Project Review Comments
- Project Name
- 19955 Wigwam Road
- Description
- Remodel existing service garage building on the site and add a new 50'x60 dry storage building. Add outdoor RV storage and outdoor U Haul rental area to the site
- Location
- Parcels
- 5726000004 5726000004
- Applicant
-
M.V.E., Inc.
David Gorman ( daveg@mvecivil.com )
(719) 635-5736 David Gorman ( daveg@mvecivil.com )
(719) 635-5736 - File Number
- PPR247
- Project Manager
- Lacey Dean
- Status
- Active
- Created
- 3/7/2022 3:12:19 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
EPC Health Department
5/10/2024 11:10:03 AM |
5/10/2024 11:10:03 AM | |
View |
County Attorney - Development Review
4/24/2024 1:31:21 PM |
Requested edits to detention maintenance agreement attached. | 4/24/2024 1:31:21 PM |
View |
PCD Project Manager
4/9/2024 4:07:40 PM |
V1_Sign Plan | 4/9/2024 4:07:40 PM |
View |
PCD Project Manager
4/9/2024 4:07:23 PM |
V1_Lighting Plan | 4/9/2024 4:07:23 PM |
View |
PCD Project Manager
4/9/2024 4:07:12 PM |
V1_Letter of Intent | 4/9/2024 4:07:12 PM |
View |
PCD Project Manager
4/9/2024 4:06:59 PM |
V1_Landscape Plan Drawings | 4/9/2024 4:06:59 PM |
View |
EPC Stormwater Review
4/9/2024 4:04:20 PM |
SWMP Checklist | 4/9/2024 4:04:20 PM |
View |
PCD Project Manager
4/9/2024 4:06:41 PM |
V1_Elevation Plans | 4/9/2024 4:06:41 PM |
View |
EPC Stormwater Review
4/9/2024 4:04:01 PM |
SDP | 4/9/2024 4:04:01 PM |
View |
PCD Project Manager
4/9/2024 4:06:30 PM |
V1_Application-Petition Form | 4/9/2024 4:06:30 PM |
PCD Project Manager
4/9/2024 4:06:18 PM |
Review 1 - EPC Planning Comments have been provided on the following documents: - Application-Petition Form - Elevation Plans - Landscape Plan Drawings - Letter of Intent - Lighting Plan - Sign Plan - Site Development Plan (to be uploaded by Stormwater Engineer) Reviewed by: Lacey Dean laceydean2@elpasoco.com |
4/9/2024 4:06:18 PM | |
View |
EPC Stormwater Review
4/9/2024 4:02:37 PM |
PBMP | 4/9/2024 4:02:37 PM |
View |
EPC Stormwater Review
4/9/2024 4:02:12 PM |
GEC Checklist | 4/9/2024 4:02:12 PM |
View |
EPC Stormwater Review
4/9/2024 4:01:51 PM |
GEC Plan | 4/9/2024 4:01:51 PM |
View |
EPC Stormwater Review
4/9/2024 4:01:18 PM |
FAE | 4/9/2024 4:01:18 PM |
View |
EPC Stormwater Review
4/9/2024 3:57:43 PM |
Detention Maintenance Agreement | 4/9/2024 3:57:43 PM |
View |
EPC Stormwater Review
4/9/2024 3:57:13 PM |
Drainage Report | 4/9/2024 3:57:13 PM |
Hanover Fire Protection District
4/8/2024 11:09:30 AM |
1. Knox box attached to the Pole barn and office. 2. Propane fill station No Smoking signs within 50ft and fire extinguishers. 3. Fire mitigation plan for interior and exterior of the lot needs to be addressed. 4. Water cistern minimal requirements and locations will need to be calculated based on number of UHaul rental, RV storage spaces, buildings, size of Propane tanks and semi-truck parking. |
4/8/2024 11:09:30 AM | |
Mountain View Electric Association, Inc.
4/8/2024 9:52:08 AM |
MVEA has existing facilities near and within this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. MVEA will work with the developer on the design of the electric service and to acquire any needed utility easements. MVEA also requests the platting of MVEA’s existing facilities with easements on the plat. | 4/8/2024 9:52:08 AM | |
PCD Engineering Division
4/5/2024 9:07:43 AM |
Review 1 - EPC Engineering Comments have been provided on the following documents (to be uploaded by project manager): - Drainage Report - GEC Plans - LOI - Site Development Plan. Due to the nature and volume of comments provided, additional comments may be generated with the second review. Note that ESQCP is required for this project. Reviewed by: Hao Vo, PE haovo@elpasoco.com |
4/5/2024 9:07:43 AM | |
Pikes Peak Regional Building Department
4/4/2024 9:50:44 AM |
Enumerations has the following comments: 1. We have no permit history for the existing building on this parcel. The Assessor page shows that this structure was built in 1982. Verify if that is correct. If so, then that building will use the parcel address of 19955 Wigwam Rd. The proposed storage building will require a separate address. Enumerations has assigned the address of 19965 Wigwam Rd. for this new building. This address should be used when submitting building plans for review/permit. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
4/4/2024 9:50:44 AM | |
EPC Stormwater Review
4/9/2024 3:53:06 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report.............(uploaded with Development Services comments) - FAE.................................(uploaded with Development Services comments) - GEC Plan........................(uploaded with Development Services comments) - GEC Checklist - PBMP Applicability Form - Private Detention Basin / Stormwater Quality BMP Maintenance Agreement - Site Development Plan....(uploaded with Development Services comments) - SWMP Checklist Please provide the following documents upon resubmittal (the planner will send an upload request): - ESQCP - O&M Manual - SDI Form or MHFD Detention Calcs - SWMP Due to the volume or complexity of the comments provided, these comments are preliminary in nature and EPC DPW Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
4/9/2024 3:53:06 PM |