View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
7/27/2022 9:16:41 AM |
Review #3: Engineering documents have been forwarded to the Engineering Manager for final approval. - Submit a signed "Pre-Development Site Grading Acknowledgement and Right of Access Form" Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
7/27/2022 9:16:41 AM | |
PCD Project Manager
6/29/2022 9:17:32 AM |
No comments from Planning Division. | 6/29/2022 9:17:32 AM | |
View |
PCD Engineering Division
6/28/2022 8:24:45 AM |
Review #2: Grading and Erosion Control Plan | 6/28/2022 8:24:45 AM |
View |
PCD Engineering Division
6/28/2022 8:23:09 AM |
Review #2: Financial Assurance Estimate | 6/28/2022 8:23:09 AM |
View |
PCD Engineering Division
6/28/2022 8:23:26 AM |
Review #2: Drainage Report | 6/28/2022 8:23:26 AM |
PCD Engineering Division
6/27/2022 11:04:05 AM |
Review #2: Redline comments on the following documents will be uploaded by the project manager: - Grading and Erosion Control Plans - Final Drainage Report - Financial Assurance Estimate Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
6/27/2022 11:04:05 AM | |
EPC Stormwater Review
6/28/2022 7:44:49 AM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - FAE.......................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
6/28/2022 7:44:49 AM | |
View |
PCD Engineering Division
5/11/2022 8:23:44 AM |
See the attached document. | 5/11/2022 8:23:44 AM |
View |
PCD Project Manager
4/21/2022 10:04:46 AM |
PCD Engineering and EPC Stormwater comments - GEC plan | 4/21/2022 10:04:46 AM |
View |
PCD Project Manager
4/21/2022 10:05:02 AM |
EPC Stormwater comments - GEC checklist | 4/21/2022 10:05:02 AM |
View |
PCD Project Manager
4/21/2022 10:03:55 AM |
PCD Engineering and EPC Stormwater comments - FAE | 4/21/2022 10:03:55 AM |
View |
PCD Project Manager
4/21/2022 9:51:10 AM |
EPC Stormwater comments - ESQCP | 4/21/2022 9:51:10 AM |
View |
PCD Project Manager
4/21/2022 9:50:46 AM |
PCD Engineering comments - drainage report | 4/21/2022 9:50:46 AM |
View |
EPC Stormwater Review
4/18/2022 4:25:41 PM |
ESQCP_v1 | 4/18/2022 4:25:41 PM |
View |
EPC Stormwater Review
4/18/2022 4:25:14 PM |
GEC Checklist_v1 | 4/18/2022 4:25:14 PM |
EPC Stormwater Review
4/18/2022 4:24:27 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - FAE.......................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - ESQCP Please provide the following documents on resubmittal: - SWMP Please sign and resubmit the following documents: - PBMP Applicability Form - SWMP Checklist Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
4/18/2022 4:24:27 PM | |
PCD Engineering Division
4/20/2022 2:56:09 PM |
Review #1: Based on the nature of the comments to the Final Drainage expect additional comments on the resubmittal. Staff recommends the design engineer contact the review engineer to discuss what needs to be presented within the drainage report associated with the early grading application. Redline comments on the following documents will be uploaded by the project manager: - Grading and Erosion Control Plans - Final Drainage Report - Financial Assurance Estimate Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
4/20/2022 2:56:09 PM |