage Report -Grading & Erosion Control Plan -Site Development Plan -FAE (must use 2022 form) Missing Documents: -Stormwater Detention and Infiltration Design Data Sheet (SDI Worksheet) -O & M Plan -El Paso County MS4 Post Construction Detention / Water Quality Facility Documentation Form Thank you Edward B. Schoenheit Engineer I Reviewer El Paso County Planning & Community Development EdwardSchoenheit@elpasoco.com 719-520-6813 (O) |
5/2/2022 9:44:27 AM | |
Cherokee Metro Dist
4/18/2022 9:15:41 AM |
No comment | 4/18/2022 9:15:41 AM |