Monument Junction West Fil No. 1 OAR
Description
plat east of I25, south of 105, access off of Jackson Creek REVIEW 2 OAR 21 123
Location
Parcels
7114400008 7114400008
Applicant
Town of Monument
Planner II Debbie Flynn ( dflynn@tomgov.org )
(719) 488-1604
Planner II Debbie Flynn ( dflynn@tomgov.org )
(719) 488-1604
File Number
OAR21108
Project Manager
Kari Parsons
Status
Closed
Created
10/25/2021 9:19:36 AM

View: Project Documents



Review Comments (2)

Link Agency Comment
PCD Project Manager
11/3/2021 10:38:32 AM
Please see engineering comments. Round a bout analysis was discussed for the adjacent property and was requested to be included in the TIS based on the County's ECM. Please provide the TIS for this site that includes the analysis. HWY 105 west of Jackson Creek Parkway is under CDOTS control although it remains unincorporated. Is Monument considering annexing HWY 105 from I25 to the east, if so what is the timing? 11/3/2021 10:38:32 AM
PCD Engineering Division
11/3/2021 10:27:54 AM
Please see comments provided by the County for Monument Junction Phase 1 PUD Plan (PCD File No. OAR2183) regarding the intersection of Jackson Creek Pkwy and Hwy 105. The Traffic Study for Phase 1 did not account for this Monument Junction West Filing 1 (OAR21108) project in determining impacts to the surrounding roadways. The Phase 1 PUD traffic study needs to be updated to incorporate this development in their traffic impact analysis.

The County request a copy of the traffic study and drainage report associated with this Monument Junction West Filing 1 to evaluate impacts to County infrastructure/properties in the vicinity of the project. The traffic impact study should analyze the long range horizon based on both Monument Junction West and Monument Junction Phase 1 development.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com