View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
1/4/2022 5:29:18 PM |
Planning Division has no comments. | 1/4/2022 5:29:18 PM | |
View |
PCD Engineering Division
1/4/2022 5:03:16 PM |
(Drainage report redlines summary) | 1/4/2022 5:03:16 PM |
View |
PCD Engineering Division
1/4/2022 5:02:52 PM |
PCD-Engineering has the following comments: 1. The proposed concept appears to be acceptable; see attached report redlines for areas needing correction and clarification. 2. Note: A separate email will be provided with a link to reprinted DBPS exhibit pdfs. 3. Note: Stapleton-Briargate corridor plan documents are under final review; additional information will be provided by email. -- Jeff Rice - 719-520-7877 |
1/4/2022 5:02:52 PM |