Project Review Comments

Back to List


Project Name
El Paso County School District 49 Transportation Center
Description
Transportation Center Development
Location
Parcels
4307300006 4307300006
Applicant
RTA Architects
Brian Calhoun ( brian@rtaarchitects.com )
(719) 471-7566 x7006
Brian Calhoun ( brian@rtaarchitects.com )
(719) 471-7566 x7006
EA Number
EA21133
File Number
PPR2236
Project Manager
Ryan Howser
Status
Closed
Created
8/17/2021 1:40:32 PM

View: Project Documents



Review Comments (66)

Link Agency Comment
EPC Stormwater Review
5/3/2023 7:51:58 AM
All stormwater comments have been addressed. 5/3/2023 7:51:58 AM
PCD Project Manager
4/27/2023 1:05:14 PM
Planning Division has no comments. 4/27/2023 1:05:14 PM
PCD Engineering Division
4/24/2023 10:30:39 AM
Review #6: Engineering comments are resolved. Documents are forwarded to the Deputy County Engineer for approval of the Final Drainage Report. Approved report and documents accepted for file will be uploaded by the project manager.
- Final Drainage Report
- Construction Drawings (To be accepted for file only. Project is under the School's MS4 permit)
- Financial Assurance Estimate Form (No longer applicable. Project is under the School's MS4 permit)
- Traffic Impact Study (Applicant is coordinating with the City of Colorado Springs regarding offsite improvements)


Reviewed By:
Gilbert LaForce
gilbertlaforce@elpasoco.com
4/24/2023 10:30:39 AM
View EPC Stormwater Review
3/9/2023 4:10:38 PM
Drainage Report_v5 3/9/2023 4:10:38 PM
View EPC Stormwater Review
3/9/2023 3:55:58 PM
CD_v5 3/9/2023 3:55:58 PM
View EPC Stormwater Review
3/9/2023 3:45:16 PM
PBMP_v5 3/9/2023 3:45:16 PM
EPC Stormwater Review
3/9/2023 3:51:36 PM
Review 5: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CDs.........................(uploaded with PCD comments)
- Drainage Report.....(uploaded with PCD comments)
- PBMP Applicability Form

Please provide the following documents upon resubmittal:
- O&M Plan for Grass Buffers (for Runoff Reduction)

The following documents will be reviewed during the next review cycle, once comments regarding WQ treatment are addressed on the Drainage Report:
- SDI Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
3/9/2023 3:51:36 PM
View PCD Engineering Division
3/7/2023 10:45:25 AM
Review #5: Financial Assurance Estimate 3/7/2023 10:45:25 AM
View PCD Engineering Division
3/7/2023 10:41:36 AM
Review #5: Traffic Impact Study 3/7/2023 10:41:36 AM
View PCD Engineering Division
3/7/2023 10:40:06 AM
Review #5: Site Plan 3/7/2023 10:40:06 AM
PCD Engineering Division
3/7/2023 10:39:30 AM
Review #5: Redline comments to the following documents will be uploaded by the project manager will upload comments.
- Final Drainage Report
- Site Plan
- Traffic Impact Study (Note: address redline comments that were uploaded in August 10, 2022.)
- Construction Drawings
- Financial Assurance Estimate Form (Note: The FAE was previously approved to expedite issuance of the ESQCP permit for early grading only. Now that the rest of the documents have been submitted for review, the FAE must be updated to include the other items outside of the early grading permit. See redline comments for missing items).
- Grading and Erosion Control Plan (Note: Update the approved GEC plans to reflect any changes based on comments to the other documents. Revisions needs to be identified with revision cloud and delta symbol).

Contact the review engineer if you have any questions regarding the comments provided. I am also available to schedule a meeting to discuss the comments.

Reviewed By:
Gilbert LaForce
gilbertlaforce@elpasoco.com
3/7/2023 10:39:30 AM
PCD Project Manager
2/17/2023 5:09:37 PM
Planning Division has no further comments. 2/17/2023 5:09:37 PM
View County Attorney - Development Review
1/10/2023 2:19:10 PM
Signature to Detention Maintenance Agreement attached. 1/10/2023 2:19:10 PM
PCD Project Manager
1/5/2023 8:42:35 AM
Planning Division has no further comments at this time. Please address PCD Engineering comments. 1/5/2023 8:42:35 AM
PCD Engineering Division
1/4/2023 9:18:56 AM
Review #4: The following documents have been forwarded to the Engineering Manager for approval. The documents will be uploaded by the project manager after approval.
- Early Grading and Erosion Control (GEC) plan
- SWMP
- SWMP & GEC Checklist
- Financial Assurance Estimate
- ESQCP

NOTE: A condition of approval have been added to the plans limiting the work allowed to earthwork operations only until the final drainage report and construction plans are approved.

List of documents still under review. See review #2 comments:
- Final Drainage Report
- Construction Drawings
- Financial Assurance Estimate (The approved FAE was limited to the early grading GEC plans and will need to be updated to include all GEC and public improvements associated associated with the project)
- Site Development Plan
- Traffic Impact Study
- SDI worksheet
- MS4 Post Construction Form
- O&M Manual
- PBMP Applicability Form
- Private Detention Pond Agreement

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
1/4/2023 9:18:56 AM
EPC Stormwater Review
12/19/2022 3:33:57 PM
Review 4: All Stormwater comments have been addressed for Early Grading Conditional Approval only.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
12/19/2022 3:33:57 PM
View EPC Stormwater Review
12/6/2022 6:27:20 PM
SWMP Checklist_v3 12/6/2022 6:27:20 PM
View EPC Stormwater Review
12/6/2022 6:26:41 PM
SWMP_v3 12/6/2022 6:26:41 PM
View EPC Stormwater Review
12/7/2022 11:17:30 AM
FAE_v3 12/7/2022 11:17:30 AM
View EPC Stormwater Review
12/6/2022 6:25:24 PM
GEC Checklist_v3 12/6/2022 6:25:24 PM
EPC Stormwater Review
12/7/2022 11:18:49 AM
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents (for Early Grading Conditional Approval only):
- CDs.........................(to be uploaded by PM with PCD comments)
- GEC Checklist
- FAE
- SWMP
- SWMP Checklist

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
12/7/2022 11:18:49 AM
View PCD Engineering Division
12/7/2022 11:14:56 AM
Review #3. Attached are the redline comments to the Construction Drawings.

* Submit Financial Assurance Estimate for Section 1 improvements associated with the early grading.

REMINDER: As noted on the comments and during the August 25 meeting, the approval of the early grading and erosion control plan is limited to earthwork operations only for rough grading. Construction/installation of permanent infrastructure such as storm sewers, and permanent detention pond features (forebay, trickle channel and outlet structures) is not permitted until the associated site plan, final drainage report, construction drawings, and final drainage report has been approved.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
12/7/2022 11:14:56 AM
View PCD Project Manager
10/28/2022 7:14:03 AM
PCD Engineering comments - SDP 10/28/2022 7:14:03 AM
View PCD Project Manager
10/28/2022 7:13:44 AM
PCD Engineering comments - Landscape plan 10/28/2022 7:13:44 AM
View PCD Project Manager
10/28/2022 7:13:23 AM
PCD Engineering and EPC Stormwater comments - FAE 10/28/2022 7:13:23 AM
View PCD Project Manager
10/27/2022 4:55:48 PM
Comment summary - FDR 10/27/2022 4:55:48 PM
View PCD Project Manager
10/27/2022 4:55:16 PM
PCD Engineering and EPC Stormwater comments - FDR 10/27/2022 4:55:16 PM
View PCD Project Manager
10/27/2022 4:54:51 PM
Comment summary - CDs 10/27/2022 4:54:51 PM
View PCD Project Manager
10/27/2022 4:54:35 PM
PCD Engineering and EPC Stormwater comments - CDs 10/27/2022 4:54:35 PM
EPC Stormwater Review
10/27/2022 2:29:46 PM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CDs.........................(to be uploaded by PM with PCD comments)
- Drainage Report.....(to be uploaded by PM with PCD comments)
- FAE.........................(to be uploaded by PM with PCD comments)

Please upload the following revised documents for review:
- SWMP

The following documents will be reviewed during the next review cycle, once comments regarding WQ treatment are addressed on the Drainage Report:
- MS4 Post Construction Form
- O&M Manual
- PBMP Applicability Form
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement
- SDI Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
10/27/2022 2:29:46 PM
PCD Engineering Division
10/25/2022 5:51:55 PM
Review #2.
Redline comments on the following documents will be uploaded by the project manager:
* Traffic Impact Study (Review #1 comments are unresolved)
* Landscape Plans
* Site Development Plan
* Drainage Report
* Financial Assurance Estimate
* Construction Drawings.

Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
10/25/2022 5:51:55 PM
View County Attorney - Development Review
10/20/2022 11:44:52 AM
Minor edits to Detention Maintenance Agreement attached. 10/20/2022 11:44:52 AM
View EPC Health Department
9/7/2022 8:54:57 PM
9/7/2022 8:54:57 PM
Falcon Fire Protection District
8/19/2022 9:57:25 AM
Falcon Fire has worked directly with D49 on this project and has approved the development plan as proposed. 8/19/2022 9:57:25 AM
View PCD Project Manager
8/10/2022 4:44:53 PM
Traffic Impact Study_5-9-22 redlines 8/10/2022 4:44:53 PM
View PCD Project Manager
8/10/2022 4:44:03 PM
SWMP Plan_V1 redlines 8/10/2022 4:44:03 PM
View PCD Project Manager
8/10/2022 4:43:36 PM
SWMP Checklist_V1 redlines 8/10/2022 4:43:36 PM
View PCD Project Manager
8/10/2022 4:43:11 PM
Site Development Plan_V1 redlines 8/10/2022 4:43:11 PM
View PCD Project Manager
8/10/2022 4:42:43 PM
Sign Plan_V1 redlines 8/10/2022 4:42:43 PM
View PCD Project Manager
8/10/2022 4:42:20 PM
Lighting Plan_V1 redlines 8/10/2022 4:42:20 PM
View PCD Project Manager
8/10/2022 4:41:56 PM
Letter of Intent_V1 redlines 8/10/2022 4:41:56 PM
View PCD Project Manager
8/10/2022 4:41:29 PM
Landscape Plan Drawings_V1 redlines 8/10/2022 4:41:29 PM
View PCD Project Manager
8/10/2022 4:40:52 PM
Grading and Erosion Control Plan_V1 redlines 8/10/2022 4:40:52 PM
View PCD Project Manager
8/10/2022 4:40:14 PM
Grading and Erosion Control Checklist_V1 8/10/2022 4:40:14 PM
View PCD Project Manager
8/10/2022 4:39:54 PM
Floor Plans_V1 redlines 8/10/2022 4:39:54 PM
View PCD Project Manager
8/10/2022 4:39:27 PM
Financial Assurance Forms_V1 redlines 8/10/2022 4:39:27 PM
View PCD Project Manager
8/10/2022 4:39:01 PM
Erosion and Stormwater Quality Control Permit_V1 redlines 8/10/2022 4:39:01 PM
View PCD Project Manager
8/10/2022 4:32:36 PM
Drainage Report Final_V1 redlines 8/10/2022 4:32:36 PM
View PCD Project Manager
8/10/2022 4:31:36 PM
Construction Drawings Plans-Profiles_V1 redlines 8/10/2022 4:31:36 PM
View PCD Project Manager
8/10/2022 4:29:58 PM
Application Petition Form_V1 redlines 8/10/2022 4:29:58 PM
View EPC Stormwater Review
8/9/2022 3:38:21 PM
GEC Checklist_v1 8/9/2022 3:38:21 PM
View EPC Stormwater Review
8/9/2022 3:37:50 PM
SWMP Checklist_v1 8/9/2022 3:37:50 PM
View EPC Stormwater Review
8/9/2022 3:37:18 PM
SWMP_v1 8/9/2022 3:37:18 PM
View EPC Stormwater Review
8/9/2022 3:36:51 PM
ESQCP_v1 8/9/2022 3:36:51 PM
View EPC Stormwater Review
8/9/2022 3:36:22 PM
FAE_v1 8/9/2022 3:36:22 PM
View Mountain View Electric Association, Inc.
8/8/2022 3:47:34 PM
See attached comments 8/8/2022 3:47:34 PM
PCD Engineering Division
8/10/2022 11:14:48 AM
Review #1. Due to the quantity and nature of comments provided the resubmittal will be treated as a first review with new comments.

Redline comments on the following documents will be uploaded by the project manager:
- Traffic Impact Study
- Landscape Plans
- Site Development Plan
- Grading and Erosion Control Plan
- Drainage Report
- Financial Assurance Estimate
- Construction Drawings.


Reviewed by:
Gilbert LaForce, PE
gilbertlaforce@elpasoco.com
8/10/2022 11:14:48 AM
Pikes Peak Regional Building Department
8/8/2022 9:10:05 AM
Regarding a request for approval of a development plan for a transportation center for School District 49, Enumerations has the following comments:

1. The address of 11971 Swingline Rd., as it appears on this development plan is correct, and should be used when submitting building plans for review/permit. If there are ever any future buildings to be constructed on this site, Enumerations does not have jurisdiction to assign additional addresses to these future buildings except at applicants request. Enumerations recommends that for emergency response purposes, any future buildings have separate addresses assigned. If the school district so desires, Enumerations is happy to assign any needed addresses.
8/8/2022 9:10:05 AM
EPC Stormwater Review
8/9/2022 3:34:36 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CDs........................(to be uploaded by PM with PCD comments)
- Drainage Report...(to be uploaded by PM with PCD comments)
- FAE
- ESQCP
- SWMP
- SWMP Checklist
- GEC Checklist

The following documents will be reviewed during the next review cycle, once comments regarding WQ treatment are addressed on the Drainage Report:
- MS4 Post Construction Form
- O&M Manual
- PBMP Applicability Form
- Private Detention Basin / Stormwater Quality BMP Maintenance Agreement
- SDI Form

Due to the volume or complexity of the comments provided, these comments are cursory in nature and EPC Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
8/9/2022 3:34:36 PM
View County Attorney - Development Review
8/4/2022 11:21:00 AM
Formatting on Detention Maintenance Agreement was problematic. I redid the agreement. Please review and advise if there are any proposed changes. Please complete D49 signature block and add exhibit. 8/4/2022 11:21:00 AM
View EPC Environmental Services
8/3/2022 3:00:47 PM
8/3/2022 3:00:47 PM
Upper Black Squirrel Creek GWMD
8/2/2022 7:50:59 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. 8/2/2022 7:50:59 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/27/2022 9:00:34 AM
If you have any queries about gas services, please contact Springs Utilities' field engineering. 719-668-4985.

Corey Masoumi - cmasoumi@csu.org
7/27/2022 9:00:34 AM
View EPC Parks Department
7/20/2022 1:57:32 PM
See final Parks comments attached.

Thanks,

Greg Stachon
Landscape Architect
El Paso County Parks
7/20/2022 1:57:32 PM
View El Paso County Conservation Dist
7/19/2022 9:24:52 PM
Native grass seed mix information submitted as .jpg 7/19/2022 9:24:52 PM
View El Paso County Conservation Dist
7/19/2022 9:24:33 PM
EPCCD brief comments attached as .docx 7/19/2022 9:24:33 PM