Project Name
Monument Glamping Site Development Plan
Description
Location
Parcels
7127001011 7127001011
Applicant
Monument Ridge Ltd.
Chris Jeub ( chrisjeub@gmail.com )
(719) 660-5781
Chris Jeub ( chrisjeub@gmail.com )
(719) 660-5781
EA Number
EA21240
File Number
PPR2253
Project Manager
Ashlyn Mathy
Status
Closed
Created
1/19/2022 2:54:57 PM

View: Project Documents



Review Comments (21)

Link Agency Comment
PCD Project Manager
7/28/2023 10:15:33 AM
comments have been addressed, moving to next steps in the process. 7/28/2023 10:15:33 AM
View EPC Code Enforcement
7/13/2023 4:57:51 PM
See attached PDF 7/13/2023 4:57:51 PM
View PCD Project Manager
6/29/2023 10:53:11 AM
landscape plans. unresolved comments from version 2&3 carrying into version 4.

Please resolve minor comments.
6/29/2023 10:53:11 AM
View PCD Project Manager
6/19/2023 8:50:04 AM
landscape plans unresolved comments from v2 6/19/2023 8:50:04 AM
View PCD Project Manager
6/19/2023 8:49:34 AM
SDP comments, unresolved from v2 6/19/2023 8:49:34 AM
View PCD Project Manager
6/19/2023 8:44:50 AM
LOI, minor comments
-please take landscaping graph and move to landscape plan.

thank you.
6/19/2023 8:44:50 AM
View EPC Health Department
1/6/2023 12:21:05 PM
1/6/2023 12:21:05 PM
View PCD Project Manager
12/27/2022 3:06:31 PM
landscape plans, planning comments 12/27/2022 3:06:31 PM
View PCD Project Manager
12/27/2022 3:06:09 PM
SDP planning comments 12/27/2022 3:06:09 PM
PCD Engineering Division
12/27/2022 1:38:28 PM
Comments have been resolved. There are no additional comments. The project manager will upload any approved documents.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
12/27/2022 1:38:28 PM
EPC Stormwater Review
12/13/2022 12:27:57 PM
Review 2: Still no comments. Planner: no re-review necessary.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
12/13/2022 12:27:57 PM
Tri-Lakes-Monument Fire Protection District
11/17/2022 8:00:59 AM
No concerns with the project as submitted. JCB 11/17/2022 8:00:59 AM
Mountain View Electric Association, Inc.
11/7/2022 2:14:04 PM
Mountain View Electric Association has no objection to the current plan. 11/7/2022 2:14:04 PM
View PCD Project Manager
11/7/2022 11:04:58 AM
Site Development Plan Redlines 11/7/2022 11:04:58 AM
View PCD Project Manager
11/7/2022 11:02:51 AM
Letter of Intent Redlines 11/7/2022 11:02:51 AM
View PCD Project Manager
11/7/2022 11:02:31 AM
Elevation Plans Redlines 11/7/2022 11:02:31 AM
Pikes Peak Regional Building Department
11/7/2022 7:25:17 AM
It appears all comments have been addressed, no further comments.

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
11/7/2022 7:25:17 AM
EPC Stormwater Review
11/2/2022 2:19:24 PM
Review 1: EPC Stormwater does not have any comments on any of the uploaded documents. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
GlennReese@elpasoco.com
11/2/2022 2:19:24 PM
PCD Engineering Division
11/2/2022 9:48:07 AM
Review 1 comments will be uploaded by the project manager for the following documents:

-Letter of intent
-Site plan

Reviewed By:
Lupe Packman
lupepackman@elpasoco.com
11/2/2022 9:48:07 AM
View Colorado Parks and Wildlife
10/22/2022 2:06:50 PM
10/22/2022 2:06:50 PM
View RBD Floodplain
10/17/2022 2:10:20 PM
please move off grid tent site 2 out of the floodway , or provide no-rise certification for floodway encroachment. 10/17/2022 2:10:20 PM