Project Review Comments
- Project Name
- Mayberry Filing No. 3 (Major)
- Description
- Final plat for Mayberry Filing No. 3. Subject to PUDSP219
- Location
- Parcels
- 3414102002 3414102002 3414102005 3414102005 3414102016 3414102016 3414201030 3414201030 3414201031 3414201031 3414208026 3414208026
- Applicant
-
N.E.S.
Cody Burghardt ( codyburghardt@mayberrycoloradosprings.com ) Cody Burghardt ( codyburghardt@mayberrycoloradosprings.com ) - EA Number
- EA2216
- File Number
- SF2219
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 2/15/2022 10:23:03 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
County Attorney - Development Review
8/3/2023 12:58:07 PM |
Signature to SIA attached. | 8/3/2023 12:58:07 PM |
View |
County Attorney - Development Review
8/3/2023 12:57:27 PM |
Signature to Detention Maintenance Agreement attached. | 8/3/2023 12:57:27 PM |
View |
County Attorney - Development Review
6/22/2023 2:10:15 PM |
Proposed edits to detention agreement attached, related to exhibit references. | 6/22/2023 2:10:15 PM |
View |
County Attorney - Development Review
6/22/2023 2:09:36 PM |
Signature to ROW license agreement attached. | 6/22/2023 2:09:36 PM |
PCD Engineering Division
6/20/2023 10:24:31 AM |
Engineering documents have been approved by the ECM Administrator. Approved documents will be uploaded onto EDARP by the project manager. reviewed by: daniel torres danieltorres@elpasoco.com |
6/20/2023 10:24:31 AM | |
PCD Project Manager
4/26/2023 4:41:04 PM |
Planning Division has no further comments at this time. | 4/26/2023 4:41:04 PM | |
EPC Stormwater Review
4/26/2023 11:19:32 AM |
All Stormwater comments have been addressed. | 4/26/2023 11:19:32 AM | |
View |
County Attorney - Development Review
4/25/2023 7:53:49 PM |
Comments to ROW license agreement attached. | 4/25/2023 7:53:49 PM |
View |
County Attorney - Development Review
4/25/2023 7:53:16 PM |
Comments to Detention Maintenance Agreement attached. | 4/25/2023 7:53:16 PM |
PCD Engineering Division
4/26/2023 4:44:45 PM |
Review 4: No additional comments. Please submit the following signed (by owner & engineer) engineering documents for approval by the ECM administrator. -CD -FAE -Final Drainage Report -GEC Plan -GEC Checklist -ESQCP -TIS -SWMP -SWMP Checklist Ryan a 3-day turnaround is sufficient for the approval. reviewed by: Daniel Torres danieltorres@elpasoco.com |
4/26/2023 4:44:45 PM | |
View |
EPC Stormwater Review
3/7/2023 3:48:39 PM |
GEC_v3 | 3/7/2023 3:48:39 PM |
View |
EPC Stormwater Review
3/7/2023 3:47:22 PM |
Drainage Report_v3 | 3/7/2023 3:47:22 PM |
View |
PCD Engineering Division
3/7/2023 4:01:54 PM |
Construction Drawing redlines | 3/7/2023 4:01:54 PM |
EPC Stormwater Review
3/7/2023 3:33:54 PM |
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(uploaded with PCD comments) - GEC Plan...............(uploaded with PCD comments) Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
3/7/2023 3:33:54 PM | |
PCD Engineering Division
3/7/2023 3:39:23 PM |
Review 3 comments on the following documents will be uploaded: -Construction Drawings -Final Drainage Report (to be uploaded by stormwater engineer) -GEC (to be uploaded by stormwater engineer) No additional PCD engineering comments on the following documents: TIS FAE Provided the comments are addressed, signed (by owner & engineer) engineering documents may be submitted for approval. Ryan a 7-day turnaround is sufficient for the resubmittal. reviewed by: Daniel Torres danieltorres@elpasoco.com |
3/7/2023 3:39:23 PM | |
View |
County Attorney - Development Review
3/3/2023 12:53:12 PM |
Edits to and comments on ROW License Agreement attached. | 3/3/2023 12:53:12 PM |
View |
County Attorney - Development Review
3/3/2023 12:52:38 PM |
1. No further proposed edits to SIA. 2. Edits to and comments on Detention Maintenance Agreement attached. |
3/3/2023 12:52:38 PM |
PCD Project Manager
2/24/2023 4:05:19 PM |
Planning Division has no further comments at this time. | 2/24/2023 4:05:19 PM | |
View |
Colorado Department of Transportation - Pueblo Office
12/7/2022 9:44:35 AM |
12/7/2022 9:44:35 AM | |
View |
County Attorney - Development Review
10/20/2022 2:23:02 PM |
I accepted most of applicant's proposed edits. Please see attached. | 10/20/2022 2:23:02 PM |
View |
PCD Project Manager
10/18/2022 10:01:08 AM |
PCD Engineering comments - TIS | 10/18/2022 10:01:08 AM |
View |
PCD Project Manager
10/18/2022 10:00:50 AM |
PCD Engineering comments - GEC | 10/18/2022 10:00:50 AM |
View |
PCD Project Manager
10/18/2022 10:00:16 AM |
PCD Engineering comments - FAE | 10/18/2022 10:00:16 AM |
View |
PCD Project Manager
10/18/2022 9:59:57 AM |
PCD Planning comments - final plat | 10/18/2022 9:59:57 AM |
View |
PCD Project Manager
10/18/2022 9:59:25 AM |
PCD Engineering comments - Drainage report | 10/18/2022 9:59:25 AM |
View |
PCD Project Manager
10/18/2022 9:58:54 AM |
PCD Engineering comments - CDs | 10/18/2022 9:58:54 AM |
PCD Engineering Division
10/18/2022 10:15:35 AM |
Review 2 comments on the following documents will be uploaded by the project manager: -Construction Drawings -Final Drainage Report -TIS -GEC -FAE No additional PCD engineering comments on the following documents: -Final Plat -Soils & Geology reviewed by: Daniel Torres danieltorres@elpasoco.com |
10/18/2022 10:15:35 AM | |
View |
EPC Stormwater Review
10/17/2022 8:41:23 AM |
GEC Checklist_v2 | 10/17/2022 8:41:23 AM |
View |
EPC Stormwater Review
10/17/2022 8:40:55 AM |
ESQCP_v2 | 10/17/2022 8:40:55 AM |
EPC Stormwater Review
10/16/2022 9:25:57 PM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments) - FAE........................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - ESQCP Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
10/16/2022 9:25:57 PM | |
View |
County Attorney - Water
9/26/2022 2:20:49 PM |
The County Attorney's Office provided its water review at the PUD Preliminary Plan stage (PUDSP-21-9). There do not appear to be any changes to the water supply; therefore, please refer to our letter dated February 28, 2022 as attached. Thank you. | 9/26/2022 2:20:49 PM |
Colorado Department of Transportation - Pueblo Office
9/19/2022 2:42:46 PM |
As part of CDOT Access Permits AP#218053 and AP#218054, updated access permits are required for each filing as this development grows. The Developer is required to make application to CDOT to update or renew existing permits for Filing No. 3 and install the additional improvements required of the permits. - Arthur Gonzales, CDOT Access Manager | 9/19/2022 2:42:46 PM | |
View |
EPC Health Department
7/8/2022 9:26:20 PM |
7/8/2022 9:26:20 PM | |
View |
PCD Project Manager
7/8/2022 4:45:29 PM |
PCD Engineering comments - TIS | 7/8/2022 4:45:29 PM |
View |
PCD Project Manager
7/8/2022 4:45:09 PM |
PCD Planning & PCD Engineering comments - soils & geology report | 7/8/2022 4:45:09 PM |
View |
PCD Project Manager
7/8/2022 4:44:42 PM |
PCD Planning comments - natural features report | 7/8/2022 4:44:42 PM |
View |
PCD Project Manager
7/8/2022 4:44:04 PM |
PCD Planning comments - LOI | 7/8/2022 4:44:04 PM |
View |
PCD Project Manager
7/8/2022 4:43:47 PM |
PCD Engineering & EPC Stormwater comments - GEC | 7/8/2022 4:43:47 PM |
View |
PCD Project Manager
7/8/2022 4:43:24 PM |
PCD Engineering comments - FAE | 7/8/2022 4:43:24 PM |
View |
PCD Project Manager
7/8/2022 4:42:50 PM |
PCD Planning & PCD Engineering comments - final plat | 7/8/2022 4:42:50 PM |
View |
PCD Project Manager
7/8/2022 4:42:30 PM |
Drainage report markup summary attached | 7/8/2022 4:42:30 PM |
View |
PCD Project Manager
7/8/2022 4:40:47 PM |
PCD Engineering & EPC Stormwater comments - Drainage report | 7/8/2022 4:40:47 PM |
View |
PCD Project Manager
7/8/2022 4:40:25 PM |
PCD Engineering comments - CDs | 7/8/2022 4:40:25 PM |
View |
EPC Stormwater Review
7/8/2022 4:33:33 PM |
MS4_v1 | 7/8/2022 4:33:33 PM |
View |
EPC Stormwater Review
7/8/2022 4:33:03 PM |
SWMP_v1 | 7/8/2022 4:33:03 PM |
EPC Stormwater Review
7/8/2022 4:34:03 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report...(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - SWMP - MS4 Post Construction Form Please provide the following documents upon resubmittal: - ESQCP - GEC Checklist -- The checklist submitted is for the Early Grading GEC Reviewed by: Christina Prete, P.E. Stormwater Engineer III christinaprete@elpasoco.com |
7/8/2022 4:34:03 PM | |
View |
Parks Advisory Board
7/7/2022 11:08:29 AM |
Parks Advisory Board endorsement not available due to lack of July quorum. See final Parks comments attached. | 7/7/2022 11:08:29 AM |
PCD Engineering Division
7/6/2022 5:51:32 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Final Plat -Construction Drawings -Final Drainage Report -TIS -GEC -FAE -Soils & geology report reviewed by: Daniel Torres danieltorres@elpasoco.com |
7/6/2022 5:51:32 PM | |
View |
Colorado Division of Water Resources
6/15/2022 12:47:17 PM |
6/15/2022 12:47:17 PM | |
View |
County Attorney - Development Review
6/14/2022 1:49:38 PM |
Proposed edits to Detention Maintenance Agreement attached. | 6/14/2022 1:49:38 PM |
View |
County Attorney - Development Review
6/14/2022 1:49:13 PM |
Proposed edits to SIA attached. | 6/14/2022 1:49:13 PM |
View |
Colorado Parks and Wildlife
6/14/2022 7:43:05 AM |
6/14/2022 7:43:05 AM | |
Pikes Peak Regional Building Department
6/9/2022 9:39:36 AM |
Regarding a request for approval of a final plat for Mayberry Fil. No. 3, Enumerations has the following comments: 1. Submit a copy of this plat to Enumerations for address assignment. Mark all locations requiring an address with (XXXX). 2. When submitting a copy for addressing, please include any plans for development that continues to the east along Union Pacific Way and El Reno Lane so that addressing can be assigned consistently along both streets. 3. Prior to recording, Enumerations will review the mylar per usual procedure. The Enumerations fee due at the time of review will be $10 per lot/tract to which an address is assigned. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
6/9/2022 9:39:36 AM | |
Colorado Geological Survey
6/8/2022 10:09:38 AM |
The site is not exposed to any geologic hazards or geotechnical constraints that would preclude the proposed final plat. CGS agrees with CTL|Thompson’s report (Geologic Hazard Evaluation, Mayberry Development aka Ellicott Town Center, Filings 1 through 4, Highway 94 and Log Road, Ellicott, Colorado, CTL|T Project No. CS18969-105, June 18, 2021) that the conditions that may pose hazards or constraints to development include expansive soil lenses, potentially collapse prone soils, and existing undocumented fill. As noted on page 6 of the Letter of Intent (N.E.S. Inc., May 2022), the following should be performed: • Site-specific, design level Soils and Foundation Investigation to provide design criteria for foundations and floor systems for proposed residential buildings. • Subgrade investigation and design after grading. • Construction testing and observation during site development and residential building construction. • Foundation drains should be anticipated for all basement areas. Provided the above development recommendations and CTL|Thompson’s recommendations are adhered to, CGS has no objection to the approval of the Filing No. 3 final plat as proposed. Note 28 on Sheet C1.3 of the Grading Plans (JPS Engineering, March 15, 2022) should be updated to CTL’s latest report. Submitted 6/8/2022 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu) |
6/8/2022 10:09:38 AM | |
View |
Mountain View Electric Association, Inc.
6/7/2022 8:05:29 AM |
See attached comments | 6/7/2022 8:05:29 AM |
View |
EPC Parks Department
6/2/2022 7:53:23 AM |
See preliminary Parks comments attached. Greg |
6/2/2022 7:53:23 AM |
911 Authority - El Paso/Teller County
5/26/2022 8:10:25 AM |
Streetnames previously approved. No action for E911 on this submittal. Thank you. Justin. |
5/26/2022 8:10:25 AM | |
Ellicott Fire Protection District
5/24/2022 3:23:19 PM |
There are no objections to the final plat as described. Question where the utility plans part of the previous filing? There is a review fee of $388.00 payable to the Ellicott Fire Department at 75 N Ellicott Highway, Calahan, CO 80808. | 5/24/2022 3:23:19 PM | |
View |
EPC Environmental Services
5/24/2022 10:13:14 AM |
5/24/2022 10:13:14 AM | |
County Attorney - Water
5/23/2022 1:02:31 PM |
County Attorney's Office will begin review once the Colorado Division of Water Resources provides findings. | 5/23/2022 1:02:31 PM |