Project Review Comments
- Project Name
- Solberg Pit Special Use Amendment - Minor
- Description
- Expansion of existing non-conforming mineral extraction use; existing gravel pit is to be reclaimed excluding access. Application of special use to being pit into compliance with the LDC. If opposition arises, this request may be elevated to requiring hearings before the Planning Commission and Board of County Commissioners.
- Location
- Parcels
- 4321000009 4321000009 4321000010 4321000010 4321000011 4321000011 4321000012 4321000012
- Applicant
-
Pioneer Landscaping Materials inc.
Kurt Thurmann ( kurt.thurmann@holcim.com )
(720) 329-8851 Kurt Thurmann ( kurt.thurmann@holcim.com )
(720) 329-8851 - EA Number
- EA21232
- File Number
- AL2218
- Project Manager
- Ryan Howser
- Status
- Closed
- Created
- 12/30/2021 10:11:20 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Administrative Notice
11/29/2023 10:34:51 AM |
PCD mailed 8 notices of potential Administrative Decision to surrounding properties within a 500-foot range on 11/29/2023. The cost to the applicant will be $5.04. MB | 11/29/2023 10:34:51 AM | |
PCD Project Manager
11/21/2023 1:00:03 PM |
Planning Division has no further comments at this time. Please note that administrative special use approval may take up to two weeks to complete. | 11/21/2023 1:00:03 PM | |
View |
Colorado Department of Public Health and Environment
11/21/2023 10:14:00 AM |
Please see auto responder from CDPHE. Please let us know if you have additional question. | 11/21/2023 10:14:00 AM |
PCD Engineering Division
11/21/2023 9:33:47 AM |
Comments have been resolved. No additional comments. reviewed by: Daniel Torres danieltorres@elpasoco.com |
11/21/2023 9:33:47 AM | |
PCD Engineering Division
11/1/2023 12:00:55 PM |
We have been informed that there are no additional comments from DPW Construction Services. | 11/1/2023 12:00:55 PM | |
View |
PCD Engineering Division
10/25/2023 5:01:23 PM |
Traffic Study comments | 10/25/2023 5:01:23 PM |
View |
PCD Engineering Division
10/25/2023 5:00:52 PM |
Letter of intent comment | 10/25/2023 5:00:52 PM |
View |
PCD Project Manager
10/24/2023 10:48:40 AM |
Review 2: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - Site Plan Drawing |
10/24/2023 10:48:40 AM |
PCD Engineering Division
10/25/2023 5:00:03 PM |
Review 2 comments on the following documents will be uploaded by the project manager: -Letter of intent -Traffic Study This project has been referred to the Department of Public Works Construction Services to provide any additional comments on the project and/or regarding a possible Haul Route Agreement/Haul Route Fee. Once we are in receipt of comments they will be provided via email and/or EDARP. reviewed by: Daniel Torres danieltorres@elpasoco.com |
10/25/2023 5:00:03 PM | |
View |
EPC Health Department
1/10/2023 8:00:28 PM |
1/10/2023 8:00:28 PM | |
View |
Colorado Department of Transportation - Pueblo Office
1/10/2023 11:24:57 AM |
Please refer to attached letter. | 1/10/2023 11:24:57 AM |
Upper Black Squirrel Creek GWMD
1/5/2023 10:50:06 AM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time, but respectfully reserves the right to comment on future submittals. | 1/5/2023 10:50:06 AM | |
Colorado Department of Transportation - Pueblo Office
12/27/2022 11:59:01 AM |
Submittals have been sent for review. CDOT comments are forthcoming. - Michelle Regalado | 12/27/2022 11:59:01 AM | |
View |
EPC Stormwater Review
11/28/2022 7:44:05 AM |
SWMP Checklist_v1 | 11/28/2022 7:44:05 AM |
View |
EPC Stormwater Review
11/28/2022 7:43:33 AM |
SWMP_v1 | 11/28/2022 7:43:33 AM |
View |
PCD Project Manager
11/23/2022 2:03:49 PM |
PCD Engineering comments - TIS | 11/23/2022 2:03:49 PM |
View |
PCD Project Manager
11/23/2022 2:03:31 PM |
PCD Planning comments - site plan drawing | 11/23/2022 2:03:31 PM |
View |
PCD Project Manager
11/23/2022 2:03:12 PM |
PCD Engineering comments - LOI | 11/23/2022 2:03:12 PM |
View |
PCD Project Manager
11/23/2022 2:02:52 PM |
PCD Engineering comments - haul route survey | 11/23/2022 2:02:52 PM |
View |
PCD Project Manager
11/29/2022 9:58:39 AM |
PCD Engineering & EPC Stormwater comments - GEC plan | 11/29/2022 9:58:39 AM |
View |
PCD Project Manager
11/23/2022 2:02:09 PM |
Drainage report markup summary | 11/23/2022 2:02:09 PM |
View |
PCD Project Manager
11/29/2022 10:00:01 AM |
PCD Engineering & EPC Stormwater comments - drainage report | 11/29/2022 10:00:01 AM |
PCD Engineering Division
11/23/2022 10:33:09 AM |
Review 1 comments on the following documents will be uploaded by the project manager: -Letter of Intent -Traffic Study -Haul Route Survey -Drainage report -Grading and Erosion Control Plan Please also refer to initial comments on documents provided by the DPW stormwater engineer. The following documents are NOT required to be submitted with this special use application and should be submitted with the subsequent site development plan application to progress the special use application. Initial comments have been provided on these documents by PCD Engineering and DPW storm water engineer. These comments may be addressed/resolved by the applicant at the site development plan stage. -Drainage report -Grading and Erosion Control Plan -Grading and Erosion Control Plan Checklist -SWMP -SWMP checklist -ESQCP reviewed by: Daniel Torres danieltorres@elpasoco.com |
11/23/2022 10:33:09 AM | |
EPC Stormwater Review
11/28/2022 7:33:19 AM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report.....(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - SWMP - SWMP Checklist These documents are NOT required to be submitted with this special use application and should be submitted with the subsequent site development plan application to progress the special use application. Initial comments have been provided on these documents by DPW Stormwater and PCD Engineering. These comments may be addressed/resolved by the applicant at the site development plan stage. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
11/28/2022 7:33:19 AM | |
View |
Colorado Department of Public Health and Environment
11/18/2022 1:13:05 PM |
Standard comments attached | 11/18/2022 1:13:05 PM |
Colorado Department of Public Health and Environment
11/18/2022 1:11:31 PM |
Reclamation of the site must be in accordance with all site permits. If alternative fills are proposed for the site, these uses must be approved by the Hazardous Materials and Waste Management Division's Permitting Unit. If necessary, a beneficial use determination must be made on any alternative fills for reclamation of the site prior to their use. The site should not be used for the disposal of regulated wastes. | 11/18/2022 1:11:31 PM | |
View |
PCD Project Manager
11/18/2022 9:29:52 AM |
Letter of Intent comments - Please provide an analysis of the criteria in Section 5.3.2.C of the Code (special use criteria). I have attached the special use criteria in this comment. I would recommend copying and pasting the bullet points into the letter and providing a response to each. You may be able to rearrange the information that has already been provided, as I believe some of the criteria points have already been addressed in the letter. | 11/18/2022 9:29:52 AM |
View |
PCD Project Manager
11/18/2022 9:26:52 AM |
Letter of Intent comments - please provide an analysis of compliance with Section 5.2.34.B of the Land Development Code. I have attached the section of the Code in this comment. I would recommend copying the criteria points into the letter and providing a response to each. | 11/18/2022 9:26:52 AM |
View |
Colorado Parks and Wildlife
11/15/2022 3:44:10 PM |
11/15/2022 3:44:10 PM | |
Falcon Fire Protection District
11/14/2022 9:28:02 AM |
Falcon Fire has no objections or concerns with this request. | 11/14/2022 9:28:02 AM | |
View |
El Paso County Conservation Dist
11/11/2022 11:33:32 AM |
EPCCD brief comments attached as a .pdf. | 11/11/2022 11:33:32 AM |
Mountain View Electric Association, Inc.
11/10/2022 9:40:19 AM |
Mountain View Electric Association has no objection to the current plan. | 11/10/2022 9:40:19 AM | |
Colorado Geological Survey
11/8/2022 1:36:16 PM |
Colorado Geological Survey understands Solberg Gravel LLC and the Solberg Gravel Pit operator, Pioneer Landscaping Materials Inc., propose a 79-acre expansion of the Solberg Gravel Pit located at 5445 Curtis Road, Peyton. The available referral documents include a Soils & Geology Report, Solberg Pit, Peyton, Colorado (Haley & Aldrich, Inc. File No. 0204990-001, July 28, 2022). The site is not undermined, and no geologic hazards are known or suspected to be present that would preclude approval of the expansion and special use amendment as proposed. The Colorado Division of Reclamation, Mining, and Safety (DRMS) approved Amendment No. 3 to mining permit M-1981-044 (Solberg Pit) on August 16, 2022. Provided the pit is operated and reclaimed in accordance with mining and reclamation plans approved by DRMS, CGS has no objection to approval of AL2218. Jill Carlson, engineering geologist (303) 384-2643 / carlson@mines.edu |
11/8/2022 1:36:16 PM | |
County Attorney - Development Review
11/4/2022 5:27:45 PM |
No comments from County Attorney - Development Review at this time. | 11/4/2022 5:27:45 PM | |
911 Authority - El Paso/Teller County
11/3/2022 1:15:18 PM |
No action for E911 on this submittal. Thank you. Justin |
11/3/2022 1:15:18 PM | |
View |
EPC Environmental Services
11/1/2022 11:29:52 AM |
11/1/2022 11:29:52 AM | |
View |
EPC Parks Department
10/31/2022 1:20:19 PM |
See administrative Parks comments attached. | 10/31/2022 1:20:19 PM |
RBD Floodplain
10/28/2022 6:35:27 AM |
parcel identified as the "expansion" (4321000010) is not within the SFHA, no comment | 10/28/2022 6:35:27 AM |