Project Review Comments

Back to List


Project Name
Black Hills Energy - Hwy 94 Enoch Rd - Mayberry
Description
Black Hills is going to install 32,000’ of 6” steel from Enoch Road to Ellicott in a Black Hills easement. Subject to 1041 determination - if 1041 does not apply, then this project will be allowed to proceed.
Location
Applicant
Black Hills Energy
Santiago Tijerina ( Santiago.Tijerina@blackhillscorp.com ) Santiago Tijerina ( Santiago.Tijerina@blackhillscorp.com )
File Number
CDR2117
Project Manager
Ryan Howser
Status
Closed
Created
9/1/2021 1:44:44 PM

View: Project Documents



Review Comments (21)

Link Agency Comment
View Colorado Department of Transportation - Pueblo Office
1/13/2022 1:00:05 PM
1/13/2022 1:00:05 PM
PCD Project Manager
12/28/2021 4:46:47 PM
No comments at this time. Approved engineering documents will be uploaded when they are approved by the ECM Administrator. 12/28/2021 4:46:47 PM
EPC Stormwater Review
12/27/2021 11:16:28 AM
Review 2: EPC Stormwater comments have been resolved on the following documents:
- ESQCP
- FAE
- GEC Plan
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
12/27/2021 11:16:28 AM
PCD Engineering Division
12/15/2021 8:25:03 AM
PCD Engineering has no further comments regarding drainage or transportation. Any approved documents will be uploaded by the project manager.


Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
12/15/2021 8:25:03 AM
Colorado Department of Transportation - Pueblo Office
12/2/2021 9:52:48 AM
CDOT staff comments are as follows.
Hydraulics:
-Missing SWMP items: total disturbance, soils, areas of seeding and blanket
-How are the windrow locations quantified?
-Identify outlets for windrow locations
-Silt fence in the floodplain is recommended to be reinforced
-LOC should include all silt fence, staging areas and VTC

Utilities:
-Work within CDOT right-of-way.
-This work will require a utility permit through CDOT-Utilities, Todd Ausbun, todd.ausbun@state.co.us or (719)696-1403.
12/2/2021 9:52:48 AM
RBD Floodplain
11/29/2021 11:42:19 AM
We have no comment or permit requirements for boring under floodplain areas as long as no permanent grading modifications or structures are installed in the SFHA. 11/29/2021 11:42:19 AM
View PCD Project Manager
11/24/2021 10:00:15 AM
PCD Engineering comments - letter of intent 11/24/2021 10:00:15 AM
View PCD Project Manager
11/24/2021 9:59:54 AM
PCD Engineering & EPC Stormwater comments - grading & erosion control plan 11/24/2021 9:59:54 AM
View PCD Project Manager
11/24/2021 9:59:22 AM
EPC Stormwater comments - financial assurance form 11/24/2021 9:59:22 AM
View PCD Project Manager
11/24/2021 9:58:56 AM
EPC Stormwater comments - ESQCP 11/24/2021 9:58:56 AM
View PCD Project Manager
11/24/2021 9:58:40 AM
PCD Engineering comments - construction drawings 11/24/2021 9:58:40 AM
PCD Engineering Division
11/23/2021 11:38:14 AM
Review 1 comments will be uploaded by the project manager. Review comments on the following documents:

- Letter of Intent
- GEC Plan
- Construction Drawings


Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
11/23/2021 11:38:14 AM
View EPC Stormwater Review
11/15/2021 6:26:39 PM
SWMP Checklist 11/15/2021 6:26:39 PM
View EPC Stormwater Review
11/15/2021 6:26:19 PM
SWMP 11/15/2021 6:26:19 PM
View EPC Stormwater Review
11/15/2021 6:25:33 PM
PBMP Applicability Form 11/15/2021 6:25:33 PM
View EPC Stormwater Review
11/15/2021 6:25:19 PM
GEC Checklist 11/15/2021 6:25:19 PM
EPC Stormwater Review
11/15/2021 6:24:35 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- ESQCP...................(to be uploaded by PM with PCD comments)
- FAE.......................(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
11/15/2021 6:24:35 PM
Ellicott Fire Protection District
11/15/2021 1:09:57 PM
There are no current issues/objections with this project, we will contact the developer directly for fees. 11/15/2021 1:09:57 PM
View El Paso County Conservation Dist
11/9/2021 11:23:42 AM
11/9/2021 11:23:42 AM
View El Paso County Conservation Dist
11/9/2021 11:23:28 AM
11/9/2021 11:23:28 AM
Upper Black Squirrel Creek GWMD
11/3/2021 11:14:52 AM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment in the future if necessary. 11/3/2021 11:14:52 AM