View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
7/7/2022 9:00:27 AM |
Planning Division has no further comments at this time. | 7/7/2022 9:00:27 AM | |
PCD Engineering Division
7/5/2022 10:14:33 AM |
Comments resolved. The approved TIS will be uploaded by the project manager. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
7/5/2022 10:14:33 AM | |
Colorado Springs Airport Advisory Commission
6/15/2022 9:21:25 AM |
Airport Staff has no additional comments to provide on this item. | 6/15/2022 9:21:25 AM | |
Colorado Springs Airport Advisory Commission
6/15/2022 9:20:50 AM |
Airport Staff has no additional comments to provide on this item. | 6/15/2022 9:20:50 AM | |
View |
PCD Project Manager
6/3/2022 12:22:37 PM |
SKP comments attached | 6/3/2022 12:22:37 PM |
View |
PCD Project Manager
6/3/2022 12:22:24 PM |
LOI comments attached | 6/3/2022 12:22:24 PM |
View |
PCD Engineering Division
5/16/2022 4:40:16 PM |
Review #2: Redline comments to the following documents is attached: - Traffic Impact Study NOTE: Remaining comment is minor. Make the necessary revision and upload with developer signature for final approval. Comments resolved on the following documents: - Sketch Plan Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
5/16/2022 4:40:16 PM |
View |
PCD Engineering Division
5/16/2022 4:38:21 PM |
Review #2: Redline comments to the following documents is attached: - Traffic Impact Study NOTE: Remaining comment is minor. Make the necessary revision and upload with developer signature for final approval. Comments resolved on the following documents: - Sketch Plan Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
5/16/2022 4:38:21 PM |
View |
EPC Health Department
4/2/2022 10:44:09 PM |
4/2/2022 10:44:09 PM | |
View |
PCD Project Manager
3/22/2022 8:12:32 AM |
PCD Engineering comments - traffic study | 3/22/2022 8:12:32 AM |
View |
PCD Project Manager
3/22/2022 8:12:00 AM |
PCD Planning and PCD Engineering comments - sketch plan | 3/22/2022 8:12:00 AM |
View |
PCD Project Manager
3/22/2022 8:07:59 AM |
PCD Planning comments - letter of intent | 3/22/2022 8:07:59 AM |
View |
PCD Project Manager
3/22/2022 8:07:39 AM |
PCD Planning comments - impact identification statement | 3/22/2022 8:07:39 AM |
PCD Engineering Division
3/21/2022 11:06:53 AM |
Review #1: Redline comments to the following documents will be uploaded by the project manager: - Sketch Plan - Traffic Impact Study Reviewed by: Gilbert LaForce gilbertlaforce@elpasoco.com |
3/21/2022 11:06:53 AM | |
View |
Colorado Division of Water Resources
3/17/2022 9:00:14 AM |
3/17/2022 9:00:14 AM | |
View |
Colorado Springs Airport Advisory Commission
3/16/2022 2:17:23 PM |
The attached land use review summary with comments will be presented at the March 23, 2022 Airport Advisory Commission meeting. | 3/16/2022 2:17:23 PM |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/16/2022 9:07:14 AM |
Ryan, I have no review comments for the above name project Al | 3/16/2022 9:07:14 AM | |
Mountain View Electric Association, Inc.
3/15/2022 1:01:07 PM |
Mountain View Electric Association has no objection to the sketch plan amendment | 3/15/2022 1:01:07 PM | |
Pikes Peak Regional Building Department
3/15/2022 12:30:06 PM |
1. Enumerations will provide a complete review of the project when the Preliminary Plan or Final Plat exhibit is submitted. 2. No further comments regarding the rezone or sketch plan amendment. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
3/15/2022 12:30:06 PM | |
Colorado Springs Public Works
3/15/2022 10:17:22 AM |
Engineering Development Review will require all public improvements to be built to full City Standards if this is chosen for pre-annexation per the IGA. In addition, since Marksheffel will be annexed into the City sometime in the future, the City will require a minimum 6' detached sidewalk to be installed adjacent to this development along Marksheffel. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
3/15/2022 10:17:22 AM | |
Falcon Fire Protection District
3/9/2022 2:06:49 PM |
Falcon Fire District has no objections to approving this request. | 3/9/2022 2:06:49 PM | |
View |
EPC Parks Department
3/7/2022 9:16:10 AM |
See final Parks comments attached. Thanks, Greg |
3/7/2022 9:16:10 AM |
Colorado Springs Public Works
3/3/2022 3:12:29 PM |
Traffic Engineering will require all public improvements to be built to full City Standards if this site is chosen for pre-annexation. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
3/3/2022 3:12:29 PM | |
Upper Black Squirrel Creek GWMD
3/1/2022 1:57:02 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. | 3/1/2022 1:57:02 PM | |
Woodmen Road Metro
2/28/2022 2:38:04 PM |
This proposed project does not impact the Woodmen Road Metropolitan District, nor is subject to the Woodmen Road fees. | 2/28/2022 2:38:04 PM | |
Central Marksheffel Metro
2/28/2022 2:36:59 PM |
This proposed project is located within the Central Marksheffel Metropolitan District boundaries. The District assess’ building permit fees for new development within the District Boundaries, the District also assess’ a mill levy on property within the District Boundaries. The fees for this year are as follows: Building Permit Fees: Commercial- Industrial/Agricultural- $1.50/SQUARE FOOT Lodging Land- $200/ROOM Recreational/Institutional/ Medical/Office/Retail - $2.00/sq Ft Residential- Single Family- $1,914/UNIT Multi Family- $1,172/UNIT Pronghorn Meadows F 2 & 3- $246.70/UNIT |
2/28/2022 2:36:59 PM | |
View |
EPC Environmental Services
2/28/2022 12:34:35 PM |
2/28/2022 12:34:35 PM | |
View |
El Paso County Conservation Dist
2/28/2022 10:36:21 AM |
2/28/2022 10:36:21 AM | |
Cherokee Metro Dist
2/28/2022 8:11:52 AM |
No Comment | 2/28/2022 8:11:52 AM | |
County Attorney - Water
2/24/2022 4:12:54 PM |
The County Attorney's Office will provide a written water review at the Preliminary Plan or Final Plat stage as necessary. Until then, the County Attorney’s Office would recommend a finding of insufficiency as to water quantity and dependability. Thank you. | 2/24/2022 4:12:54 PM |