Digital Billboard Conversion Special Use
Description
May be administrative per LDC Sec. 6.2.9.B.3.c
Location
Parcels
7102200010 7102200010
Applicant
Outfront Media
Stephen Shinn ( stephen.shinn@outfront.com ) Stephen Shinn ( stephen.shinn@outfront.com )
EA Number
EA21183
File Number
AL2211
Project Manager
Remove Ashlyn Mathy
Status
Closed
Created
10/13/2021 9:00:55 AM

View: Project Documents



Review Comments (14)

Link Agency Comment
View EPC Health Department
7/22/2022 6:57:21 PM
7/22/2022 6:57:21 PM
PCD Engineering Division
7/21/2022 2:50:54 PM
Review 1 comments resolved. PCD Engineering has no further comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
7/21/2022 2:50:54 PM
Tri-Lakes-Monument Fire Protection District
6/28/2022 12:08:04 PM
No comments. JCB 6/28/2022 12:08:04 PM
View PCD Project Manager
6/23/2022 2:02:19 PM
light plan 6/23/2022 2:02:19 PM
View PCD Project Manager
6/23/2022 2:02:00 PM
site plan 6/23/2022 2:02:00 PM
Pikes Peak Regional Building Department
6/23/2022 9:19:40 AM
1. We do not have any comments regarding the special use aspect of this exhibit.
2. It appears based off of the recent bill from MVEA, the address for the existing sign is the same as the existing office building.

Thank you,

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
6/23/2022 9:19:40 AM
Woodmoor Water and Sanitation District
6/13/2022 3:31:07 PM
Woodmoor Water & Sanitation District owns and maintains a sanitary sewer pipeline in the vicinity of this project. The District requests a site utility and construction plan to ensure adequate clearances are met between existing sanitary sewer main and new construction work. 6/13/2022 3:31:07 PM
Mountain View Electric Association, Inc.
6/13/2022 1:56:58 PM
Mountain View Electric Association has no objection to the current plan. 6/13/2022 1:56:58 PM
View PCD Project Manager
6/10/2022 2:15:47 PM
see comments. 6/10/2022 2:15:47 PM
View PCD Project Manager
6/10/2022 2:15:26 PM
see engineer and project manager comments. 6/10/2022 2:15:26 PM
PCD Engineering Division
6/7/2022 4:28:33 PM
Review 1 comments will be uploaded by the project manager. Review comments on the following documents:

- Site Plan Drawing

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
6/7/2022 4:28:33 PM
PCD Project Manager
6/3/2022 7:57:16 AM
Per the conservation district:
"The El Paso County Conservation District Board of Supervisors recommendations are as follows; if the ground is disturbed it should be mulched or revegetated within 45 days of disturbance."
-they attached a document about various native grasses that can be planted
-they suggested a weed management plan and that it is reviewed by the EPC Weed advisory board
-contact epcdistrict@yahoo.com for any questions or concerns
6/3/2022 7:57:16 AM
View El Paso County Conservation Dist
6/2/2022 7:43:29 PM
EPCCD grass seed native shotgun mix added as .jpg. 6/2/2022 7:43:29 PM
View El Paso County Conservation Dist
6/2/2022 7:39:21 PM
EPCCD brief comments added as a .docx. 6/2/2022 7:39:21 PM